3F0912-07, Emergency Response Data System
| ML12270A370 | |
| Person / Time | |
|---|---|
| Site: | Crystal River |
| Issue date: | 09/19/2012 |
| From: | Rigsby M Duke Energy Corp, Progress Energy Florida |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| 3F0912-07 | |
| Download: ML12270A370 (8) | |
Text
PDuke EEnergy@
Crystal River Nuclear Plant Docket No. 50-302 Operating License No. DPR-72 Ref: 10CFR50, Appendix E September 19, 2012 3F0912-07 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001
Subject:
Crystal River Unit 3 - Emergency Response Data System
Dear Sir:
The purpose of this letter is to provide a 30 day report to the NRC required by 10CFR50, Appendix E, Section VI.3.a.
On September 10, 2012, Florida Power Corporation (FPC) implemented software modifications due to a design change that replaced airborne radioactivity monitors RM-A1 (Containment Purge Exhaust Duct) and RM-A2 (Auxiliary Building and Fuel Handling Area Exhaust Duct). This design change required that modifications be made, in part, to the Emergency Response Data System (ERDS) Data Point Library for Crystal River Unit 3 (CR-3).
The new airborne radioactivity monitors use two (2) noble gas channels per system instead of the three (3) noble gas channels per system used in the old airborne radioactivity monitors.
Data points W324, W325, W329 and W330 have been revised.
The high range noble gas information previously transmitted by data points W326 (RM-A1) and W331 (RM-A2) are now part of the information transmitted by data points W325 and W330.
Data points W326 and W331 will be re-used for non-ERDS purposes and are deleted from the CR-3 ERDS Data Point Library.
No new regulatory commitments are contained in this letter.
If you have any questions regarding this submittal, please contact Mr. Dan Westcott, Superintendent, Licensing and Regulatory Programs at (352) 563-4796.
Sincerely, Mark D. Rigsby Manager Support Services - Nuclear Crystal River Unit 3 Nuclear Plant MDR/dwh
Attachment:
CR-3 ERDS Data Point Library Changes xc:
Regional Administrator, Region II Senior Resident Inspector NRR Project Manager Progress Energy Florida, Inc.
Crystal River Nuclear Plant 15760 W. Power Line Street Crystal River, FL 34428
FLORIDA POWER CORPORATION CRYSTAL RIVER UNIT 3 DOCKET NUMBER 50 - 302 / LICENSE NUMBER DPR - 72 ATTACHMENT CR-3 ERDS DATA POINT LIBRARY CHANGES
U. S. Nuclear Regulatory Commission 3F0912-07 Attachment Page 1 of 6 9/10/2012 CR3 - Crystal River Unit 3 N/A EFF GAS RAD W324 RM-A1 N RB PURGE DUCT ACTIVITY Radioactivity of Released Gases A
pCi/cc N/A 1.OE-06 1.OE-02 N/A N/A S
1 N/A Auxiliary Building N/A N/A N/A Low N/A N/A N/A Yellow = Revised data.
U. S. Nuclear Regulatory Commission 3F0912-07 Attachment Page 2 of 6 09/10/2012 CR3 - Crystal River Unit 3 N/A EFF GAS RAD W325 RM-A1A RB PURGE DUCT ACTIVITY Radioactivity of Released Gases A
pCi/cc N/A 1.OE-03 1.OE+05 N/A N/A S
1 N/A Auxiliary Building N/A N/A N/A Low N/A N/A N/A Yellow = Revised data.
U. S. Nuclear Regulatory Commission 3F0912-07 Attachment Page 3 of 6
- U. S. Nuclear Regulatory Commission 3F0912-07 Attachment Page 4 of 6 09/10/2012 CR3 - Crystal River Unit 3 N/A EFF GAS RAD W329 RM-A2N AB/FH ACTIVITY Radioactivity of Released Gases A
pCi/cc N/A 1.OE-06 1.OE-02 N/A N/A S
1 N/A Auxiliary Building N/A N/A N/A Low N/A N/A N/A Yellow = Revised data.
- U. S. Nuclear Regulatory Commission 3F0912-07 Attachment Page 5 of 6 09/10/2012 CR3 - Crystal River Unit 3 N/A EFF GAS RAD W330 RM-A2A AB/FH ACTIVITY Radioactivity of Released Gases A
pCi/cc N/A 1.OE-03 1.OE+05 N/A N/A S
1 N/A Auxiliary Building N/A N/A N/A Low N/A N/A N/A Yellow = Revised data.
- U. S. Nuclear Regulatory Commission 3F0912-07 Attachment Page 6 of 6