MONTHYEARBSEP 19-0012, Submittal of 2018 Sea Turtle Annual Report2019-01-17017 January 2019 Submittal of 2018 Sea Turtle Annual Report BSEP 18-0052, Annual Radiological Environmental Operating Report - 20172018-05-10010 May 2018 Annual Radiological Environmental Operating Report - 2017 BSEP 18-0051, Annual Radioactive Effluent Release Report - 20172018-04-26026 April 2018 Annual Radioactive Effluent Release Report - 2017 BSEP 18-0045, Request for License Amendment: Technical Specification 3.8.3, Diesel Fuel Oil, One-Time Extension of Main Fuel Oil Storage Tank Completion Time2018-04-25025 April 2018 Request for License Amendment: Technical Specification 3.8.3, Diesel Fuel Oil, One-Time Extension of Main Fuel Oil Storage Tank Completion Time BSEP 18-0054, Response to Request for Additional Information Regarding Inservice Inspection Program Proposed Alternative ISI-09 in Accordance with 10 CFR 50.55a(z)(1) Regarding Reactor Pressure Vessel Circumferential.2018-04-24024 April 2018 Response to Request for Additional Information Regarding Inservice Inspection Program Proposed Alternative ISI-09 in Accordance with 10 CFR 50.55a(z)(1) Regarding Reactor Pressure Vessel Circumferential. BSEP 18-0048, Response to Request for Additional Information Regarding Inservice Inspection Program Proposed Alternative ISI-09 in Accordance with 10 CFR 50.55a(z)(1) Regarding Reactor Pressure Vessel Circumferential Shell Weld Examinations2018-04-11011 April 2018 Response to Request for Additional Information Regarding Inservice Inspection Program Proposed Alternative ISI-09 in Accordance with 10 CFR 50.55a(z)(1) Regarding Reactor Pressure Vessel Circumferential Shell Weld Examinations BSEP 18-0044, Application of Dissimilar Metal Weld Full Structural Overlay - Reactor Pressure Vessel Nozzles N4A and N4D2018-04-11011 April 2018 Application of Dissimilar Metal Weld Full Structural Overlay - Reactor Pressure Vessel Nozzles N4A and N4D BSEP 18-0046, Supplement to Response to Request for Additional Information SRXB-RAI-2 Regarding Request for License Amendment Regarding Core Flow Operating Range Expansion2018-04-10010 April 2018 Supplement to Response to Request for Additional Information SRXB-RAI-2 Regarding Request for License Amendment Regarding Core Flow Operating Range Expansion BSEP 18-0047, Supplement to Proposed Alternative in Accordance with 10 CFR 50.55a(z)(2) for End of Interval Leakage Test2018-04-0505 April 2018 Supplement to Proposed Alternative in Accordance with 10 CFR 50.55a(z)(2) for End of Interval Leakage Test BSEP 18-0041, Request for License Amendment to Revise the Technical Specifications to Relocate the Pressure-Temperature Limit Curves to a Pressure and Temperature Limits Report2018-04-0404 April 2018 Request for License Amendment to Revise the Technical Specifications to Relocate the Pressure-Temperature Limit Curves to a Pressure and Temperature Limits Report BSEP 18-0043, Application of Dissimilar Metal Weld Full Structural Overlay - Reactor Pressure Vessel Nozzles N4A and N4D2018-03-31031 March 2018 Application of Dissimilar Metal Weld Full Structural Overlay - Reactor Pressure Vessel Nozzles N4A and N4D BSEP 18-0035, Response to Request for Additional Information Regarding Request for License Amendment Regarding Core Flow Operating Range Expansion2018-03-29029 March 2018 Response to Request for Additional Information Regarding Request for License Amendment Regarding Core Flow Operating Range Expansion BSEP 18-0042, Cycle 22 Core Operating Limits Report (COLR)2018-03-27027 March 2018 Cycle 22 Core Operating Limits Report (COLR) BSEP 18-0040, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) for End of Interval Leakage Test2018-03-23023 March 2018 Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) for End of Interval Leakage Test BSEP 18-0039, Proposed In-Service Inspection Alternative for Application of Dissimilar Metal Weld Full Structural Overlay - Nozzles N4A and N4D2018-03-19019 March 2018 Proposed In-Service Inspection Alternative for Application of Dissimilar Metal Weld Full Structural Overlay - Nozzles N4A and N4D BSEP 18-0034, Corrected Affidavit Relating to the Request for License Amendment Regarding Core Flow Operating Range Expansion2018-03-16016 March 2018 Corrected Affidavit Relating to the Request for License Amendment Regarding Core Flow Operating Range Expansion BSEP 18-0032, Additional Testing Information Relating to the Request for License Amendment Regarding Core Flow Operating Range Expansion2018-03-14014 March 2018 Additional Testing Information Relating to the Request for License Amendment Regarding Core Flow Operating Range Expansion BSEP 18-0026, Additional Information Regarding Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) for Reactor Pressure Vessel Nozzle-to-Vessel Weld Examination2018-03-0707 March 2018 Additional Information Regarding Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) for Reactor Pressure Vessel Nozzle-to-Vessel