MONTHYEARDCL-20-047, 10 CFR Part 21 Notification: Inadequate Dedication of Replacement Thermocouples2020-06-16016 June 2020 10 CFR Part 21 Notification: Inadequate Dedication of Replacement Thermocouples ML17081A4532017-03-20020 March 2017 Part 21 - Plastic Jar Dedication Sampling ML15188A0662015-06-25025 June 2015 Part 21 Report - Deviation in Nozzle Modeling Internal Reports ML14125A2702014-05-0202 May 2014 Missing Jam Nuts on Size 4, Pressure Class 600 Normally Open, In-Line Check Valve Per Flowserve Drawing No. 07-45546-01 ML13165A3422013-06-12012 June 2013 60-Day Interim Report Involving an Evaluation of a Design Change to Magne-Blast Circuit Breakers ML12094A3712012-04-0202 April 2012 Part 21 Report - Rosemount Pressure Transmitters with Nonzero Based Calibrations ML12097A3162012-03-0202 March 2012 Part 21 Report - Rosemont Pressure Tranmitters Out of Tolerance Condition ML12066A1182012-03-0202 March 2012 Part 21 Report - Rosemount Pressure Transmitters with Nonzero Based Calibrations 2020-06-16
[Table view] Category:Letter type:DCL
MONTHYEARDCL-24-010, Nuclear Material Transaction Report for New Fuel2024-01-29029 January 2024 Nuclear Material Transaction Report for New Fuel DCL-24-009, Nuclear Material Transaction Report for New Fuel2024-01-17017 January 2024 Nuclear Material Transaction Report for New Fuel DCL-24-008, Schedule Considerations for Review of the DCPP License Renewal Application2024-01-17017 January 2024 Schedule Considerations for Review of the DCPP License Renewal Application DCL-24-004, Supplement to License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2024-01-15015 January 2024 Supplement to License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b DCL-23-129, Nuclear Material Transaction Report for New Fuel2023-12-27027 December 2023 Nuclear Material Transaction Report for New Fuel DCL-23-122, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-14014 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation DCL-23-128, Emergency Plan Update2023-12-13013 December 2023 Emergency Plan Update DCL-23-125, Core Operating Limits Report for Unit 1 Cycle 252023-12-0606 December 2023 Core Operating Limits Report for Unit 1 Cycle 25 DCL-23-121, Supplement to License Amendment Request 23-03, Revision to Technical Specification3.7.8, Auxiliary Saltwater System2023-11-16016 November 2023 Supplement to License Amendment Request 23-03, Revision to Technical Specification3.7.8, Auxiliary Saltwater System DCL-23-120, License Amendment Request 23-03 Revision to Technical Specification 3.7.8, Auxiliary Saltwater (Asw) System2023-11-14014 November 2023 License Amendment Request 23-03 Revision to Technical Specification 3.7.8, Auxiliary Saltwater (Asw) System DCL-23-118, License Renewal Application2023-11-0707 November 2023 License Renewal Application DCL-2023-520, Discharge Self-Monitoring at Diablo Canyon Power Plant (DCPP)2023-10-19019 October 2023 Discharge Self-Monitoring at Diablo Canyon Power Plant (DCPP) DCL-23-103, Independent Spent Fuel Storage Installation - Withdrawal of License Amendment Request 22-01, Request for Approval of Alternative Security Measures for Early Warning System2023-10-13013 October 2023 Independent Spent Fuel Storage Installation - Withdrawal of License Amendment Request 22-01, Request for Approval of Alternative Security Measures for Early Warning System DCL-23-092, Material Status Report for the Period Ending August 31, 20232023-09-28028 September 2023 Material Status Report for the Period Ending August 31, 2023 DCL-23-077, License Amendment Request 23-02 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors2023-09-27027 September 2023 License Amendment Request 23-02 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors DCL-23-083, Upcoming Meeting with Nuclear Security and Incident Response