MONTHYEAR3F1099-02, Monthly Operating Rept for Sept 1999 for Crystal River,Unit 3.With1999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Crystal River,Unit 3.With 3F0999-02, Monthly Operating Rept for Aug 1999 for Crystal River,Unit 3.With1999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Crystal River,Unit 3.With ML20210U5341999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Crystal River,Unit 3 3F0799-01, Monthly Operating Rept for June 1999 for Crystal River,Unit 3.With1999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Crystal River,Unit 3.With ML20210U5411999-06-30030 June 1999 Revised Monthly Operating Rept for June 1999 for Crystal River,Unit 3 ML20210U5601999-05-31031 May 1999 Revised Monthly Operating Rept for May 1999 for Crystal River,Unit 3 3F0699-07, Monthly Operating Rept for May 1999 for Crystal River,Unit 3.With1999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Crystal River,Unit 3.With ML20210U5631999-04-30030 April 1999 Revised Monthly Operating Rept for Apr 1999 for Crystal River,Unit 3 3F0599-04, Monthly Operating Rept for Apr 1999 for Crystal River Unit 3.With1999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Crystal River Unit 3.With 3F0499-04, Monthly Operating Rept for Mar 1999 for Crystal River Unit 3.With1999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Crystal River Unit 3.With 3F0399-03, Monthly Operating Rept for Feb 1999 for Crystal River Unit 3.With1999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for Crystal River Unit 3.With 3F0199-05, Monthly Operating Rept for Dec 1998 for Crystal River Unit 3.With1998-12-31031 December 1998 Monthly Operating Rept for Dec 1998 for Crystal River Unit 3.With 3F1298-13, Monthly Operating Rept for Nov 1998 for Crystal River,Unit 3.With1998-11-30030 November 1998 Monthly Operating Rept for Nov 1998 for Crystal River,Unit 3.With 3F1198-05, Monthly Operating Rept for Oct 1998 for Crystal River,Unit 3.With1998-10-31031 October 1998 Monthly Operating Rept for Oct 1998 for Crystal River,Unit 3.With 3F1098-06, Monthly Operating Rept for Sept 1998 for Crystal River Unit 3.With1998-09-30030 September 1998 Monthly Operating Rept for Sept 1998 for Crystal River Unit 3.With 3F0998-07, Monthly Operating Rept for Aug 1998 for Crystal River Unit 3.With1998-08-31031 August 1998 Monthly Operating Rept for Aug 1998 for Crystal River Unit 3.With 3F0898-02, Monthly Operating Rept for Jul 1998 for Crystal River,Unit 11998-07-31031 July 1998 Monthly Operating Rept for Jul 1998 for Crystal River,Unit 1 3F0798-01, Monthly Operating Rept for June 1998 for Crystal River Unit 31998-06-30030 June 1998 Monthly Operating Rept for June 1998 for Crystal River Unit 3 3F0698-02, Monthly Operating Rept for May 1998 for Crystal River Unit 31998-05-31031 May 1998 Monthly Operating Rept for May 1998 for Crystal River Unit 3 3F0598-07, Monthly Operating Rept for Apr 1998 for Crystal River Unit 31998-04-30030 April 1998 Monthly Operating Rept for Apr 1998 for Crystal River Unit 3 3F0498-07, Monthly Operating Rept for Mar 1998 for Crystal River,Unit 31998-03-31031 March 1998 Monthly Operating Rept for Mar 1998 for Crystal River,Unit 3 3F0398-05, Monthly Operating Rept for Feb 1998 for Crystal River, Unit 31998-02-28028 February 1998 Monthly Operating Rept for Feb 1998 for Crystal River, Unit 3 3F0298-06, Monthly Operating Rept for Jan 1998 for Crystal River,Unit 31998-01-31031 January 1998 