CP-201800306, Guarantees of Payment of Deferred Premiums
| ML18144A787 | |
| Person / Time | |
|---|---|
| Site: | Comanche Peak |
| Issue date: | 05/22/2018 |
| From: | Hope T Luminant Power, TXU Energy, Vistra Operations Company |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| CP-201800306, TXX-18033 | |
| Download: ML18144A787 (3) | |
Text
CP-201800306 TXX-18033 U. 5. Nuclear Regulatory Commission ATIN: Document Control Desk Washington, DC 20555-0001
- ~TXU I m!
..._, energy Luminant 5/22/2018
SUBJECT:
COMANCHE PEAK NUCLEAR POWER PLANT DOCKET NOS. 50-445 AND 50-446 GUARANTEES OF PAYMENT OF DEFERRED PREMIUMS
Dear Sir or Madam:
Timothy A. Hope Manager, Regulatory Affairs Luminant P.0. Box 1002 6322 North FM 56 Glen Rose, TX 76043 o 254.897.6370 Ref 10 CFR 50.54(w)
Pursuant to 10 CFR 50.54{w}{3}, Vistra Operations Company LLC {Vistra OpCo}, hereby submits the attached summary report of the level and source of on-site property damage insurance coverage for Comanche Peak as of April 1, 2018. The level of coverage maintaineµ is in excess of the $1.06 billion as required by 10CFR50.54{w).
6555 SIERRA DRIVE IRVING, TEXAS 75039 0214-812-4600 VISTRAENERGY.COM
TXX-18033 Page 2 of 2 This communication contains no new commitments regarding CPNPP Units 1 and 2.
Should you have any questions, please contact Carl B. Corbin at (254) 897-0121.
c-Attachment Kriss Kennedy, Region IV Margaret Watford O'Banion, NRR Resident Inspectors, Comanche Peak Sincerely,
~~
Timothy A. Hop~
to TXX-18033 Page 1 of 1
- Policy No.
P18-115 X18-115 Comanche Peak Power Company LLC Comanche Peak Nuclear Power Plant Nuclear Property Insurance Coverage As of April 11 2018 Property - All Risk (Operating Facility)
Insuring Company Amount of Insurance Nuclear Electric Insurance Ltd.
$ 1,500,000,000 Nuclear Electric Insurance Ltd.
750,000,000 Total
$ 2,250,000,000 Expires April 1, 2019 April 1, 2019