MONTHYEARBSEP 14-0028, Seismic Hazard and Screening Report (CEUS Sites), Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) the Seismic Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi A2014-03-31031 March 2014 Seismic Hazard and Screening Report (CEUS Sites), Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) the Seismic Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accid Project stage: Response to RAI BSEP 14-0087, Response to Request for Additional Information Associated with Near-Term Task Force Recommendation 2.1, Seismic Hazard and Screening Report2014-08-14014 August 2014 Response to Request for Additional Information Associated with Near-Term Task Force Recommendation 2.1, Seismic Hazard and Screening Report Project stage: Response to RAI ML14231A9642014-09-17017 September 2014 Screening and Prioritization Results of Information Provided Pursuant to Title 10 of the Code of Federal Regulations Part 50, Section 50.54(f), Seismic Hazard Reevaluations for Recommendation 2.1 Fukushima Project stage: Other BSEP 14-0131, Expedited Seismic Evaluation Process Report in Response to 10 CFR 50.54(f) Request for Information Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-lchi Accident2014-12-18018 December 2014 Expedited Seismic Evaluation Process Report in Response to 10 CFR 50.54(f) Request for Information Regarding Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-lchi Accident Project stage: Request ML15231A0222015-09-0808 September 2015 Nuclear Regulatory Commission Plan for the Audit of Duke Energy Progress, Inc. Interim Evaluation Associated with Reevaluated Seismic Hazard Implementing Near-Term Task Force Recommendation 2.1 - Seismic for Brunswick Steam Electric Plant, Project stage: Other ML15279A4502015-12-0909 December 2015 NRC Report for the Audit of Duke Entergy Progress, Inc. Interim Evaluation Associated with Reevaluated Seismic Hazard Implementing Near-Term Task Force Recommendation 2.1 -- Seismic for: Brunswick Steam Electric Plant, Units 1 and 2 (TACs M Project stage: Other 2014-08-14
[Table View] |
|
---|
Category:Letter type:BSEP
MONTHYEARBSEP 19-0012, Submittal of 2018 Sea Turtle Annual Report2019-01-17017 January 2019 Submittal of 2018 Sea Turtle Annual Report BSEP 18-0052, Annual Radiological Environmental Operating Report - 20172018-05-10010 May 2018 Annual Radiological Environmental Operating Report - 2017 BSEP 18-0051, Annual Radioactive Effluent Release Report - 20172018-04-26026 April 2018 Annual Radioactive Effluent Release Report - 2017 BSEP 18-0045, Request for License Amendment: Technical Specification 3.8.3, Diesel Fuel Oil, One-Time Extension of Main Fuel Oil Storage Tank Completion Time2018-04-25025 April 2018 Request for License Amendment: Technical Specification 3.8.3, Diesel Fuel Oil, One-Time Extension of Main Fuel Oil Storage Tank Completion Time BSEP 18-0054, Response to Request for Additional Information Regarding Inservice Inspection Program Proposed Alternative ISI-09 in Accordance with 10 CFR 50.55a(z)(1) Regarding Reactor Pressure Vessel Circumferential.2018-04-24024 April 2018 Response to Request for Additional Information Regarding Inservice Inspection Program Proposed Alternative ISI-09 in Accordance with 10 CFR 50.55a(z)(1) Regarding Reactor Pressure Vessel Circumferential. BSEP 18-0048, Response to Request for Additional Information Regarding Inservice Inspection Program Proposed Alternative ISI-09 in Accordance with 10 CFR 50.55a(z)(1) Regarding Reactor Pressure Vessel Circumferential Shell Weld Examinations2018-04-11011 April 2018 Response to Request for Additional Information Regarding Inservice Inspection Program Proposed Alternative ISI-09 in Accordance with 10 CFR 50.55a(z)(1) Regarding Reactor Pressure Vessel Circumferential Shell Weld Examinations BSEP 18-0044, Application of Dissimilar Metal Weld Full Structural Overlay - Reactor Pressure Vessel Nozzles