Monthly Operating Rept for Jan 1998 for Crystal River,Unit 3 3F0198-05, Monthly Operating Rept for Dec 1997 for Crystal River,Unit 31997-12-31031 December 1997 Monthly Operating Rept for Dec 1997 for Crystal River,Unit 3 3F1297-02, Monthly Operating Rept for Nov 1997 for Crystal River,Unit 31997-11-30030 November 1997 Monthly Operating Rept for Nov 1997 for Crystal River,Unit 3 3F1197-02, Monthly Operating Rept for Oct 1997 for Crystal River, Unit 31997-10-31031 October 1997 Monthly Operating Rept for Oct 1997 for Crystal River, Unit 3 3F1097-03, Monthly Operating Rept for Sept 1997 for Crystal River,Unit 31997-09-30030 September 1997 Monthly Operating Rept for Sept 1997 for Crystal River,Unit 3 3F0997-08, Monthly Operating Rept for Aug 1997 for Crystal River1997-08-31031 August 1997 Monthly Operating Rept for Aug 1997 for Crystal River 3F0897-04, Monthly Operating Rept for Jul 1997 for Crystal River Unit 31997-07-31031 July 1997 Monthly Operating Rept for Jul 1997 for Crystal River Unit 3 3F0797-01, Monthly Operating Rept for June 1997 for Crystal River Unit 31997-06-30030 June 1997 Monthly Operating Rept for June 1997 for Crystal River Unit 3 3F0697-01, Monthly Operating Rept for May 1997 for Crystal River 31997-05-31031 May 1997 Monthly Operating Rept for May 1997 for Crystal River 3 3F0597-02, Monthly Operating Rept for Apr 1997 for Crystal River Unit 31997-04-30030 April 1997 Monthly Operating Rept for Apr 1997 for Crystal River Unit 3 3F0497-01, Monthly Operating Rept for Mar 1997 for Crystal River Unit 31997-03-31031 March 1997 Monthly Operating Rept for Mar 1997 for Crystal River Unit 3 3F0397-07, Monthly Operating Rept for Feb 1997 for Crystal River Unit 31997-02-28028 February 1997 Monthly Operating Rept for Feb 1997 for Crystal River Unit 3 3F0297-08, Monthly Operating Rept for Jan 1997 for Crystal River Unit 31997-01-31031 January 1997 Monthly Operating Rept for Jan 1997 for Crystal River Unit 3 3F0197-08, Monthly Operating Rept for Dec 1996 for Crystal River Unit 31996-12-31031 December 1996 Monthly Operating Rept for Dec 1996 for Crystal River Unit 3 3F1296-03, Monthly Operating Rept for Nov 1996 for Crystal River Unit 31996-11-30030 November 1996 Monthly Operating Rept for Nov 1996 for Crystal River Unit 3 3F1196-08, Monthly Operating Rept for Oct 1996 for Crngp1996-10-31031 October 1996 Monthly Operating Rept for Oct 1996 for Crngp 3F1096-03, Monthly Operating Rept for Sept 1996 for Crystal River Unit 31996-09-30030 September 1996 Monthly Operating Rept for Sept 1996 for Crystal River Unit 3 ML20117N5101996-08-31031 August 1996 Monthly Operating Rept for Aug 1996 for Crystal River Unit 3 3F0896-01, Monthly Operating Rept for Jul 1996 for Crystal River Unit 31996-07-31031 July 1996 Monthly Operating Rept for Jul 1996 for Crystal River Unit 3 3F0796-01, Monthly Operating Rept for June 1996 for Crystal River Unit 31996-06-30030 June 1996 Monthly Operating Rept for June 1996 for Crystal River Unit 3 3F0696-02, Monthly Operating Rept for May 1996 for Crystal River Unit 31996-05-31031 May 1996 Monthly Operating Rept for May 1996 for Crystal River Unit 3 3F0596-08, Monthly Operating Rept for Apr 1996 for Crystal River Unit 31996-04-30030 April 1996 Monthly Operating Rept for Apr 1996 for Crystal River Unit 3 3F0496-12, Monthly Operating Rept for Mar 1996 for Crystal River,Unit 31996-03-31031 March 1996 Monthly Operating Rept for Mar 1996 for Crystal