BVY 22-013, Notification of Revised Decommissioning Cost Estimate

From kanterella
(Redirected from BVY 22-013)
Jump to navigation Jump to search
Notification of Revised Decommissioning Cost Estimate
ML22171A011
Person / Time
Site: Vermont Yankee  Entergy icon.png
Issue date: 06/17/2022
From: State S
NorthStar Vermont Yankee
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards, Office of Nuclear Reactor Regulation
References
BVY 22-013
Download: ML22171A011 (4)


Text

NorthStar Vermont Yankee, LLC Vermont Yankee Nuclear Power Station 320 Governor Hunt Road Vernon, VT 05354 Office: 802.451.5354 24-Hour Emergency Response: 800.283.2933 The Worlds Most Comprehensive Facility & Infrastructure Solutions Company - We Bring Answers.

Scott E. State, P.E.

Chief Nuclear Officer 10 CFR 50.82(a)(7)

BVY 22-013 June 17, 2022 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

SUBJECT:

Notification of Revised Decommissioning Cost Estimate Vermont Yankee Nuclear Power Station Docket Nos. 50-271 and 72-59 License No. DPR-28

REFERENCE:

Letter, NorthStar Group Services, Inc. to NRC Notification of Revised Post-Shutdown Decommissioning Activities Report (Revised PSDAR),

(BVY 17-045), dated April 6, 2017 (ADAMS Accession No. ML17096A394)

Dear Sir or Madam:

Pursuant to 10 CFR 50.82(a)(7), NorthStar Vermont Yankee, LLC (VY), is submitting an updated Decommissioning Cost Estimate (DCE) table. In the above reference, VY submitted a Revised Post-Shutdown Decommissioning Activities Report (Revised PSDAR) which contained a revised DCE table, titled Decommissioning Annual Spend Plan.

The DCE has been updated to reflect the actual annual project costs through December 31, 2021. The revised table reflects no change to the original Total Decommissioning Costs but does reflect a change in the sequence in which the costs were incurred. The revised table also reflects expected future costs for the projects remaining periods. The revised DCE table is attached.

This letter contains no new regulatory commitments.

Abatement & Demolition l Emergency & Disaster Response l Environmental Remediation l Nuclear Decommissioning l NorthStar.com

Should you have any questions concerning this letter, or require additional information, please contact me at 212.951.3660.

Best Regards, NorthStar Vermont Yankee, LLC By: _______________________________________________

Scott E. State, P.E.

Chief Nuclear Officer Attachment 1: Revised Decommissioning Cost Estimate Table cc: Mr. David C. Lew Regional Administrator, Region 1 U.S. Nuclear Regulatory Commission 2100 Renaissance Blvd, Suite 100 King of Prussia, PA 19406-2713 Commissioner Vermont Department of Public Service 112 State Street - Drawer 20 Montpelier, Vermont 05602-2601 Mr. Gregory G. DiCarlo, Vice President & General Counsel NorthStar Group Services, Inc.

2760 South Falkenburg Road Riverview, FL 33578 BVY 22-013 Page 2 of 2

BVY 22-013 / Attachment 1 / Page 1 of 2 Attachment Vermont Yankee Nuclear Power Station Revised Decommissioning Cost Estimate Table (2 pages)

Abatement & Demolition l Emergency & Disaster Response l Environmental Remediation l Nuclear Decommissioning l NorthStar.com

BVY 22-013 / Attachment 1 / Page 2 of 2 Table 3 Decommissioning Annual Spend Plan (Thousands of Performance Year Dollars)

ANNUAL COST PROFILE (2017-2052)

Pre-Turnover Work Completed Work Remaining Work Forecast 2017 2018 2019 2020 2021 (25 yea rs )

Actual Actual Actual Actual Actual 2022 2023 2024 2025 2026 2027-2051 2052 TOTAL License Termination Costs Facility Management $0 $0 $12,541 $11,041 $11,041 $11,041 $11,041 $11,041 $11,041 $4,703 $83,494 Pre-Turnover Work (Completed Post-Closing) $7,159 $2,825 $886 $0 $0 $0 $0 $0 $0 $10,870 Decontamination and Decommissioning $0 $0 $22,745 $33,874 $35,296 $31,155 $48,407 $40,541 $12,928 $0 $224,946 Large Component Removal $3,248 $16,432 $33,183 $17,808 $19,843 $20,173 $1,549 $0 $7 $0 $112,243 Project Management $0 $0 $9,515 $10,531 $16,545 $16,545 $16,045 $14,105 $6,363 $4,686 $94,335 ISFSI Decommissioning $3,454 $3,454 Total License Termination Costs (10 CFR 50.75) $10,406 $19,257 $78,870 $73,255 $82,726 $78,915 $77,043 $65,687 $30,340 $9,390 $0 $3,454 $529,342 Spent Fuel Management (10 CFR 50.54(bb)) $0 $0 $11,141 $4,241 $4,241 $4,241 $4,241 $4,241 $4,241 $4,241 $238,030 $8,944 $287,802 Site Restoration (10 CFR 50.54(bb)) $0 $0 $2,057 $4,808 $5,123 $936 $936 $936 $10,205 $0 $25,000 Total Decommissioning Costs $10,406 $19,257 $92,068 $82,304 $92,090 $84,092 $82,220 $70,864 $44,785 $13,631 $238,030 $12,398 $842,144 BVY 22-013 Page 2 of 2