Weld Examination BSEP 18-0014, Fifth 10-Year Inservice Testing Program Plan2018-02-19019 February 2018 Fifth 10-Year Inservice Testing Program Plan BSEP 18-0021, Response to Request for Additional Information Regarding Request for License Amendment Regarding Core Flow Operating Range Expansion (CAC Nos. MF8864 and MF8865). Without Proprietary Enclosure2018-02-0505 February 2018 Response to Request for Additional Information Regarding Request for License Amendment Regarding Core Flow Operating Range Expansion (CAC Nos. MF8864 and MF8865). Without Proprietary Enclosure BSEP 18-0017, Revision to Radiological Emergency Response Plan and Implementing Procedure2018-01-30030 January 2018 Revision to Radiological Emergency Response Plan and Implementing Procedure BSEP 18-0015, Inservice Inspection Program Proposed Alternative ISI-09 in Accordance with 10 CFR 50.55a(z)(1) Regarding Reactor Pressure Vessel Circumferential Shell Weld Examinations2018-01-23023 January 2018 Inservice Inspection Program Proposed Alternative ISI-09 in Accordance with 10 CFR 50.55a(z)(1) Regarding Reactor Pressure Vessel Circumferential Shell Weld Examinations BSEP 18-0013, Supplement to Application to Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control2018-01-23023 January 2018 Supplement to Application to Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control BSEP 18-0001, Application to Revise Technical Specifications to Adopt TSTF-551, Revise Secondary Containment Surveillance Requirements2018-01-23023 January 2018 Application to Revise Technical Specifications to Adopt TSTF-551, Revise Secondary Containment Surveillance Requirements BSEP 18-0012, Application to Revise Technical Specifications to Adopt TSTF-208, Revision 0, Extension of Time to Reach Mode 2 in LCO 3.0.32018-01-23023 January 2018 Application to Revise Technical Specifications to Adopt TSTF-208, Revision 0, Extension of Time to Reach Mode 2 in LCO 3.0.3 BSEP 18-0009, 2017 Sea Turtle Annual Report2018-01-15015 January 2018 2017 Sea Turtle Annual Report BSEP 17-0098, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components (Sscs) for Nuclear Power Reactors2018-01-10010 January 2018 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components (Sscs) for Nuclear Power Reactors BSEP 17-0119, Snubber Program Plan for Fifth 10-Year Interval Inservice Testing Program2018-01-10010 January 2018 Snubber Program Plan for Fifth 10-Year Interval Inservice Testing Program BSEP 17-0115, Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control2018-01-0404 January 2018 Response to Request for Additional Information Regarding Application to Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control BSEP 17-0110, Seventh Six-Month Status Report in Response to June 6, 2013, Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions2017-12-20020 December 2017 Seventh Six-Month Status Report in Response to June 6, 2013, Commission Order Modifying Licenses with Regard to Reliable Hardened Containment Vents Capable of Operation Under Severe Accident Conditions BSEP 17-0121, Post-Examination Documentation and Comments for Operator Retake Initial Examination2017-12-14014 December 2017 Post-Examination Documentation and Comments for Operator Retake Initial Examination BSEP 17-0120, Withdrawal of Request for Risk-Informed Exigent License Amendment - Technical Specification 3.8.1, AC Sources - Operating, One-Time Extension of Emergency Diesel Generator Completion Times and Suspension..2017-12-12012 December 2017 Withdrawal of Request for Risk-Informed Exigent License Amendment - Technical Specification 3.8.1, AC Sources - Operating, One-Time Extension of Emergency Diesel Generator Completion Times and Suspension.. BSEP 17-0118, Supplement to Response to Request for Additional Information Regarding Request for Risk-Informed Exigent License Amendment - Technical Specification 3.8.1, AC Sources - Operating, One-Time Extension of Emergency Diesel..2017-12-0707 December 2017 Supplement to Response to Request for Additional Information Regarding Request for Risk-Informed Exigent License Amendment - Technical Specification 3.8.1, AC Sources - Operating, One-Time Extension of Emergency Diesel.. BSEP 17-0117, Response to Request for Additional Information (Probabilistic Risk Assessment and Human Performance Branches) Regarding Request for Risk-Informed Exigent License Amendment - Technical Specification 3.8.1 AC Sources..2017-12-0606 December 2017 Response to Request for Additional Information (Probabilistic Risk Assessment and Human Performance Branches) Regarding Request for Risk-Informed Exigent License Amendment - Technical Specification 3.8.1 AC Sources.. BSEP 17-0116, Response to Request for Additional Information Regarding Request for Risk- Informed Exigent License Amendment - Technical Specification 3.8.1, AC Sources - Operating, One-Time Extension of ..2017-12-0404 December 2017 Response to Request for Additional Information Regarding