River,Unit 3 3F0396-06, Monthly Operating Rept for Feb 1996 for Crystal River Unit 31996-02-29029 February 1996 Monthly Operating Rept for Feb 1996 for Crystal River Unit 3 3F0296-14, Monthly Operating Rept for Jan 1996 for Crystal River Unit 31996-01-31031 January 1996 Monthly Operating Rept for Jan 1996 for Crystal River Unit 3 3F0196-05, Monthly Operating Rept for Dec 1995 for Crystal River Unit 31995-12-31031 December 1995 Monthly Operating Rept for Dec 1995 for Crystal River Unit 3 3F1295-02, Monthly Operating Rept for Nov 1995 for Crystal River Unit 31995-11-30030 November 1995 Monthly Operating Rept for Nov 1995 for Crystal River Unit 3 3F1195-02, Monthly Operating Rept for Oct 1995 for Crystal River Unit 31995-10-31031 October 1995 Monthly Operating Rept for Oct 1995 for Crystal River Unit 3 1999-09-30
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20217G0191999-10-15015 October 1999 Safety Evaluation Concluding That Licensee Followed Analytical Methods Provided in GL 90-05.Grants Relief Until Next Refueling Outage,Scheduled to Start on 991001.Temporary non-Code Repair Must Then Be Replaced with Code Repair 3F1099-19, Part 21 Rept Re Damage on safety-grade Cable Provided to FPC by Bicc Brand-Rex Co.Damage Was Created During Cabling Process While Combining Three Conducters.Corrective Action Program Precursor Card PC99-2868 Was Initiated1999-10-13013 October 1999 Part 21 Rept Re Damage on safety-grade Cable Provided to FPC by Bicc Brand-Rex Co.Damage Was Created During Cabling Process While Combining Three Conducters.Corrective Action Program Precursor Card PC99-2868 Was Initiated ML20217B0931999-10-0606 October 1999 Part 21 Rept Re Damaged Safety Grade Electrical Cabling Found in Supply on 990831.Damage Created During Cabling Process While Combining Three Conductors Just Prior to Closing.Vendor Notified of Reporting of Issue ML20212L0881999-10-0404 October 1999 SER Accepting Licensee Requests for Relief 98-012 to 98-018 Related to Implementation of Subsections IWE & Iwl of ASME Section XI for Containment Insp for Crystal River Unit 3 ML20212J8631999-10-0101 October 1999 Safety Evaluation Supporting Licensee Proposed Alternatives to Provide Reasonable Assurance of Structural Integrity of Subject Welds & Provide Acceptable Level of Quality & Safety.Relief Granted Per 10CFR50.55a(g)(6)(i) ML20212E9031999-09-30030 September 1999 FPC Crystal River Unit 3 Plant Reference Simulator Four Year Simulator Certification Rept Sept 1995-Sept 1999 3F1099-02, Monthly Operating Rept for Sept 1999 for Crystal River,Unit 3.With1999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for Crystal River,Unit 3.With ML20212E6911999-09-21021 September 1999 Safety Evaluation Supporting Proposed EALs Changes for Plant Unit 3.Changes Meet Requirements of 10CFR50.47(b)(4) & App E to 10CFR50 ML20211L1321999-08-31031 August 1999 EAL Basis Document 3F0999-02, Monthly Operating Rept for Aug 1999 for Crystal River,Unit 3.With1999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Crystal River,Unit 3.With ML20212C1501999-08-31031 August 1999 Non-proprietary Version of Rev 0 to Crystal River Unit 3 Enhanced Spent Fuel Storage Engineering Input to LAR Number 239 ML20211B7291999-08-16016 August 1999 Rev 2 to Cycle 11 Colr ML20210P1111999-08-0505 August 1999 SER Accepting Evaluation of Third 10-year Interval Inservice Insp Program Requests for Relief for Plant,Unit 3 