N4A and N4D2018-04-11011 April 2018 Application of Dissimilar Metal Weld Full Structural Overlay - Reactor Pressure Vessel Nozzles N4A and N4D BSEP 18-0046, Supplement to Response to Request for Additional Information SRXB-RAI-2 Regarding Request for License Amendment Regarding Core Flow Operating Range Expansion2018-04-10010 April 2018 Supplement to Response to Request for Additional Information SRXB-RAI-2 Regarding Request for License Amendment Regarding Core Flow Operating Range Expansion BSEP 18-0047, Supplement to Proposed Alternative in Accordance with 10 CFR 50.55a(z)(2) for End of Interval Leakage Test2018-04-0505 April 2018 Supplement to Proposed Alternative in Accordance with 10 CFR 50.55a(z)(2) for End of Interval Leakage Test BSEP 18-0041, Request for License Amendment to Revise the Technical Specifications to Relocate the Pressure-Temperature Limit Curves to a Pressure and Temperature Limits Report2018-04-0404 April 2018 Request for License Amendment to Revise the Technical Specifications to Relocate the Pressure-Temperature Limit Curves to a Pressure and Temperature Limits Report BSEP 18-0043, Application of Dissimilar Metal Weld Full Structural Overlay - Reactor Pressure Vessel Nozzles N4A and N4D2018-03-31031 March 2018 Application of Dissimilar Metal Weld Full Structural Overlay - Reactor Pressure Vessel Nozzles N4A and N4D BSEP 18-0035, Response to Request for Additional Information Regarding Request for License Amendment Regarding Core Flow Operating Range Expansion2018-03-29029 March 2018 Response to Request for Additional Information Regarding Request for License Amendment Regarding Core Flow Operating Range Expansion BSEP 18-0042, Cycle 22 Core Operating Limits Report (COLR)2018-03-27027 March 2018 Cycle 22 Core Operating Limits Report (COLR) BSEP 18-0040, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) for End of Interval Leakage Test2018-03-23023 March 2018 Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) for End of Interval Leakage Test BSEP 18-0039, Proposed In-Service Inspection Alternative for Application of Dissimilar Metal Weld Full Structural Overlay - Nozzles N4A and N4D2018-03-19019 March 2018 Proposed In-Service Inspection Alternative for Application of Dissimilar Metal Weld Full Structural Overlay - Nozzles N4A and N4D BSEP 18-0034, Corrected Affidavit Relating to the Request for License Amendment Regarding Core Flow Operating Range Expansion2018-03-16016 March 2018 Corrected Affidavit Relating to the Request for License Amendment Regarding Core Flow Operating Range Expansion BSEP 18-0032, Additional Testing Information Relating to the Request for License Amendment Regarding Core Flow Operating Range Expansion2018-03-14014 March 2018 Additional Testing Information Relating to the Request for License Amendment Regarding Core Flow Operating Range Expansion BSEP 18-0026, Additional Information Regarding Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) for Reactor Pressure Vessel Nozzle-to-Vessel Weld Examination2018-03-0707 March 2018 Additional Information Regarding Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) for Reactor Pressure Vessel Nozzle-to-Vessel Weld Examination BSEP 18-0014, Fifth 10-Year Inservice Testing Program Plan2018-02-19019 February 2018 Fifth 10-Year Inservice Testing Program Plan BSEP 18-0021, Response to Request for Additional Information Regarding Request for License Amendment Regarding Core Flow Operating Range Expansion (CAC Nos. MF8864 and MF8865). Without Proprietary Enclosure2018-02-0505 February 2018 Response to Request for Additional Information Regarding Request for License Amendment Regarding Core Flow Operating Range Expansion (CAC Nos. MF8864 and MF8865). Without Proprietary Enclosure BSEP 18-0017, Revision to Radiological Emergency Response Plan and Implementing Procedure2018-01-30030 January 2018 Revision to Radiological Emergency Response