Staff2023-09-13013 September 2023 Upcoming Meeting with Nuclear Security and Incident Response Staff DCL-23-078, Nuclear Material Transaction Report for New Fuel2023-09-0606 September 2023 Nuclear Material Transaction Report for New Fuel DCL-23-070, Withdrawal of Request Regarding Senior Reactor Operator License Application2023-08-16016 August 2023 Withdrawal of Request Regarding Senior Reactor Operator License Application DCL-23-068, Nuclear Material Transaction Report for New Fuel2023-08-0909 August 2023 Nuclear Material Transaction Report for New Fuel DCL-23-066, Nuclear Material Transaction Report for New Fuel2023-08-0303 August 2023 Nuclear Material Transaction Report for New Fuel DCL-23-065, Letter DCL-23-065 Request That Exam Material Be Withheld from Public Disclosure2023-07-27027 July 2023 Letter DCL-23-065 Request That Exam Material Be Withheld from Public Disclosure DCL-23-064, Nuclear Material Transaction Report for New Fuel2023-07-26026 July 2023 Nuclear Material Transaction Report for New Fuel DCL-23-054, License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2023-07-13013 July 2023 License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b DCL-23-055, Nuclear Material Transaction Report for New Fuel2023-07-0606 July 2023 Nuclear Material Transaction Report for New Fuel DCL-23-042, Independent Spent Fuel Storage Installation, Submittal of Quality Assurance Program Description, Revision 02023-05-24024 May 2023 Independent Spent Fuel Storage Installation, Submittal of Quality Assurance Program Description, Revision 0 DCL-23-032, Independent Spent Fuel Storage Installation Docket No. 72-27, Materials License Number SNM-2514 Humboldt Bay Independent Spent Fuel Storage Installation - NRC Requested Notification of Withdrawal from Voluntary Program2023-05-22022 May 2023 Independent Spent Fuel Storage Installation Docket No. 72-27, Materials License Number SNM-2514 Humboldt Bay Independent Spent Fuel Storage Installation - NRC Requested Notification of Withdrawal from Voluntary Program DCL-23-041, 10 CFR 50.46 Annual Report of Emergency Core Cooling System Evaluation Model Changes for Peak Cladding Temperature for 20222023-05-22022 May 2023 10 CFR 50.46 Annual Report of Emergency Core Cooling System Evaluation Model Changes for Peak Cladding Temperature for 2022 DCL-23-038, Revision to the Unit 1 Reactor Vessel Material Surveillance Program Withdrawal Schedule2023-05-15015 May 2023 Revision to the Unit 1 Reactor Vessel Material Surveillance Program Withdrawal Schedule DCL-23-034, 2022 Annual Nonradiological Environmental Operating Report2023-05-0101 May 2023 2022 Annual Nonradiological Environmental Operating Report DCL-23-036, 2022 Annual Radiological Environmental Operating Report2023-05-0101 May 2023 2022 Annual Radiological Environmental Operating Report DCL-23-025, 2022 Annual Radioactive Effluent Release Report2023-05-0101 May 2023 2022 Annual Radioactive Effluent Release Report DCL-2023-512, Submittal of Receiving Water Monitoring Program 2022 Annual Report2023-04-27027 April 2023 Submittal of Receiving Water Monitoring Program 2022 Annual Report DCL-23-035, Response to Request for Additional Information on Request Regarding Senior Reactor Operator License Application2023-04-24024 April 2023 Response to Request for Additional Information on Request Regarding Senior Reactor Operator License Application DCL-23-028, Technical Specification Bases, Revision 142023-04-24024 April 2023 Technical Specification Bases, Revision 14 DCL-2023-511, Report on Discharge Monitoring for the First Quarter of 20232023-04-20020 April 2023 Report on Discharge Monitoring for the First Quarter of 2023 DCL-23-031, Submittal of Annual Report of Occupational Radiation Exposure for 20222023-04-19019 April 2023 Submittal of Annual Report of Occupational Radiation Exposure