ENS 51178
From kanterella
Jump to navigation
Jump to search
ENS Event | |
---|---|
15:45 Jun 16, 2015 | |
Title | Unanalyzed Condition Due to Open High Energy Line Break Doors |
Event Description | On June 16, 2015 at 1145 EDT while in Mode 1 at 100% power steady-state conditions, two fire doors between the Reactor Auxiliary building (RAB) and steam tunnel were opened under administrative controls to support maintenance. These doors are credited in high energy line break equipment qualification and internal flooding analyses and opening of the doors is not addressed in the analyses. A high energy line break in the steam tunnel with the doors open could result in equipment in the RAB experiencing high temperature, pressure, or humidity beyond conditions analyzed for equipment qualification which has the potential to render redundant safety-related equipment inoperable.
The event was determined to be reportable on June 24, 2015 at approximately 1550 [EDT]. During that reportability evaluation, it was determined that the doors may have been in a similar condition multiple times in the May-June time frame. This condition is reportable in accordance with 10 CFR 50.72(b)(3)(ii)(B) as an unanalyzed condition and in accordance with 10 CFR 50.72(b)(3)(v)(D) as a condition that could have prevented the fulfillment of the safety function of structures or system that are needed to mitigate the consequences of an accident. There was no adverse impact to public health and safety or to plant employees. The NRC Resident Inspector has been notified. |
Where | |
---|---|
Harris North Carolina (NRC Region 2) | |
Reporting | |
10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition 10 CFR 50.72(b)(3)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident | |
Time - Person (Reporting Time:+195.73 h8.155 days <br />1.165 weeks <br />0.268 months <br />) | |
Opened: | Raymond Moore 19:29 Jun 24, 2015 |
NRC Officer: | Daniel Mills |
Last Updated: | Jun 24, 2015 |
51178 - NRC Website
Loading map... {"minzoom":false,"maxzoom":false,"mappingservice":"leaflet","width":"350px","height":"250px","centre":false,"title":"","label":"","icon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"zoom":6,"defzoom":14,"layers":["OpenStreetMap"],"image layers":[],"overlays":[],"resizable":false,"fullscreen":false,"scrollwheelzoom":true,"cluster":false,"clustermaxzoom":20,"clusterzoomonclick":true,"clustermaxradius":80,"clusterspiderfy":true,"geojson":"","clicktarget":"","imageLayers":[],"locations":[{"text":"\u003Cb\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003E\u003Ca class=\"mw-selflink selflink\"\u003EENS 51178\u003C/a\u003E - \u003Ca href=\"/Harris\" title=\"Harris\"\u003EHarris\u003C/a\u003E\n\u003C/p\u003E\u003C/div\u003E\u003C/b\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003EUnanalyzed Condition Due to Open High Energy Line Break Doors\n\u003C/p\u003E\u003C/div\u003E","title":"ENS 51178 - Harris\n","link":"","lat":35.63344166666667,"lon":-78.95586666666667,"icon":"/w/images/7/75/Duke_Energy_icon.png"}],"imageoverlays":null} | |
Unit 1 | |
---|---|
Reactor critical | Critical |
Scram | No |
Before | Power Operation (100 %) |
After | Power Operation (100 %) |