ML20210U5341999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Crystal River,Unit 3 ML20209F5601999-07-31031 July 1999 EAL Basis Document, for Jul 1999 3F0799-01, Monthly Operating Rept for June 1999 for Crystal River,Unit 3.With1999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Crystal River,Unit 3.With ML20210U5411999-06-30030 June 1999 Revised Monthly Operating Rept for June 1999 for Crystal River,Unit 3 3F0699-07, Monthly Operating Rept for May 1999 for Crystal River,Unit 3.With1999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Crystal River,Unit 3.With ML20210U5601999-05-31031 May 1999 Revised Monthly Operating Rept for May 1999 for Crystal River,Unit 3 ML20195C6271999-05-28028 May 1999 Non-proprietary Rev 0 to Addendum to Topical Rept BAW-2346P, CR-3 Plant Specific MSLB Leak Rates ML20196L2031999-05-19019 May 1999 Non-proprietary Rev 0 to BAW-2346NP, Alternate Repair Criteria for Tube End Cracking in Tube-to-Tubesheet Roll Joint of Once-Through Sgs 3F0599-04, Monthly Operating Rept for Apr 1999 for Crystal River Unit 3.With1999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Crystal River Unit 3.With ML20210U5631999-04-30030 April 1999 Revised Monthly Operating Rept for Apr 1999 for Crystal River,Unit 3 3F0499-04, Monthly Operating Rept for Mar 1999 for Crystal River Unit 3.With1999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Crystal River Unit 3.With ML20204D9661999-03-31031 March 1999 Non-proprietary Rev 1,Addendum a to BAW-2342, OTSG Repair Roll Qualification Rept 3F0399-04, Special Rept 99-01:on 990310,discovered Containment Tendons That Required Grease Addition in Excess of Prescribed Limits During Recent Insp Activites.Six Tendons Were Refilled with Appropriate Amount of Grease1999-03-10010 March 1999 Special Rept 99-01:on 990310,discovered Containment Tendons That Required Grease Addition in Excess of Prescribed Limits During Recent Insp Activites.Six Tendons Were Refilled with Appropriate Amount of Grease 3F0399-03, Monthly Operating Rept for Feb 1999 for Crystal River Unit 3.With1999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for Crystal River Unit 3.With ML20203A4381999-02-0303 February 1999 Safety Evaluation Supporting EAL Changes for License DPR-72, Per 10CFR50.47(b)(4) & App E to 10CFR50 ML20206E9891998-12-31031 December 1998 Kissimmee Utility Authority 1998 Annual Rept ML20206E9021998-12-31031 December 1998 Florida Progress Corp 1998 Annual Rept ML20206E9701998-12-31031 December 1998 Ouc 1998 Annual Rept. with Financial Statements from Seminole Electric Cooperative,Inc 3F0199-05, Monthly Operating Rept for Dec 1998 for Crystal River Unit 3.With1998-12-31031 December 1998 Monthly Operating Rept for Dec 1998 for Crystal River Unit 3.With ML20206E9261998-12-31031 December 1998 Gainesville Regional Utilities 1998 Annual Rept 3F1298-13, Monthly Operating Rept for Nov 1998 for Crystal River,Unit 3.With1998-11-30030 November 1998 Monthly Operating Rept for Nov 1998 for Crystal River,Unit 3.With 3F1198-05, Monthly Operating Rept for Oct 1998 for Crystal River,Unit 3.With1998-10-31031 October 1998 Monthly Operating Rept for Oct 1998 for Crystal River,Unit 3.With ML20155F4071998-10-31031 October 1998 Rev 2 to Pressure/Temp Limits Rept ML20155J2701998-10-28028 October 1998 Second Ten-Year Insp Interval Closeout Summary Rept 3F1098-06, Monthly Operating Rept for Sept 1998 for Crystal River Unit 3.With1998-09-30030 September 1998 Monthly