Plan and Implementing Procedure BSEP 18-0015, Inservice Inspection Program Proposed Alternative ISI-09 in Accordance with 10 CFR 50.55a(z)(1) Regarding Reactor Pressure Vessel Circumferential Shell Weld Examinations2018-01-23023 January 2018 Inservice Inspection Program Proposed Alternative ISI-09 in Accordance with 10 CFR 50.55a(z)(1) Regarding Reactor Pressure Vessel Circumferential Shell Weld Examinations BSEP 18-0013, Supplement to Application to Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control2018-01-23023 January 2018 Supplement to Application to Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control BSEP 18-0001, Application to Revise Technical Specifications to Adopt TSTF-551, Revise Secondary Containment Surveillance Requirements2018-01-23023 January 2018 Application to Revise Technical Specifications to Adopt TSTF-551, Revise Secondary Containment Surveillance Requirements BSEP 18-0012, Application to Revise Technical Specifications to Adopt TSTF-208, Revision 0, Extension of Time to Reach Mode 2 in LCO 3.0.32018-01-23023 January 2018 Application to Revise Technical Specifications to Adopt TSTF-208, Revision 0, Extension of Time to Reach Mode 2 in LCO 3.0.3 BSEP 18-0009, 2017 Sea Turtle Annual Report2018-01-15015 January 2018 2017 Sea Turtle Annual Report BSEP 17-0098, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components (Sscs) for Nuclear Power Reactors2018-01-10010 January 2018 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components (Sscs) for Nuclear Power Reactors BSEP 17-0119, Snubber Program Plan for Fifth 10-Year Interval Inservice Testing Program2018-01-10010 January 2018 Snubber Program Plan for Fifth 10-Year Interval Inservice Testing Program BSEP 17-0115, Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control2018-01-0404 January 2018 Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control BSEP 17-0110, Seventh Six-Month Status Report in Response to June 6, 2013, Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions2017-12-20020 December 2017 Seventh Six-Month Status Report in Response to June 6, 2013, Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions BSEP 17-0121, Post-Examination Documentation and Comments for Operator Retake Initial Examination2017-12-14014 December 2017 Post-Examination Documentation and Comments for Operator Retake Initial Examination BSEP 17-0120, Withdrawal of Request for Risk-Informed Exigent License Amendment - Technical Specification 3.8.1, AC Sources - Operating, One-Time Extension of Emergency Diesel Generator Completion Times and Suspension..2017-12-12012 December 2017 Withdrawal of Request for Risk-Informed Exigent License Amendment - Technical Specification 3.8.1, AC Sources - Operating, One-Time Extension of Emergency Diesel Generator Completion Times and Suspension.. BSEP 17-0118, Supplement to Response to Request for Additional Information Regarding Request for Risk-Informed Exigent License Amendment - Technical Specification 3.8.1, AC Sources - Operating, One-Time Extension of Emergency Diesel..2017-12-0707 December 2017 Supplement to Response to Request for Additional Information Regarding Request for Risk-Informed Exigent License Amendment - Technical Specification 3.8.1, AC Sources - Operating, One-Time Extension of Emergency Diesel.. BSEP 17-0117, Response to Request for Additional Information (Probabilistic Risk Assessment and Human Performance Branches) Regarding Request for Risk-Informed Exigent License Amendment - Technical Specification 3.8.1 AC Sources..2017-12-0606 December 2017 Response to Request for Additional Information (Probabilistic Risk Assessment and Human Performance Branches) Regarding Request for Risk-Informed Exigent License Amendment - Technical Specification 3.8.1 AC Sources.. BSEP 17-0116, Response to Request for Additional Information Regarding Request for Risk- Informed Exigent License Amendment - Technical Specification 3.8.1, AC Sources - Operating, One-Time Extension of ..2017-12-0404 December 2017 Response to Request for Additional Information Regarding Request for Risk- Informed Exigent License Amendment - Technical Specification 3.8.1, AC Sources - Operating, One-Time Extension of .. BSEP 17-0104, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) for Reactor Pressure Vessel Nozzle-to-Vessel Weld Examination2017-11-29029 November 2017 Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) for Reactor Pressure Vessel Nozzle-to-Vessel Weld Examination BSEP 17-0111, Request for Risk-Informed Exigent License Amendment - Technical Specification 3.8.1, AC Sources Operating, One-Time Extension of Emergency Diesel Generator Completion Times and Suspension of Surveillance Requirements2017-11-28028 November 2017 Request for Risk-Informed Exigent License Amendment - Technical Specification 3.8.1, AC Sources Operating, One-Time Extension of Emergency Diesel Generator Completion Times and Suspension of Surveillance Requirements BSEP 17-0109, Response to Request for Additional Information Regarding Request for Emergency License Amendment - Technical Specification 3.8.1, AC Sources - Operating, One-Time Extension of Emergency Diesel Generator Completion Times And.2017-11-24024 November 2017 Response to Request for Additional Information Regarding Request for Emergency License Amendment - Technical Specification 3.8.1, AC Sources - Operating, One-Time Extension of Emergency Diesel Generator Completion Times And. BSEP 17-0108, Request for Emergency License Amendment - Technical Specification 3.8.1, AC Sources - Operating, One-Time Extension of Emergency Diesel Generator Completion Times and Suspension of Surveillance Requirements2017-11-22022 November 2017 Request for Emergency License Amendment - Technical Specification 3.8.1, AC Sources - Operating, One-Time Extension of Emergency Diesel Generator Completion Times and Suspension of Surveillance Requirements BSEP 17-0017, Submittal of Request for License Amendment for Performance-Based Fire Protection Alternative for Thermal Insulation Material2017-11-15015 November 2017 Submittal of Request for License Amendment for Performance-Based Fire Protection Alternative for Thermal Insulation Material BSEP 17-0100, Fifth 10-Year Inservice Testing Interval2017-11-0202 November 2017 Fifth 10-Year Inservice Testing Interval BSEP 17-0089, Updates to Request for License Amendment Regarding Core Flow Operating Range Expansion2017-11-0101 November 2017 Updates to Request for License Amendment Regarding Core Flow Operating Range Expansion BSEP 17-0093, Response to Request for Additional Information Regarding Request for License Amendment Regarding Core Flow Operating Range Expansion2017-11-0101 November 2017 Response to Request for Additional Information Regarding Request for License Amendment Regarding Core Flow Operating Range Expansion BSEP 17-0078, Request for License Amendment - DC Sources - Operating Surveillance Requirement (SR) 3.8.4.52017-10-0303 October 2017 Request for License Amendment - DC Sources - Operating Surveillance Requirement (SR) 3.8.4.5 BSEP 17-0076, Registration for Use of General License Spent Fuel Casks2017-09-0606 September 2017 Registration for Use of General License Spent Fuel Casks BSEP 17-0081, Revision to Radiological Emergency Response Plan Implementing Procedures2017-09-0505 September 2017 Revision to Radiological Emergency Response Plan Implementing Procedures BSEP 17-0039, Submittal of Response to Inspection Report 05000324/2015404 and 05000325/2015404, Dated March 30, 2015, Inspection of Interim Cyber Security Milestones 1-7 and Target Set Requirements2017-08-15015 August 2017 Submittal of Response to Inspection Report 05000324/2015404 and 05000325/2015404, Dated March 30, 2015, Inspection of Interim Cyber Security Milestones 1-7 and Target Set Requirements