Request for Risk- Informed Exigent License Amendment - Technical Specification 3.8.1, AC Sources - Operating, One-Time Extension of .. BSEP 17-0104, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) for Reactor Pressure Vessel Nozzle-to-Vessel Weld Examination2017-11-29029 November 2017 Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) for Reactor Pressure Vessel Nozzle-to-Vessel Weld Examination BSEP 17-0111, Request for Risk-Informed Exigent License Amendment - Technical Specification 3.8.1, AC Sources Operating, One-Time Extension of Emergency Diesel Generator Completion Times and Suspension of Surveillance Requirements2017-11-28028 November 2017 Request for Risk-Informed Exigent License Amendment - Technical Specification 3.8.1, AC Sources Operating, One-Time Extension of Emergency Diesel Generator Completion Times and Suspension of Surveillance Requirements BSEP 17-0109, Response to Request for Additional Information Regarding Request for Emergency License Amendment - Technical Specification 3.8.1, AC Sources - Operating, One-Time Extension of Emergency Diesel Generator Completion Times And.2017-11-24024 November 2017 Response to Request for Additional Information Regarding Request for Emergency License Amendment - Technical Specification 3.8.1, AC Sources - Operating, One-Time Extension of Emergency Diesel Generator Completion Times And. BSEP 17-0108, Request for Emergency License Amendment - Technical Specification 3.8.1, AC Sources - Operating, One-Time Extension of Emergency Diesel Generator Completion Times and Suspension of Surveillance Requirements2017-11-22022 November 2017 Request for Emergency License Amendment - Technical Specification 3.8.1, AC Sources - Operating, One-Time Extension of Emergency Diesel Generator Completion Times and Suspension of Surveillance Requirements BSEP 17-0017, Submittal of Request for License Amendment for Performance-Based Fire Protection Alternative for Thermal Insulation Material2017-11-15015 November 2017 Submittal of Request for License Amendment for Performance-Based Fire Protection Alternative for Thermal Insulation Material BSEP 17-0100, Fifth 10-Year Inservice Testing Interval2017-11-0202 November 2017 Fifth 10-Year Inservice Testing Interval BSEP 17-0089, Updates to Request for License Amendment Regarding Core Flow Operating Range Expansion2017-11-0101 November 2017 Updates to Request for License Amendment Regarding Core Flow Operating Range Expansion BSEP 17-0093, Response to Request for Additional Information Regarding Request for License Amendment Regarding Core Flow Operating Range Expansion2017-11-0101 November 2017 Response to Request for Additional Information Regarding Request for License Amendment Regarding Core Flow Operating Range Expansion BSEP 17-0078, Request for License Amendment - DC Sources - Operating Surveillance Requirement (SR) 3.8.4.52017-10-0303 October 2017 Request for License Amendment - DC Sources - Operating Surveillance Requirement (SR) 3.8.4.5 BSEP 17-0076, Registration for Use of General License Spent Fuel Casks2017-09-0606 September 2017 Registration for Use of General License Spent Fuel Casks BSEP 17-0081, Revision to Radiological Emergency Response Plan Implementing Procedures2017-09-0505 September 2017 Revision to Radiological Emergency Response Plan Implementing Procedures BSEP 17-0039, Submittal of Response to Inspection Report 05000324/2015404 and 05000325/2015404, Dated March 30, 2015, Inspection of Interim Cyber Security Milestones 1-7 and Target Set Requirements2017-08-15015 August 2017 Submittal of Response to Inspection Report 05000324/2015404 and 05000325/2015404, Dated March 30, 2015, Inspection of Interim Cyber Security Milestones 1-7 and Target Set Requirements BSEP 17-0071, ISFSI - Registration for Use of General License Spent Fuel Casks2017-08-15015 August 2017 ISFSI - Registration for Use of General License Spent Fuel Casks BSEP 17-0064, Application of Dissimilar Metal Weld Full Structural Overlay on Reactor Pressure Vessel Nozzle N92017-07-10010 July 2017 Application of Dissimilar Metal Weld Full Structural Overlay on Reactor Pressure Vessel Nozzle N9 BSEP 17-0060, Application to Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control.2017-06-29029 June 2017 Application to Revise Technical Specifications to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control. 2019-01-17
[Table view] |
Text
On PJohn S. Keenan Vice President Brunswick Nuclear Plant Progress Energy Carolinas. Inc FEB 17 2003 SERIAL: BSEP 03-0036 IU.S. Nuclear Regulatory Commission
%ATTN: Document Control Desk Washington, DC 20555-0901
SUBJECT:
Brunswick Steam Electric Plant, Unit No. 2 Docket No. 50-324/License No. DPR-62 Response to Request for Additional Information Regarding Technical Specification 2.1.1.2, Reactor Core Safety Limits Minimum Critical Power Ratio Safety Limit Ladies and Gentlemen:
On November 7, 2002 (i.e., Serial: BSEP 02-0174), Progress Energy Carolinas, Inc.