Operating Rept for Sept 1998 for Crystal River Unit 3.With ML20206E9461998-09-30030 September 1998 Utilities Commission City of New Smyrna Beach,Fl Comprehensive Annual Financial Rept Sept 30,1998 & 1997 ML20206E9561998-09-30030 September 1998 City of Ocala Comprehensive Annual Financial Rept for Yr Ended 980930 ML20206E9101998-09-30030 September 1998 City of Bushnell Fl Comprehensive Annual Financial Rept for Fiscal Yr Ended 980930 ML20206E9811998-09-30030 September 1998 City of Tallahassee,Fl Comprehensive Annual Financial Rept for Yr Ended 980930 ML20195E3121998-09-30030 September 1998 Comprehensive Annual Financial Rept for City of Leesburg,Fl Fiscal Yr Ended 980930 3F0998-07, Monthly Operating Rept for Aug 1998 for Crystal River Unit 3.With1998-08-31031 August 1998 Monthly Operating Rept for Aug 1998 for Crystal River Unit 3.With ML20236W6501998-07-31031 July 1998 Emergency Action Level Basis Document 3F0898-02, Monthly Operating Rept for Jul 1998 for Crystal River,Unit 11998-07-31031 July 1998 Monthly Operating Rept for Jul 1998 for Crystal River,Unit 1 ML20236V8801998-07-30030 July 1998 Control Room Habitability Rept 3F0798-01, Monthly Operating Rept for June 1998 for Crystal River Unit 31998-06-30030 June 1998 Monthly Operating Rept for June 1998 for Crystal River Unit 3 ML20236Q4611998-06-30030 June 1998 SER for Crystal River Power Station,Unit 3,individual Plant Exam (Ipe).Concludes That Plant IPE Complete Re Info Requested by GL 88-20 & IPE Results Reasonable Given Plant Design,Operation & History 3F0698-02, Monthly Operating Rept for May 1998 for Crystal River Unit 31998-05-31031 May 1998 Monthly Operating Rept for May 1998 for Crystal River Unit 3 1999-09-30
[Table view] |
Text
. _ _ _ . _ . . . - __._. _ _ _ _ _ _ _ _ __ . _
.3 .
OPERATING DATA REPORT DOCKET NO.30-302 DAfg _1_mso -
COMPLETED SY n ri .ha rn TELEPHONE (904) 795-3802
- OPERATING.57AIU.S '
i 1. Unit Nanw:
Crystal River Unit 3 Notes Please note correction
. 2. Reporting Period: 12/1/84 - 12/31/84 (circled) of gross
- 3. Licensed Thermal Power (MWt p: 2544 generation for December.
j 4. Nansepiste Rating (Gross MWe): 890
- 3. Design Electrical Rating (Net MWe): 82s
]
j 6. Maximum Dependable Capedty (Gross MWe): 860 i
- 7. Maximum Dependable Capa ty (Net MWe): 821
- 8. If Changes occur in Capselty Ratings (Items Number 3 Through 7) Since Last Report. Give Reasons
- NA i ;
i '
i, NA i
- 9. Power Level To Which Restricted.lf2nygNet MWe):
- 10. Reasons For Restrictions.lf Any:
~-
- This Month Yr.to.Dete Cumulative
- 11. Hours in Reporting Period 744 8784 68424
- 12. Number of Hours Reactor Was Critical 744 _
8346.5 45915.7
- 13. Rosetor Reserve Shutdown Hours 0 0 1280.3
- 14. Hours Generstor On.Line 744 8298.8 44917.8
~
l$. Unit Reserve Shutdown Hours o o n I 16. Gross Thermal tnergy Generated (MWH) 1715240 19897K50 . 1018A1Aa5 17 Gross Electrical Energy Generated (MWH) C59765 D _
C 68000617 ( 347267977 ~
568890
~
- 18. Net Electrical Energy Generated (MWH) 6478928 32T96011
- 19. Unit Service Factor 100 % 94.5 % 65.6 %
- 20. Unit Aveliability Factor 100% 94.5 % 85.8%
- 21. Unit Capacity Factor (Using MDC Net) -
93.1 % 89.8% 60.7 %
- 22. Unit Capecity Factor (Using DER Net) Ot1% .__ -- AG AE -
An At
- 23. Unit Forced Outage Rete 0%
j j 24. Shutdowns Scheduled Over Next 6' Months IType. Date,and Duration of Each :
0.9% _
20.2 % ]
l Refuellne outare scheduled to berin h/9/95. anet tant 20 weelte.
