MONTHYEARDCL-20-047, 10 CFR Part 21 Notification: Inadequate Dedication of Replacement Thermocouples2020-06-16016 June 2020 10 CFR Part 21 Notification: Inadequate Dedication of Replacement Thermocouples ML17081A4532017-03-20020 March 2017 Part 21 - Plastic Jar Dedication Sampling ML15188A0662015-06-25025 June 2015 Part 21 Report - Deviation in Nozzle Modeling Internal Reports ML14125A2702014-05-0202 May 2014 Missing Jam Nuts on Size 4, Pressure Class 600 Normally Open, In-Line Check Valve Per Flowserve Drawing No. 07-45546-01 ML13165A3422013-06-12012 June 2013 60-Day Interim Report Involving an Evaluation of a Design Change to Magne-Blast Circuit Breakers ML12094A3712012-04-0202 April 2012 Part 21 Report - Rosemount Pressure Transmitters with Nonzero Based Calibrations ML12097A3162012-03-0202 March 2012 Part 21 Report - Rosemont Pressure Tranmitters Out of Tolerance Condition ML12066A1182012-03-0202 March 2012 Part 21 Report - Rosemount Pressure Transmitters with Nonzero Based Calibrations 2020-06-16
[Table view] Category:Letter type:DCL
MONTHYEARDCL-24-103, Pg&Es Voluntary Submittal of Information Related to 10 CFR 2.206 Petition Regarding Seismic Core Damage Frequency for DCPP, Units 1 and 22024-10-24024 October 2024 Pg&Es Voluntary Submittal of Information Related to 10 CFR 2.206 Petition Regarding Seismic Core Damage Frequency for DCPP, Units 1 and 2 DCL-24-092, Supplement and Annual Update License Renewal Application, Amendment 12024-10-14014 October 2024 Supplement and Annual Update License Renewal Application, Amendment 1 DCL-24-098, Material Status Report for the Period Ending August 31, 20242024-10-0909 October 2024 Material Status Report for the Period Ending August 31, 2024 DCL-24-091, Response to Request for Additional Information by the Office of Nuclear Reactor Regulation2024-10-0303 October 2024 Response to Request for Additional Information by the Office of Nuclear Reactor Regulation DCL-24-087, License Renewal - Historic and Cultural Resources Reference Documents (Redacted)2024-09-12012 September 2024 License Renewal - Historic and Cultural Resources Reference Documents (Redacted) DCL-24-083, CFR Part 21 Notification: Commercially Dedicated Snubber Valve Not Properly Heat Treated2024-09-0909 September 2024 CFR Part 21 Notification: Commercially Dedicated Snubber Valve Not Properly Heat Treated DCL-24-078, Pre-Notice of Disbursement from Decommissioning Trust2024-09-0303 September 2024 Pre-Notice of Disbursement from Decommissioning Trust DCL-24-082, Decommissioning Draft Biological Assessment and Draft Essential Fish Habitat Assessment2024-08-28028 August 2024 Decommissioning Draft Biological Assessment and Draft Essential Fish Habitat Assessment DCL-24-077, Responses to NRC Requests for Additional Information on Diablo Canyon Power License Renewal Application Severe Accident2024-08-15015 August 2024 Responses to NRC Requests for Additional Information on Diablo Canyon Power License Renewal Application Severe Accident DCL-24-075, Response to Request for Additional Information for License Amendment Request 23-02, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power React2024-08-0808 August 2024 Response to Request for Additional Information for License Amendment Request 23-02, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power React DCL-24-079, DC-2024-07 Post Exam Comments Analysis2024-08-0202 August 2024 DC-2024-07 Post Exam Comments Analysis DCL-24-070, License Amendment Request 24-03 Revision to Technical Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies2024-07-31031 July 2024 License Amendment Request 24-03 Revision to Technical Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies DCL-24-071, Core Operating Limits Report for Unit 2 Cycle 252024-07-22022 July 2024 Core Operating Limits Report for Unit 2 Cycle 25 DCL-2024-523, Submittal of Report on