requested a revision to the Technical Specifications for the Brunswick Steam Electric Plant (BSEP), Unit No. 2. The proposed license amendment revises the Minimum Critical Power Ratio (MCPR) Safety Limit values contained in Technical Specification 2.1.1.2 from 1.09 to 1.11 for two recirculation loop operation and from 1.10 to 1.13 for single recirculation loop operation. On February 6, 2003, the NRC provided an electronic version of a request for additional information (RAI) concerning the MCPR Safety Limit amendment request. The response to this RAI is included in Enclosure 1. Some of the information contained in the response is considered proprietary by Global Nuclear Fuel Americas, LLC and should be withheld from public disclosure in accordance with 10 CFR 9.17(a)(4) and 10 CFR 2.790(a)(4). An affidavit attesting to this fact is provided in Enclosure 2. A non-proprietary version of the response is provided in Enclosure 3.
Enclosure 4 contains an updated typed technical specification page associated with this amendment request. An editorial change has been made to Specification 2.1.1.1 to incorporate a revision previously issued by License Amendment No. 247 dated May 31, 2002. Progress Energy Carolinas, Inc. has determined that this editorial change does not affect the bases for concluding that the proposed amendment does not involve a Significant Hazards Consideration. As such, the 10 CFR 50.92 Evaluation, provided in the November 7, 2002, submittal and published in the Federal Register (i.e., 67 FR 75869, dated December 10, 2002) remains valid.
PO Box 10429 Southport, NC 28461 T> 9104572496 F> 9104572803
Document Control Desk BSEP 03-0036 / Page 2 Please refer any questions regarding this submittal to Mr. Edward T. O'Neil, Manager - Support Services, at (910) 457-3512.
Sincerely, K.nan WRM/wrm
Enclosures:
- 1. Response to Request for Additional Information (Proprietary Information)
- 2. Global Nuclear Fuel - Americas, LLC Affidavit Regarding Withholding From Public Disclosure
- 3. Response to Request for Additional Information (Non-Proprietary Version)
- 4. Typed Technical Specification Page - Unit 2 John S. Keenan, having been first duly sworn, did depose and say that the information contained herein is true and correct to the best of his information, knowledge and belief; and the sources of his information are officers, employees, and agents of Carolina Power &
Light Company.
