In accordance with
10CFR50.73(a)(2(iv)(A), this telephone notification reports an invalid actuation of the Unit 1 train A (1A)
Emergency Diesel Generator (
DG) on October 1, 2012, at
1403 hours0.0162 days <br />0.39 hours <br />0.00232 weeks <br />5.338415e-4 months <br />. At the time of the event Unit 1 was in Mode 5, Cold Shutdown. The 1A
DG was undergoing a surveillance procedure that verifies a safety injection override signal when a technician actuated the incorrect under voltage relay which resulted in the inadvertent start of the 1A
DG. The engine functioned successfully and ran unloaded, as expected. The cause is attributed to the technicians failing to verify they were actuating the correct relay. This condition was entered into the corrective action program.
The licensee notified the NRC Resident Inspector and the
Illinois Department of Nuclear Safety.