BSEP 17-0071, ISFSI - Registration for Use of General License Spent Fuel Casks2017-08-15015 August 2017 ISFSI - Registration for Use of General License Spent Fuel Casks BSEP 17-0064, Application of Dissimilar Metal Weld Full Structural Overlay on Reactor Pressure Vessel Nozzle N92017-07-10010 July 2017 Application of Dissimilar Metal Weld Full Structural Overlay on Reactor Pressure Vessel Nozzle N9 BSEP 17-0060, Application to Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control.2017-06-29029 June 2017 Application to Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control. 2019-01-17
[Table view] |
Text
George T. Hamrick Vice President ENERGY, Brunswick Nuclear Plant P.O. Box 10429 Southport, NC 28461 o: 910.457.3698 10 CFR 50.54(f)
August 14, 2014 Serial: BSEP 14-0087 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001
Subject:
Brunswick Steam Electric Plant, Unit Nos. 1 and 2 Docket Nos. 50-325 and 50-324 Renewed License Nos. DPR-71 and DPR-62 Response to Request for Additional Information Associated with Near-Term Task Force Recommendation 2.1, Seismic Hazard and Screening Report
References:
- 1. NRC Letter, Request for Information Pursuantto Title 10 of the Code of Federal Regulations 50.54(f) Regarding Recommendations 2.1, 2.3, and 9.3, of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichiAccident, dated March 12, 2012, ADAMS Accession No. ML12053A340.
- 2. Electric Power Research Institute (EPRI) Report 1025287, Seismic Evaluation Guidance, Screening, Prioritizationand Implementation Details (SPID)for the Resolution of Fukushima Near-Term Task Force Recommendation 2.1: Seismic, dated November 2012, ADAMS Accession No. ML12333A170.
- 3. NRC Letter, Endorsement of EPRI FinalDraft Report 1025287: "SeismicEvaluation Guidance,"dated February 15, 2013, ADAMS Accession No. ML12319A074.
- 4. Duke Energy Letter, Seismic Hazard and Screening Report (CEUS Sites), Response to NRC Request for Information Pursuantto 10 CFR 50.54(f) Regarding the Seismic Aspects of Recommendation 2. 1 of the Near-Term Task Force Review of Insights from the Fukushimd Dai-ichiAccident, dated March 31, 2014, ADAMS Accession No. ML14106A461.
- 5. NRC Letter, Brunswick Steam Electric Plant, Units 1 and 2 - Request for Additional Information Associated with Near-Term Task Force Recommendation 2. 1, Seismic Hazardand Screening Report, dated July 16, 2014, ADAMS Accession No. ML14195A071.
oC
U.S. Nuclear Regulatory Commission Page 2 of 3 Ladies and Gentlemen, On March 12, 2012, the U. S. Nuclear Regulatory Commission (NRC) staff issued a letter requesting information per Title 10 of the Code of Federal Regulations, Section 50.54(f)
(i.e., Reference 1). The letter requested licensees located in the Central and Eastern United States (CEUS) to submit a Seismic Hazard Evaluation and Screening Report. Reference 2 contains industry guidance and detailed information to be included in the Seismic Hazard Evaluation and Screening Report submittals. The industry guidance was endorsed by the NRC in Reference 3.
By letter dated March 31, 2014 (i.e., Reference 4), Duke Energy submitted to the NRC the Seismic Hazard and Screening Report. By letter dated July 16, 2014 (i.e., Reference 5), the NRC requested additional information related to the Individual Plant Examination for External Events (IPEEE) for Brunswick Steam Electric Plant (BSEP), Units 1 and 2. The NRC staff requested that a response be provided no later than August 15, 2014, as discussed during a recent phone call with members of my staff.
Enclosed, please find the response to the request for additional information.
This letter contains no new regulatory commitments.
If you have any questions regarding this submittal, please contact Mr. Lee Grzeck, Manager-Regulatory Affairs, at (910) 457-2487.
I declare under penalty of perjury that the foregoing is true and correct, executed on August 14, 2014.
