Revised Reference for 50.83 Partial Site Release
ML19079A274
Person / Time
Site: Crystal River  Duke Energy icon.png
Issue date: 03/20/2019
From: Wilson I
Duke Energy Florida
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards
Shared Package
ML19086A067 List:
References
3F0319-03
Download: ML19079A274 (1)


Text

e.l_~ DUKE Crystal River Nuclear Plant 15760 W. Power Line Street

~ ENERGY Crystal River, FL 34428 Docket 50-302 Docket 72-1035 Operating License No. DPR-72 10 CFR 50.83(b)

March 20, 2019 3F0319-03 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001

Subject:

Crystal River Unit 3 - Revised Reference for 50.83 Partial Site Release

References:

1. CR-3 to NRG letter dated January 22, 2019, "Crystal River Unit 3 - Partial Site Release Request" (ADAMS Accession No. ML19022A076)

Dear Sir:

In accordance with 10 CFR 50.83(b), Duke Energy Florida, LLC (DEF), submitted a request for approval to remove a portion of the site from the Crystal River Nuclear Plant (CR3) Part 50 license (License No. DPR-72) (Reference 1). Specifically, DEF requested approval to remove the non-impacted survey units from its Part 50 license in accordance with 10 CFR 50.83(b), "Release of part of a power reactor facility or site for unrestricted use".

Attachment 3 to the above-mentioned submittal included a computer disk (CD) containing the non-NRG references. On this CD, document 15 (CR-SC-RPT-001 Final Report Rev 0) contained proprietary information marking on certain pages. This document has been revised to remove the proprietary marking and is being resubmitted as non-proprietary.

Attachment 1, of this letter, contains the CD with the new revised document.

This correspondence contains no new regulatory commitments.

If you have any questions regarding this submittal, please contact Mr. Mark Van Sicklen, Licensing Lead, Nuclear Regulatory Affairs, at (352) 501-3045.

Sincerely, 9 ~f0L--

lvan L. Wilson Manager - SAFSTOR Operations and Maintenance Crystal River Nuclear Plant ILW/mvs Attachments:

1. CD containing reference 15, CR-SC-RPT-001 Final Report Rev 1 xc: NMSS Project Manager Regional Administrator, Region I