Discharge Self-Monitoring2024-07-18018 July 2024 Submittal of Report on Discharge Self-Monitoring DCL-2024-527, Sea Turtle Stranding Report (Loggerhead Sea Turtle) Diablo Canyon Power Plant2024-07-0101 July 2024 Sea Turtle Stranding Report (Loggerhead Sea Turtle) Diablo Canyon Power Plant DCL-24-066, Request to Extend the Nrg Approval of Alternative for Use of Full Structural Weld Overlay, REP-RHR-SWOL2024-06-27027 June 2024 Request to Extend the Nrg Approval of Alternative for Use of Full Structural Weld Overlay, REP-RHR-SWOL DCL-24-052, Responses to NRC Requests for Additional Information on the Diablo Canyon Power Plant License Renewal Application Environmental Report2024-05-16016 May 2024 Responses to NRC Requests for Additional Information on the Diablo Canyon Power Plant License Renewal Application Environmental Report DCL-24-051, One Hundred Eighty Day Steam Generator Report for Twenty-Fourth Refueling Outage2024-05-0808 May 2024 One Hundred Eighty Day Steam Generator Report for Twenty-Fourth Refueling Outage DCL-24-049, 2023 Annual Radiological Environmental Operating Report2024-05-0101 May 2024 2023 Annual Radiological Environmental Operating Report DCL-24-047, 2023 Annual Non-radiological Environmental Operating Report2024-05-0101 May 2024 2023 Annual Non-radiological Environmental Operating Report DCL-24-048, O CFR 50.59 and 1 O CFR 72.48 Summary Report for the Period of January 1, 2022, Through December 31, 20232024-04-30030 April 2024 O CFR 50.59 and 1 O CFR 72.48 Summary Report for the Period of January 1, 2022, Through December 31, 2023 DCL-24-027, 2023 Annual Radioactive Effluent Release Report2024-04-28028 April 2024 2023 Annual Radioactive Effluent Release Report DCL-24-045, Annual Report of Occupational Radiation Exposure for 20232024-04-24024 April 2024 Annual Report of Occupational Radiation Exposure for 2023 DCL-24-042, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-04-17017 April 2024 Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations DCL-24-022, Notification of Changes to Decommissioning Schedule2024-04-0202 April 2024 Notification of Changes to Decommissioning Schedule DCL-24-023, Revised Certification of Permanent Cessation of Power Operations2024-04-0202 April 2024 Revised Certification of Permanent Cessation of Power Operations DCL-24-031, Decommissioning Funding Report2024-03-27027 March 2024 Decommissioning Funding Report DCL-24-032, 2024 Annual Statement of Insurance for Pacific Gas and Electric Company’S Diablo Canyon Power Plant2024-03-27027 March 2024 2024 Annual Statement of Insurance for Pacific Gas and Electric Company’S Diablo Canyon Power Plant DCL-24-028, Request for Enforcement Discretion Regarding Compliance with Technical Specification 3.0.3, Limiting Condition for Operation Applicability2024-03-21021 March 2024 Request for Enforcement Discretion Regarding Compliance with Technical Specification 3.0.3, Limiting Condition for Operation Applicability DCL-24-018, License Amendment Request 24-01 Revision to Technical Specification 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR)2024-02-28028 February 2024 License Amendment Request 24-01 Revision to Technical Specification 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR) DCL-2024-507, 2023 Annual Report on Discharge Self-Monitoring2024-02-27027 February 2024 2023 Annual Report on Discharge Self-Monitoring DCL-24-020, Nuclear Material Transaction Report for New Fuel2024-02-21021 February 2024 Nuclear Material Transaction Report for New Fuel DCL-24-014, Owners Activity Report for Unit 1 Twenty-Fourth Refueling Outage2024-02-12012 February 2024 Owners Activity Report for Unit 1 Twenty-Fourth Refueling Outage DCL-24-013, Nuclear Material Transaction Report for New Fuel2024-02-0707 February 2024 Nuclear Material Transaction Report for New Fuel DCL-24-010, Nuclear Material Transaction