Sincerely, C4~ a j~,mu George T. Hamrick RAZ/raz
Enclosure:
Response to the NRC Request for Additional Information (RAI) Associated with Near-Term Task Force Recommendation 2.1, Seismic Hazard and Screening Report
U.S. Nuclear Regulatory Commission Page 3 of 3 cc (with enclosures):
U. S. Nuclear Regulatory Commission, Region II ATTN: Mr. Victor M. McCree, Regional Administrator 245 Peachtree Center Ave, NE, Suite 1200 Atlanta, GA 30303-1257 U. S. Nuclear Regulatory Commission ATTN: Ms. Michelle P. Catts, NRC Senior Resident Inspector 8470 River Road Southport, NC 28461-8869 U. S. Nuclear Regulatory Commission ATTN: Mr. Andrew Hon (Mail Stop OWFN 8G9A) (Electronic Copy Only) 11555 Rockville Pike Rockville, MD 20852-2738 Chair - North Carolina Utilities Commission P.O. Box 29510 Raleigh, NC 27626-0510
BSEP 14-0087 Enclosure Page 1 of 4 Response to NRC Request for Additional Information (RAI) Associated With Near-Term Task Force Recommendation 2.1. Seismic Hazard and Screening Report
Background:
On March 12, 2012, the NRC issued a request for information pursuant to 10 CFR 50.54(f) to gather information concerning, in part, the seismic hazards at operating reactor sites and to enable the NRC staff to determine whether licenses should be modified, suspended, or revoked.
In response to the 50.54(f) letter, Duke Energy committed to follow the Electric Power Research Institute (EPRI) Report, "Seismic Evaluation Guidance: Screening, Prioritization and Implementation Details (SPID) for the Resolution of Fukushima Near-Term Task Force Recommendation 2.1: Seismic," (ADAMS Accession No. ML12333A170) as supplemented by the EPRI Report, "Seismic Evaluation Guidance: Augmented Approach for the Resolution of Fukushima Near-Term Task Force (NTTF) Recommendation 2.1: Seismic" (ADAMS Accession No. ML13102A142). The reevaluation of the seismic hazards for Brunswick Steam Electric Plant (BSEP), Units 1 and 2, was submitted to the NRC by letter dated March 31, 2014 (ADAMS Accession No. ML14106A461). On May 9, 2014, the NRC staff issued a letter (ADAMS Accession No. ML 14111 Al 47) identifying BSEP, Units 1 and 2, as "conditional screen-in" for the purposes of prioritizing and conducting additional evaluations.
In accordance with the SPID and Augmented Approach guidance, the reevaluated seismic hazard is used to determine if additional seismic risk evaluations are warranted. The SPID guidance provides criteria for a plant with ground motion response spectra (GMRS) above the safe shutdown earthquake, but bounded by the Individual Plant Examination for External Events (IPEEE) capacity spectrum. A plant screens out of conducting a seismic risk evaluation if the IPEEE capacity is greater than the GMRS in the 1-10 Hz range. The March 31, 2014, submittal demonstrates the adequacy of the IPEEE seismic evaluation and provides full-scope soil failure evaluation results.
By letter dated July 16, 2014 (ADAMS Accession No. ML14195A071), the NRC requested additional information related to the IPEEE for BSEP, Units 1 and 2. The NRC staff requested that a response be provided no later than August 15, 2014, as discussed during a recent phone call with BSEP staff.
NRC RAI 1:
In Appendix B, Section 2.1.2 of the submittal, it states that soils evaluation considered relevant structures on the Safe Shutdown Equipment List which includes the intake canal. The submittal also states that slope stability screens out at BSEP. Describe the basis for screening out slope stability along the intake canal under the review level earthquake loading.
BSEP 14-0087 Enclosure Page 2 of 4 BSEP Response to RAI 1:
The Intake Canal was originally designed to provide normal cooling water loads for five (5) units.
The current design accommodates a flow requirement of 1390 cubic feet (ft3 )/ second per unit.