i l 2$. If Shut Dow At End Of Report Period. Estimated Date of Startup: NA
- 26. Units la Test Status IPrior to Commerefal Operations: Forecast Achiesed
. INITIAL CRITICALITY 1/14/77 INITIAL ELECTRICITY -
1/30/77 COMMERCIAL OPER ATION -
3/12/77 DOklgt ,ge . ,.,c ,
b \
1
. l OPERATING DATA REPORT DOCKETNO. 50-302 DATE 7 /1 M COMPLETED BY 3. Grabarn TELEPHONE 1904) 795-3802 OPERATING STATUS
- 1. Unit Name:
Crystal River Unit 3 Notei
- 2. Reporting Period: 1/1/85 - 1/31/85
- 3. Licensed Thermal Power (MW ): 2544
- 4. Namepiste Rating (Gross MWe): 890
- 5. Design Electrical Rating (Net MWe): _ 9"
- 6. Maximum Dependable capacity (Gross MWe): 860
- 7. Maximum Dependable Capacity (Net MWe): 821
- 8. If Changes Occur in Capacity Ratings (Items Number 3 Through 7) Since Last Report. Give Reasons:
NA
- 9. Power Level To Which Restricte41f1'n y Net MWe): NA
- 10. Reasons For Restrictions.If Any: A 4
1 This Month Yr to.Ds'e Cumulative
- 11. Hours in Reporting Period 744 744 ~69168
- 12. Number Of Hours Resetor Was Critical 744 744 46659.7
, 13. Reactor Reserve Shutdown Hour, 0 0 1280.3 l 14. Hours Generator On-Line 744 744 45661.8 j 15. Unit Reserve Shutdown Hours 0 _
0 0
- 16. Gross Thermal Energy Generated (MWH) 1571111 1571111 -
103232998 .
- 17. Gross Electrical Energy Generated (MWH) 550098 , , , 550098 35277315
- 18. Net Electrical Energy Generated (MWH) 521380 521380 _. 33517391-
- 19. Unit Service Factor 100 % 100 % 66.0%
l
- 20. Unit Availability Factor 100 % 100 % 66.0 %
- 21. Unit Capacity Factor (Using MDC Neti 85.4 % 85.4 % 61.0 %
- 22. Unit Capacity Factor (Using DER Net) 84.9 % 84.9 % 58.7 % ;
- 23. Unit Forced Outage Rate 0% 0% 19.9% __
- 24. Shutdowns Scheduled Over Next 6 Mo.iths (Type. Dete.and Duration of Each):
Refueling Outage scheduled to begin 3/9/85 and last 20 Weeks.
