CNRO-2002-00014, Entergy Operations, Inc. - Answer to Issuance of Order for Interim Safeguards and Security Compensatory Measures

From kanterella
Jump to navigation Jump to search
Entergy Operations, Inc. - Answer to Issuance of Order for Interim Safeguards and Security Compensatory Measures
ML020790031
Person / Time
Site: Grand Gulf, Arkansas Nuclear, River Bend, Waterford  Entergy icon.png
Issue date: 03/15/2002
From: Mcgaha J
Entergy Operations
To:
NRC/SECY/RAS
References
CNRO-2002-00014
Download: ML020790031 (5)


Text

Entergy Operations, Inc.

-Entergy PO. Box 31995 Jackson, MS 39286 1995 Tel 601 368 5690 jmcgaha@entergycom John R. McGaha President CNRO-2002-00014 March 15, 2002 Secretary, Office of the Secretary U. S. Nuclear Regulatory Commission ATTN: Rulemakings and Adjudications Staff Washington, DC 20555-0001

SUBJECT:

Entergy Operations, Inc. - Answer to Issuance of Order for Interim Safeguards and Security Compensatory Measures River Bend Station Grand Gulf Nuclear Station Docket No. 50-458 Docket No. 50-416 License No. NPF-47 License No. NPF-29 Arkansas Nuclear One Waterford 3 Steam Electric Station Units 1 & 2 Docket No. 50-382 Docket Nos. 50-313 & 50-368 License No. NPF-38 License Nos. DPR-51 & NPF-6

REFERENCE:

Letters to Gary J. Taylor from Samuel J. Collins dated February 25, 2002 Issuance of Order for Interim Safeguards and Security Compensatory Measures (CNRI-2002-00002, CNRI-2002-00003, CNRI-2002-00004, CNRI-2002-00005)

Dear Sir:

Pursuant to the requirements of 10 CFR § 2.202(a)(2), Entergy's Answer to February 25, 2002 Commission Order to Modify License for Interim Safeguards and Security Measures is being transmitted to the Secretary of the Commission for filing. Also transmitted under separate cover to the Director, Office of Nuclear Reactor Regulation is a request for an extension of time in which to request a hearing.

Entergy's responses to Section II1. B. and C. of the referenced Order were provided separately pursuant to the requirements of 10 CFR § 50.4 g2oo/

CNRO-2002-00014 Page 2 of 2 If you have any questions or require additional information, please contact me.

This letter includes no new commitments.

Sincerely, A W RM/LAE/ba Attachment cc: (all with attachment)

See Service List Mr. C. G. Anderson (N-GSB)

Mr. J. L. Blount (M-ECH-62)

Mr. W. A. Eaton (G-ESC-VPNO)

Mr. P. D. Hinnenkamp (R-GSB-40)

Mr. M. J. Wetterhahn (W&S)

Mr. L. Jager Smith (Wise, Carter)

Mr. G.J. Taylor (M-ECH-62 Mr. J. A. Thayer (M-ECH-579)

Mr. J. E. Venable (W-GSB-300)

Mr. W. D. Reckley, Project Manager (ANO-1)

Mr. T. W. Alexion, Project Manager, (ANO-2)

Mr. S. P. Sekerak, Project Manager (GGNS)

Mr. D. J. Wrona, Project Manager (RBS)

Mr. N. Kalyanam, Project Manager (W-3)

Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Mail Stop O7-D-01 Washington, DC 20555-0001 Mr. R. L. Bywater Mr. T. L. Hoeg Senior Resident Inspector Senior Resident Inspector Arkansas Nuclear One Grand Gulf Nuclear Station Mr. P. J. Alter Mr. T. R. Farnholtz Senior Resident Inspector Senior Resident Inspector River Bend Station Waterford 3 Steam Electric Station

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION In the Matter of )

)

Entergy Operations, Inc. )

) Docket Nos. 50-313 (Arkansas Nuclear One, ) 50-368 Units 1 and 2; ) 50-416 50-458 Grand Gulf Nuclear Station; ) 50-382

)

River Bend Station; )

)

Waterford 3 Steam Electric Station) )

LICENSEE'S ANSWER TO FEBRUARY 25, 2002 COMMISSION ORDER TO MODIFY LICENSE FOR INTERIM SAFEGUARDS AND SECURITY MEASURES On February 25, 2002, the Nuclear Regulatory Commission ("NRC" or "Commission") issued an immediately effective order in the captioned matter entitled Order Modifying Licenses (Effective Immediately) ("Order") to, inter alia, Entergy Operations, Inc.

("Entergy"). The Order stated that following September 11, 2001, the Commission took a number of actions, including the commencement of a comprehensive review of its safeguards and security programs and requirements. The Commission stated its determination that power reactor licensees be required to implement compensatory measures as prudent, interim actions to address the generalized high-level threat environment in a consistent manner throughout the nuclear reactor community. Therefore, 1

the NRC stated it was imposing requirements as set forth in Attachment 2 of the Order.

1 Attachment 2 contained Safeguards Information and was not publicly released.

Entergy has responded to the substantive requirements of the Order in letters dated March 2

15, 2002 in accordance with the provisions of 10 C.F.R. § 50.4, as directed by the Order.

Pursuant to 10 C.F.R. § 2.202(d), Entergy consents to the Order, except as follows:

pursuant to a letter sent to Mr. Samuel J. Collins, Director, Nuclear Reactor Regulation, on March 15, 2002, in the same dockets, Entergy has requested an extension of time in which to request a hearing with respect to certain interim compensatory measures in Attachment 2 of the Order. The request is based on the pendency of several analyses needed to provide a basis to determine whether a request for a hearing would be appropriate. That request for extension of time is incorporated by reference in this Answer.

I declare under penalty of perjury that the forgoing is true and correct.

Respectfully submitted, Entergy Operations, Inc.

John R. McGaha President -E01 P

2 The enclosures to that letter were transmitted as Safeguards Information.

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION In the Matter of )

)

Entergy Operations, Inc.

)

)

) Docket Nos. 50-313 (Arkansas Nuclear One, 50-368 Units 1 and 2;

)

) 50-416

) 50-458 Grand Gulf Nuclear Station; 50-382

)

River Bend Station;

)

)

Waterford Steam Electric Station)

)

CERTIFICATE OF SERVICE I hereby certify under penalty of perjury that copies of the ANSWER TO FEBRUARY 25, 2002, COMMISSION ORDER TO MODIFY LICENSE FOR INTERIM SAFEGUARDS AND SECURITY MEASURES in the captioned action have been served on the following by deposit in the United States mail, first class, or by overnight delivery, as indicated by an asterisk (*), this 15th day of March 2002.

Secretary Mr. Samuel J. Collins, Director*

Office of the Secretary Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Mail Stop O-5E7 ATTN: Rulemakings and Adjudications One White Flint North Staff 11555 Rockville Pike Washington, DC 20555-0001 Rockville, MD 20852-2738 Regional Administrator - Region IV Assistant General Counsel for Materials U.S. Nuclear Regulatory Commission Litigation and Enforcement 611 Ryan Plaza Drive, Suite 400 U.S. Nuclear Regulatory Commission Arlington, TX 76011 Washington, DC 20555-0001 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 t a4 PR.eMcsaie President - E01