for 2022 DCL-23-024, Independent Spent Fuel Storage Installation, Response to Nrg Request for Additional Information for Revision to License Amendment Request 22-01 Request for Approval of Alternative Security Measures for Early Warning System2023-04-0404 April 2023 Independent Spent Fuel Storage Installation, Response to Nrg Request for Additional Information for Revision to License Amendment Request 22-01 Request for Approval of Alternative Security Measures for Early Warning System DCL-23-022, 2023 Annual Statement of Insurance for Pacific Gas and Electric Companys Diablo Canyon Power Plant2023-03-29029 March 2023 2023 Annual Statement of Insurance for Pacific Gas and Electric Companys Diablo Canyon Power Plant DCL-23-023, Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 and 22023-03-28028 March 2023 Decommissioning Funding Report for Diablo Canyon Power Plant, Units 1 and 2 DCL-23-021, Independent Spent Fuel Storage Installation, Emergency Plan Update2023-03-23023 March 2023 Independent Spent Fuel Storage Installation, Emergency Plan Update DCL-23-020, Responses to NRC Questions Regarding License Renewal Efforts2023-03-17017 March 2023 Responses to NRC Questions Regarding License Renewal Efforts DCL-23-009, Owner'S Activity Report for Unit 2 Twenty-Third Refueling Outage2023-02-22022 February 2023 Owner'S Activity Report for Unit 2 Twenty-Third Refueling Outage DCL-23-008, Request Regarding Senior Reactor Operator License Application2023-02-22022 February 2023 Request Regarding Senior Reactor Operator License Application DCL-2023-503, Annual Sea Turtle Report2023-01-26026 January 2023 Annual Sea Turtle Report DCL-2023-502, (DCPP) 4th Quarter 2022 Report on Discharge Self-Monitoring2023-01-18018 January 2023 (DCPP) 4th Quarter 2022 Report on Discharge Self-Monitoring DCL-22-091, Revised Steam Generator Tube Inspection Report for Twenty-First Refueling Outage2022-12-20020 December 2022 Revised Steam Generator Tube Inspection Report for Twenty-First Refueling Outage DCL-22-089, Core Operating Limits Report for Unit 2 Cycle 242022-12-20020 December 2022 Core Operating Limits Report for Unit 2 Cycle 24 DCL-22-085, Request to Resume Review of the License Renewal Application or, Alternatively, for an Exemption from 10 CFR 2.109(b), Concerning a Timely Renewal Application2022-10-31031 October 2022 Request to Resume Review of the License Renewal Application or, Alternatively, for an Exemption from 10 CFR 2.109(b), Concerning a Timely Renewal Application DCL-22-041, Site-Specific Decommissioning Cost Estimate, Revision 12022-10-12012 October 2022 Site-Specific Decommissioning Cost Estimate, Revision 1 DCL-22-042, Post-Shutdown Decommissioning Activities Report, Revision 12022-10-12012 October 2022 Post-Shutdown Decommissioning Activities Report, Revision 1 2024-01-29
[Table view] |
Text
James M. Welsch Diablo Canyon Power Plant Senior Vice President P.O. Box 56 Generation and Avila Beach, CA 93424 Chief Nuclear Officer 805.545.3242 E-Mail: James.Welsch@pge.com June 16, 2020 PG&E Letter DCL-20-047 U.S. Nuclear Regulatory Commission 10 CFR 21.21 ATTN: Document Control Desk Washington, DC 20555-0001 Docket No. 50-275, OL-DPR-80 Docket No. 50-323, OL-DPR-82 Diablo Canyon Power Plant, Units 1 and 2 10 CFR Part 21 Notification: Inadequate Dedication of Replacement Thermocouples
Dear Commissioners and Staff,
In accordance with the requirements of 10 CFR 21.21 (d)(3)(ii), Pacific Gas and Electric Company (PG&E) hereby submits the enclosed Diablo Canyon Power Plant (DCPP) written notification of the identification of a defect. This information was initially reported to the Nuclear Regulatory Commission Operations Center on May 20, 2020 (Event Notification 54721). The information provided in the enclosed report meets the reporting requirements of 10 CFR 21.21 (d)(4).