Report for New Fuel2024-01-29029 January 2024 Nuclear Material Transaction Report for New Fuel DCL-2024-502, 2023 Annual Sea Turtle Report for Diablo Canyon Power Plant (DCPP)2024-01-25025 January 2024 2023 Annual Sea Turtle Report for Diablo Canyon Power Plant (DCPP) DCL-2024-501, Sea Turtle Stranding Report (Green Sea Turtle)2024-01-24024 January 2024 Sea Turtle Stranding Report (Green Sea Turtle) DCL-2024-500, Transmittal of the 4th Quarter of 2023 Report on Discharge Self-Monitoring2024-01-18018 January 2024 Transmittal of the 4th Quarter of 2023 Report on Discharge Self-Monitoring DCL-24-008, Schedule Considerations for Review of the DCPP License Renewal Application2024-01-17017 January 2024 Schedule Considerations for Review of the DCPP License Renewal Application DCL-24-009, Nuclear Material Transaction Report for New Fuel2024-01-17017 January 2024 Nuclear Material Transaction Report for New Fuel DCL-24-004, Supplement to License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2024-01-15015 January 2024 Supplement to License Amendment Request 23-01 Revision to Technical Specifications to Adopt Risk-Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b DCL-23-129, Nuclear Material Transaction Report for New Fuel2023-12-27027 December 2023 Nuclear Material Transaction Report for New Fuel DCL-23-122, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-14014 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation DCL-23-128, Emergency Plan Update2023-12-13013 December 2023 Emergency Plan Update DCL-23-125, Core Operating Limits Report for Unit 1 Cycle 252023-12-0606 December 2023 Core Operating Limits Report for Unit 1 Cycle 25 DCL-23-121, Supplement to License Amendment Request 23-03, Revision to Technical Specification3.7.8, Auxiliary Saltwater System2023-11-16016 November 2023 Supplement to License Amendment Request 23-03, Revision to Technical Specification3.7.8, Auxiliary Saltwater System DCL-23-120, License Amendment Request 23-03 Revision to Technical Specification 3.7.8, Auxiliary Saltwater (Asw) System2023-11-14014 November 2023 License Amendment Request 23-03 Revision to Technical Specification 3.7.8, Auxiliary Saltwater (Asw) System DCL-23-118, License Renewal Application2023-11-0707 November 2023 License Renewal Application DCL-2023-520, Discharge Self-Monitoring at Diablo Canyon Power Plant (DCPP)2023-10-19019 October 2023 Discharge Self-Monitoring at Diablo Canyon Power Plant (DCPP) DCL-23-103, Independent Spent Fuel Storage Installation - Withdrawal of License Amendment Request 22-01, Request for Approval of Alternative Security Measures for Early Warning System2023-10-13013 October 2023 Independent Spent Fuel Storage Installation - Withdrawal of License Amendment Request 22-01, Request for Approval of Alternative Security Measures for Early Warning System 2024-09-09
[Table view] |
Text
James M. Welsch Diablo Canyon Power Plant Senior Vice President P.O. Box 56 Generation and Avila Beach, CA 93424 Chief Nuclear Officer 805.545.3242 E-Mail: James.Welsch@pge.com June 16, 2020 PG&E Letter DCL-20-047 U.S. Nuclear Regulatory Commission 10 CFR 21.21 ATTN: Document Control Desk Washington, DC 20555-0001 Docket No. 50-275, OL-DPR-80 Docket No. 50-323, OL-DPR-82 Diablo Canyon Power Plant, Units 1 and 2 10 CFR Part 21 Notification: Inadequate Dedication of Replacement Thermocouples
Dear Commissioners and Staff,
In accordance with the requirements of 10 CFR 21.21 (d)(3)(ii), Pacific Gas and Electric Company (PG&E) hereby submits the enclosed Diablo Canyon Power Plant (DCPP) written notification of the identification of a defect. This information was initially reported to the Nuclear Regulatory Commission Operations Center on May 20, 2020 (Event Notification 54721). The information provided in the enclosed report meets the reporting requirements of 10 CFR 21.21 (d)(4).