The maximum designed capacity of the Intake Canal is approximately 7,000 ft3/second. The Intake Canal mean sea level (MSL) velocity for one unit operating is 0.3 feet (ft)/second, and maximum low tide velocity is 0.4 ft/second. When two units are in operation the MSL velocity is 0.6 ft/second, and maximum low tide velocity is 0.8 ft/second. The representative low water level velocity in the Intake Canal is 1.5 ft/second.
The bottom of the Intake Canal is at Elevation -18 feet MSL; The Intake Canal bottom is 170 feet wide, and the side slopes are at a 4Horizontal (H):1 Vertical (V) slope in the marsh area, and 3H:1V in the high ground area. The total length of the Intake Canal is 2.57 miles. The figure below provides a cross-sectional profile of the Intake Canal.
High Ground Area Intake Canal Cross-Section Profile UINTAKE CANAL
..SERVICE ROAD
.SERVICE ROAD EL. 36' I
The original Intake Canal design evaluation acknowledges that the Intake Canal is susceptible to slope sliding as discussed in the original Final Safety Analysis Report (FSAR). Section 2.4.8.2 of the current Updated FSAR provides a general description of the Intake Canal.
A breakdown of the consequences of liquefaction based on soil conditions and topography is provided in EPRI Report NP-6041-SL, Table 7-1A, "Relationship Between Observed Lateral Deformation During Earthquakes and Geometric Properties of Liquefied Alluvial Soils". Intake
BSEP 14-0087 Enclosure Page 3 of 4 Canal slope slides similar to those presented in Table 7-1A will occur based on the canal design slope, elevation changes and susceptibility to liquefaction.
To illustrate the margin associated with the Intake Canal, sliding at any point along the Intake Canal length, on both sides, is conservatively postulated to occur. For the purpose of determining the adequacy of the IPEEE for BSEP, Units 1 and 2, complete failure of canal slopes with all soils sliding into canal is assumed. This results in a median angle of repose of approximately 50 corresponding to a slope of approximately 12H:1V. The amount of material transported will not significantly impact the Intake Canal performance.
The Service Water system provides all critical cooling water needs for normal and emergency plant conditions. Service Water pump capacity for all ten (10) pumps for both units is 80,000 gallons per minute (gpm). At a velocity of 1.5 ft/second, the required cross-section area for 80,000 gpm is 119 square feet (ft2). Design cross-section area of the canal at low tide is 3,760 ft 2. After postulated worst case canal slope failure the remaining cross-section area of water would be at least 910 ft2 . This is more than seven times the maximum demand of all 10 Service Water pumps. For this worst case scenario, the Intake Canal design capacity ensures significant margin remains to provide adequate cooling water to both units following a Review Level Earthquake (RLE) of 0.3g.
Simplistic & Conservative Intake Canal Profile After Slope Failure EL 0' E .-- , .
2 I \-A=910 Ft A monitoring program is in place to perform hydrographic surveys of cross-sections along the length of the Intake Canal at various stations and is used to determine when canal dredging is required to maintain the Intake Canal profile. Intake Canal maintenance dredging is performed in accordance with a recurring Preventive Maintenance (PM) program Work Order model. Post dredging hydrographic surveys are performed to ensure acceptable Intake Canal profiles are achieved.
BSEP 14-0087 Enclosure Page 4 of 4 NRC RAI 2:
In Appendix B, Section 2.1.2 of the submittal, it states that considerations similar to Table 7-1A of Reference 6.4 was used for screening out liquefaction for the intake canal. If appears that the reference should have been Reference 6.6. Clarify whether the submittal should cite Reference 6.6 instead of Reference 6.4 when referring to Table 7-1A or provide a description of the considerations were used for screening.
BSEP Response to RAI 2:
The submittal should have cited Reference 6.6 instead of Reference 6.4 when referring to Table 7-1A.