PG&E makes no new or revised regulatory commitments (as defined by NEI 99-04) in this report. Corrective actions identified in this letter will be implemented in accordance with the DCPP Corrective Action Program.
This event did not adversely affect the health and safety of the public.
Sincerely,
/Maureen ZawaliFN for James Welsch James M. Welsch dqmg/51072190 Enclosure Cc/enc: Scott A. Morris, NRC Region IV Administrator Christopher W. Newport, NRC Senior Resident Inspector Balwant K. Singal, NRR Senior Project Manager INPO Diablo Distribution A member of the STARS Alliance Callaway x Diablo Canyon x Palo Verde x Wolf Creek
Enclosure PG&E Letter DCL-20-047 10 CFR PART 21 NOTIFICATION INADEQUATE DEDICATION OF REPLACEMENT THERMOCOUPLES
Enclosure PG&E Letter DCL-20-047 10 CFR Part 21 Notification Inadequate Dedication of Replacement Thermocouples The following information is provided pursuant to 10 CFR 21.21(d)(4).
- i. Name and address of the individual or individuals informing the Commission.
James M. Welsch Senior Vice President, Generation and Chief Nuclear Officer Diablo Canyon Power Plant Mail Code 104/6 P.O. Box 56 Avila Beach, CA 93424 ii. Identification of the facility, the activity, or the basic component supplied for such facility or such activity within the United States which fails to comply or contains a defect.
Facility: Diablo Canyon Power Plant (DCPP) Unit 1 and 2 Docket No. 50-275 and 50-323 License No. OL-DPR-80 and OL-DPR-82 Basic Component: Thermocouple, Bellofram Model 3060-2-JJ-2-13.00-0-1-000 iii. Identification of the firm constructing the facility or supplying the basic component which fails to comply or contains a defect.
Diablo Canyon Power Plant P.O. Box 56 Avila Beach, CA 93424 iv. Nature of the defect or failure to comply and the safety hazard which is created or could be created by such defect or failure to comply.
The original defect was discovered on April 10, 2020, during bench testing where two separate thermocouples exhibited leakage during static assembly. The two thermocouples were tested as part of a spare safety-related pump motor refurbishment. Upon subsequent review, it was identified that a pressure boundary test had not been required as part of the dedication process, but should have been for its safety-related application.
- v. The date on which the information of such defect or failure to comply was obtained.
Enclosure PG&E Letter DCL-20-047 On May 18, 2020, Pacific Gas and Electric (PG&E) completed its evaluation of a deviation concerning commercial-grade thermocouples dedicated at DCPP.
The reporting officer was informed on May 18, 2020. The defect was reported to the NRC telephonically on May 20, 2020 (Event Notification 54721).
vi. In the case of a basic component which contains a defect or fails to comply, the number and location of these components in use at, supplied for, being supplied for, or may be supplied for, manufactured, or being manufactured for one or more facilities or activities subject to the regulations in this part.
Components of the suspect batch were not installed in the plant and there was no risk to the health and safety of the public. Thermocouples from the same batch have been quarantined to prevent installation, and it has been confirmed that none of the suspect batch of thermocouples have been installed in the plant.
vii. The corrective action which has been, is being, or will be taken; the name of the individual or organization responsible for the action; and the length of time that has been or will be taken to complete the action.
This defect was documented in the DCPP corrective action program. The thermocouple replacement part evaluation has been revised to include a pressure boundary test as part of the commercial-grade dedication prior to acceptance.
viii. Any advice related to the defect or failure to comply about the facility, activity, or basic component that has been, is being, or will be given to purchasers or licensees.
None.
ix. In the case of an early site permit, the entities to whom an early site permit was transferred.
This event does not involve an early site permit.