PG&E makes no new or revised regulatory commitments (as defined by NEI 99-04) in this report. Corrective actions identified in this letter will be implemented in accordance with the DCPP Corrective Action Program.
This event did not adversely affect the health and safety of the public.
Sincerely,
/Maureen ZawaliFN for James Welsch James M. Welsch dqmg/51072190 Enclosure Cc/enc: Scott A. Morris, NRC Region IV Administrator Christopher W. Newport, NRC Senior Resident Inspector Balwant K. Singal, NRR Senior Project Manager INPO Diablo Distribution A member of the STARS Alliance Callaway x Diablo Canyon x Palo Verde x Wolf Creek
Enclosure PG&E Letter DCL-20-047 10 CFR PART 21 NOTIFICATION INADEQUATE DEDICATION OF REPLACEMENT THERMOCOUPLES
Enclosure PG&E Letter DCL-20-047 10 CFR Part 21 Notification Inadequate Dedication of Replacement Thermocouples The following information is provided pursuant to 10 CFR 21.21(d)(4).
- i. Name and address of the individual or individuals informing the Commission.
James M. Welsch Senior Vice President, Generation and Chief Nuclear Officer Diablo Canyon Power Plant Mail Code 104/6 P.O. Box 56 Avila Beach, CA 93424 ii. Identification of the facility, the activity, or the basic component supplied for such facility or such activity within the United States which fails to comply or contains a defect.
Facility: Diablo Canyon Power Plant (DCPP) Unit 1 and 2 Docket No. 50-275 and 50-323 License No. OL-DPR-80 and OL-DPR-82 Basic Component: Thermocouple, Bellofram Model 3060-2-JJ-2-13.00-0-1-000 iii. Identification of the firm constructing the facility or supplying the basic component which fails to comply or contains a defect.
Diablo Canyon Power Plant P.O. Box 56 Avila Beach, CA 93424 iv. Nature of the defect or failure to comply and the safety hazard which is created or could be created by such defect or failure to comply.
The original defect was discovered on April 10, 2020, during bench testing where two separate thermocouples exhibited leakage during static assembly. The two thermocouples were tested as part of a spare safety-related pump motor refurbishment. Upon subsequent review, it was identified that a pressure boundary test had not been required as part of the dedication process, but should have been for its safety-related application.
- v. The date on which the information of such defect or failure to comply was obtained.
Enclosure PG&E Letter DCL-20-047 On May 18, 2020, Pacific Gas and Electric (PG&E) completed its evaluation of a deviation concerning commercial-grade thermocouples dedicated at DCPP.
The reporting officer was informed on May 18, 2020. The defect was reported to the NRC telephonically on May 20, 2020 (Event Notification 54721).
vi. In the case of a basic component which contains a defect or fails to comply, the number and location of these components in use at, supplied for, being supplied for, or may be supplied for, manufactured, or being manufactured for one or more facilities or activities subject to the regulations in this part.
Components of the suspect batch were not installed in the plant and there was no risk to the health and safety of the public. Thermocouples from the same batch have been quarantined to prevent installation, and it has been confirmed that none of the suspect batch of thermocouples have been installed in the plant.
vii. The corrective action which has been, is being, or will be taken; the name of the individual or organization responsible for the action; and the length of time that has been or will be taken to complete the action.
This defect was documented in the DCPP corrective action program. The thermocouple replacement part evaluation has been revised to include a pressure boundary test as part of the commercial-grade dedication prior to acceptance.
viii. Any advice related to the defect or failure to comply about the facility, activity, or basic component that has been, is being, or will be given to purchasers or licensees.
None.
ix. In the case of an early site permit, the entities to whom an early site permit was transferred.
This event does not involve an early site permit.