- 25. If Shut Down At End Of Report Period, Estimated Date of Startup: NA
- 26. Uniti In Test Status (Prior to Commerelal Operation): Forecast Achieved INITIAL CRITICALITY -
1/14/77 INITIAL ELECTRICITY . 1/30/77 COMMERCIAL OPERATION 3/13/77 (0/77)
/
l
- - _ - . 1
. AVERACE DA!LY UNIT POWER LEVEL DOCKET NO. 50-302 UNIT PLORP-3 __
DATE 2/1/85 COMPLETED BY D. Graham TELEPHONE (904) 795-3802 MONTH January 1985 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe. Net) (gwe. Net) 1 767 728 17 2 -
765 ,, 737 3 747 i, 698 4 728 -
20 -- 722 5 687 680 6 -- 730 -
22 693 7 715 08I 23 g 720 678 34 9
718 23 -- 665 I 704 10 -
26 662 706 11 27 __
649 12 728 23 641 13 716 632 39 _
14 730 30 625 is 724 3g 633 16 720
! INSTRUCTIONS i
On this format.hst the average daih uni: powei leselin MWe Net for cash day m the 'cri rting month.C. impute to the flearest whole megawJtt.
(UI77 3 3
I l /
..o-._.. - _ . _ .__ ._- - _ _ _ . _ - - _
l ..
i IBOCET NO. 02 - i UNIT SHU1 DOWNS AND F0WER REDUCDONS ,
UNIT NAME _ .CRP-3 DATE 2/4/85 COMPT ETED BY R- A Raeurart I
kEFORT MONTil 1/85 1Et.EFle0NE (904) 795-3802 i
- , .5 E 3g E Licenec [v, cLw raine a rue,eceive N.s. Ikage r. gg jg5 I: vent g,7 E 'S O
Actism to H wO
$E cE jis g Repast 't Picsent Recurrence 6
85-01 8581IS S 0.0 F 5 NA RC FUELXX End of f#rel life. Power coastdown began.
i l
l t
1 E . 3 4 F: Itwed Reasant: 80eelsud. Exhibst G . hiseractions 5: SIwdeded A-Fquspawee Faslose(Emplain) I-teasamal fin Prepasassun ed Dasa B-Maisstessace of Test 2-leanaal Scrasi. Ents) Skecis few livnice C-Itefeeling 3.Assuseussc Scrmen. Escal Repi=i tI.ER) Fue 4 NtlREG-D-Regulasexy lleseristion 4Otises (Explain 6 016Ii E-Operaisir Training & lxrnse Fxassimatiums F-Admenmarative 5 G4perational Eer.= (Emplaml Exinbis I- Some Soviec r8/77) IlCoher(Emplain)
=
~
MONTHLY OPERATIONAL SU.WJtY STATDGNI DOCKET No. 50-302 UNIT FLCRP-3 DATE 2/4/85 i
COMPLETED BY 5. A. Stewart TELEPHONE (904) 795-3802 MONTH January 1985 St.HMARY STATEMENT: Crystal River 3 operated normally with no outages during the month.
The plant began reducing power due to the end of cycle power coast-down.
I e
4 e
e 4
8
/
_ _ .. . . . _ _- ~ _ . - - - - _ _ _ _ _ _ _ - . -
N e *
.**),
$g . . . ,
- p. .
Florida Power C O R P O A AT 10 N February 8,1983 3F0283-08 Mr. Richard C. DeYoung. Director Offlee of Inspection and Enforcement U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20335
Subject:
Crystal River Unit 3 Docket No.30-302 Operating License No. DPR-72 Monthly Operating Report Dear S!rt Attached are twelve (12) copies of the Crystal River Unit 3 January 1983 Monthly Operating Report and corrected report for December 1984 These reports are submitted in accordance with Technical Specification 6.9.1.6.
Sincerely, G. R. Westafer Manager, Nuclear Operations Licensing and Fuel Management AEF/feb Attachments cc Dr. 3. Nelson Grace Regional Administrator, Region 11 Office of Inspection & Enforcement sts1GW33 oMGl# #3 g7[6 U.S. Nuclear Regulatory Commiss!on 101 Marietta Street N.W., Sulte 2900 Atlanta, GA 30323 certi j By 9 8 l
.-