Notary (Seal) t~~a[ S::-"I My commission expires:
Document Control Desk BSEP 03-0036 / Page 3 -
cc (with Enclosures 1 through 4):
U. S. Nuclear Regulatory Commission, Region II AT'TN: Mr. Luis A. Reyes, Regional Administrator Sam Nunn Atlanta Federal Center 61 Forsyth Street, SW, Suite 23T85 Atlanta, GA 30303-8931 U. S. Nuclear Regulatory Commission ATTN: Mr. Theodore A. Easlick, NRC Senior Resident Inspector 8470 River Road Southport, NC 28461-8869 U. S. Nuclear Regulatory Commission ATrN: Ms. Brenda L. Mozafari (Mail Stop OWFN 8G9) 11555 Rockville Pike Rockville, MD 20852-2738 cc (with Enclosures 2 through 4 only):
Ms. Jo A. Sanford Chair - North Carolina Utilities Commission P.O. Box 29510 Raleigh, NC 27626-0510 Ms. Beverly 0. Hall, Section Chief Radiation Protection Section, Division of Radiation Protection North Carolina Department of Environment and Natural Resources 3825 Barrett Drive Raleigh, NC 27609-7221
BSEP 03-0036 Enclosure 3 Response to Request for Additional Information (Non-Proprietary Version)
NRC Requests for Additional Information for February 11, 2003 Brunswick Steam Electric Plant, Unit No. 2 Docket No. 50-324/License No. DPR-62 Request For License Amendment Regarding Technical Specification 2.1.1.2, Reactor Core Safety Limits Minimum Critical Power Ratio Safety Limit NRC Question 1 Describe detailed calculation process including approved methods used, based on a plant/cycle specific parameters, to model ((
)) the entire cycle operation. Also, provide a Table to show net adjustment to SLMCPR for both dual loop operation and single loop operation including BOC, MOC and EOC.
Response
In the last paragraph of the Summary section of the attachment titled "Additional Information Regarding the Cycle Specific SLMCPR for Brunswick Unit 2 Cycle 16" it is stated that ((
)). Thus a table((
)) is not necessary. If present, the table would simply show that no adjustments were necessary to the calculated dual loop and single loop SLMCPR values.
R[
)) The process for determining whether adjustments were required is documented in Reference 6 of the aforementioned attachment.
NRC Question 2 Provide description for the cause of the large increase of SLMCPR value from Cycle 15 to Cycle 16. Also, identify the major core design difference between Cycle 15 and Cycle 16 ((
Response
The calculated SLMCPR value for Cycle 16 is substantially higher than for Cycle 15 because the core MCPR distribution is significantly flatter. This fact is reflected in the increase ((
((GNF Proprietary Information )) page 1 of 2
((removed between double brackets))
_e' NRC Requests for Additional Information for February 11, 2003 Brunswick Steam Electric Plant, Unit No. 2 Docket No. 50-324/License No. DPR-62 Request For License Amendment Regarding Technical Specification 2.1.1.2, Reactor Core Safety Limits Minimum Critical Power Ratio Safety Limit
)) The conclusion is that requested Technical Specification SLMCPR value of 1.11 for dual loop operations is appropriate. The 1.13 value for single loop operation is also consistent with expectations for the Cycle 16 core.
Another aspect of the NRC request is to identify the major core design difference between Cycle 15 and Cycle 16, especially with regard to how these differences impact the increase in the calculated SLMCPR. First and foremost is the fact Cycle 16 was licensed to accommodate an additional 365 MWth relative to Cycle 15. To gain the extra energy requires a larger batch size (42.5% for Cycle 16 versus 39.3% for Cycle 15) and higher batch enrichment (4.24% for Cycle 16 versus 3.99% for Cycle 15). The result is that the fresh batch of fuel produces a higher fraction of the core power in Cycle 16 compared to Cycle 15 which means that the radial power distribution must be flattened to provide operating margin at the uprated power level. Evidence of this increased flatness is given in the fact that for the limiting point in the cycles that set the cycle SLMCPR, Cycle 15 at BOC has ((
)) whereas for Cycle 16 at EOR ((
)) In fact, for Cycle 16 at EOR, ((
)). The impact that this increase in the flatness of the MCPR has on the calculated SLMCPR was discussed in the previous paragraph.
((GNF Proprietary Information )) page 2 of 2
((removed between double brackets))
BSEP 03-0036 Enclosure 4 Typed Technical Specification Page - Unit 2
SLs 2.0 2.0 SAFETY LIMITS (SLs)
- 2. 1 SLs 2.1.1 Reactor Core SLs 2.1.1.1 With the reactor steam dome pressure < 785 psig or core flow < 10% rated core flow:
THERMAL POWER shall be - 23% RTP.
2.1.1.2 With the reactor steam dome pressure z,785 psig and core flow Ž 10% rated core flow:
MCPR shall be ; 1.11 for two recirculation loop operation or z 1.13 for single recirculation loop operation.
2.1.1.3 Reactor vessel water level shall be greater than the top of active irradiated fuel.
2.1.2 Reactor Coolant System Pressure SL Reactor steam dome pressure shall be
2.2 SL Violations With any SL violation, the following actions shall be completed within 2 hour2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />s:
2.2.1 Restore compliance with all SLs; and 2.2.2 Insert all insertable control rods.
Brunswick Unit 2 2.0-1 Amendment No. I