| Title | Fire Barrier Rating of Vital Swtichgear Walls May Not Meet Standards |
| Event Description | On December 31, 2011 at 0200 PST, a plant employee indentified the fire barrier material in each unit was potentially not qualified as a 3 hour3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> rated fire barrier as specified by the Diablo Canyon power plant fire protection program. The fire barrier material in question is installed between the block wall portion of the barrier and the door frames in the walls separating three of the 480 Volt switchgear buses and separating the three vital instrument AC inverters. The condition was discovered by a plant employee who questioned the configuration while performing a routine tour of that area. Operators confirmed existing fire watches were in place and established additional fire watches as compensatory measures as required by the Diablo Canyon fire protection program.
A review of the Appendix R fire protection analysis is in progress to confirm the rating of the installed configuration. The licensee has notified the NRC Resident Inspector.
This is an update to EN 47564 reported on 12/31/11 where it was reported that plant personnel had identified rated fire barriers were not qualified as a three hour rated barrier as required by the DCPP Fire Protection Program. On 1/3/12 plant personnel provided barrier design drawings to the manufacturer of the DCPP fireproofing material. The manufacturer reviewed the design detail and confirmed that the barrier design depicted on the drawing is qualified as a 3 hour3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> barrier. Therefore no unanalyzed condition that significantly degraded plant safety existed. This event is being retracted. The licensee notified the NRC Resident Inspector. Notified R4DO (Vasquez). |
| Where | |
|---|---|
| Diablo Canyon California (NRC Region 4) | |
| Reporting | |
| 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition | |
| Time - Person (Reporting Time:+1.88 h0.0783 days <br />0.0112 weeks <br />0.00258 months <br />) | |
| Opened: | Michael Kennedy 11:53 Dec 31, 2011 |
| NRC Officer: | Bill Huffman |
| Last Updated: | Jan 4, 2012 |
| 47564 - NRC Website
Loading map... | |
Unit 1 | |
|---|---|
| Reactor critical | Critical |
| Scram | No |
| Before | Power Operation (100 %) |
| After | Power Operation (100 %) |
Unit 2 | |
|---|---|
| Reactor critical | Critical |
| Scram | No |
| Before | Power Operation (100 %) |
| After | Power Operation (100 %) |
WEEKMONTHYEARENS 544172019-11-30T19:00:00030 November 2019 19:00:00
[Table view]10 CFR 50.72(b)(3)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident, 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Both Trains of Containment Spray Removed from Service ENS 522602016-09-21T03:47:00021 September 2016 03:47:00 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Steam Line Pipe Whip Restraint Coupling Sleeve Found Not Engaged ENS 503342014-08-01T00:29:0001 August 2014 00:29:00 10 CFR 50.72(b)(3)(v)(A), Loss of Safety Function - Shutdown the Reactor, 10 CFR 50.72(b)(3)(v)(B), Loss of Safety Function - Remove Residual Heat, 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition, 10 CFR 50.72(b)(3)(v)(C), Loss of Safety Function - Release of Radioactive Material Unanalyzed Condition ENS 498792014-03-06T17:06:0006 March 2014 17:06:00 10 CFR 50.72(b)(3)(v)(A), Loss of Safety Function - Shutdown the Reactor, 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Unanalyzed Condition Regarding Potential Tornado Missile Damage to Emergency Diesel Exhaust Plenum ENS 496632013-12-19T15:52:00019 December 2013 15:52:00 10 CFR 50.72(b)(3)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident, 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Two of Three Emergencey Diesel Generators Inoperable at the Same Time ENS 496342013-12-14T23:03:00014 December 2013 23:03:00 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Unanalyzed Condition Affecting Unit 1 Emergency Diesel Generator ENS 491482013-06-26T04:58:00026 June 2013 04:58:00 10 CFR 50.72(b)(2)(xi), Notification to Government Agency or News Release, 10 CFR 50.72(b)(3)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident, 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition, 10 CFR 50.72(b)(2)(i), Tech Spec Required Shutdown Plant Shutdown Required Due to Rhr System Socket Weld Leak ENS 491472013-06-24T23:15:00024 June 2013 23:15:00 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Emergency Diesel Generators Unavailable for Auto-Start ENS 487262013-02-06T23:24:0006 February 2013 23:24:00 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Unanalyzed Condition for Control Room Ventilation ENS 483952012-10-04T01:15:0004 October 2012 01:15:00 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Unanalyzed Fire Protection Deficiencies ENS 482462012-08-29T00:00:00029 August 2012 00:00:00 10 CFR 50.72(b)(3)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident, 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Mitigating Actions Implemented for Inoperable Control Room Envelope ENS 475642011-12-31T10:00:00031 December 2011 10:00:00 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Fire Barrier Rating of Vital Swtichgear Walls May Not Meet Standards ENS 474142011-11-03T22:50:0003 November 2011 22:50:00 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Unanalyzed Condition - Control Room Ventilation Single Point Vulnerability ENS 472582011-09-13T00:45:00013 September 2011 00:45:00 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Control Room Envelope Declared Inoperable ENS 472232011-08-30T00:24:00030 August 2011 00:24:00 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Maintenance Inadvertently Renders Control Room Ventilation System Inoperable ENS 465312011-01-10T21:21:00010 January 2011 21:21:00 10 CFR 50.72(b)(3)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident, 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Both Trains of Auxiliary Building Ventilation Became Inoperable ENS 457542010-03-10T03:16:00010 March 2010 03:16:00 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Potential Loss of 1E Pumps Due to Degraded Voltage During Postulated Accidents ENS 454612009-10-23T15:00:00023 October 2009 15:00:00 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Post Loca Recirculation Valve Position Interlocks ENS 449272009-03-22T20:34:00022 March 2009 20:34:00 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition Unit 1 Steam Generator Found in an Unanalyzed Condition Related to Gaps on Seismic Washer Plates 2019-11-30T19:00:00 | |