05000461/LER-2016-001

From kanterella
Jump to navigation Jump to search
LER-2016-001, 1 OF 4
Clinton Power Station, Unit 1
Event date: 01-20-2016
Report date: 03-18-2016
Reporting criterion: 10 CFR 50.73(a)(2)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident

10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition
Initial Reporting
ENS 51669 10 CFR 50.72(b)(3)(v)(D), Loss of Safety Function - Mitigate the Consequences of an Accident, 10 CFR 50.72(b)(3)(ii)(B), Unanalyzed Condition
4612016001R00 - NRC Website

Reported lessons learned are incorporated into the licensing process and fed back to industry.

Send comments regarding burden estimate to the FOIA, Privacy and Information Collections Branch (T-5 F53), U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001, or by Internet e-mail to Infocollects.Resource@nrc.gov, and to the Desk Officer, Office of Information and Regulatory Affairs, NEOB-10202, (3150-0104), Office of Management and Budget, Washington, DC 20503. If a means used to impose an information collection does not display a currently valid OMB control number, the NRC may not conduct or sponsor, and a person is not required to respond to, the information collection.

PLANT AND SYSTEM IDENTIFICATION

General Electric -- Boiling Water Reactor, 3473 Megawatts Thermal Rated Core Power Energy Industry Identification System (EllS) codes are identified in text as [XX].

EVENT IDENTIFICATION

Continuous Containment Purge Exhaust Fan Trip due to Unvalidated Assumptions in Work Planning Resulted in an Unanalyzed Condition of Primary to Secondary Containment Differential Pressure and Safety System Functional Failure A. Plant Operating Conditions Prior to the Event:

Unit: 1 Event Date: 1/20/2016 Mode: 1 Mode Name: Power Operation

B. DESCRIPTION OF EVENT

Event Time: 1311 Central Time Reactor Power: 099 percent On January 17, 2016 at 1544 Operations de-energized 4160/480 Volt Unit Substation [USS] K (0AP52E) due to a loud crackling noise heard coming from the unit substation. Troubleshooting Work Order (WO) 1892378 was created to inspect the transformer [XFMR] located in the unit substation to determine the cause of the noise.

At 2214 on January 17, 2016, Clearance Order (C/0) 130969 was hung to support the transformer inspection which placed the Main Feeder breaker [BKR] OAP52E-3B in the Racked Out position.

On January 19, 2016 the Electrical Maintenance Manager approached Electrical Maintenance Planning in regards to performing Preventive Maintenance Work Order (PMWO) 1575170 Clean and Inspect Unit Substation `K.' scheduled in July 2016 in conjunction with the troubleshooting WO 1892378.

Electrical Maintenance requested that the work planner incorporate specific steps from the Clean and Inspect PMWO 1575170 into the current troubleshooting package WO 1892378 so that the PMWO could be credited. While adding the requested steps into the troubleshooting WO, the work planner noticed that an existing job step stated "Coordinate with Ops to ensure all breakers are open/racked out". Because the work planner believed that this was a duplicate of a requested step, the work planner believed the prerequisite conditions would be met and did not need to be added into the WO task being planned.

Procedure WC-AA-104, Integrated Risk Management, Attachment 8, Risk Screening/Mitigation Plan was completed, but the need for an OPS review was not noted and therefore not completed. The form identified Auxiliary Power (AP) system impacts but did not take into account the Containment Building Ventilation (VR) system effects. The work activity was not properly screened for risk and there was no reference for ensuring validation of initial conditions prior to commencing the work under WO 1892378.

Clinton Power Station, Unit 1 05000461 On January 20, 2016 the Electrical Maintenance Department (EMD) was preparing to perform the Clean and Inspect WO 1892378. EMD supervision contacted the Operations Work Control Supervisor (WCS) to request all breakers on Unit Substation K be opened and racked out. The WCS dispatched operators to Unit Substation K and opened all the breakers, but did not rack the breakers out. Since the Clean and Inspect WO was being performed under a clearance order and the bus was de-energized, Operations indicated to EMD the breakers could be racked out by them.

The EMD technicians proceeded to rack out the breakers to enable the breakers to be removed. The racking out of breaker OAP52E-5D for Continuous Containment Purge (CCP) "A" exhaust fan [FAN], 1VRO7CA, disconnected the'B' auxiliary contact that is used to provide the start permissive signal for the CCP "B" Exhaust Fan, 1VRO7CB. This caused 1VRO7CB to shutdown/trip and resulted in Operations receiving Main Control Room (MCR) annunciator 5043-2A for Unexpected Automatic Trip of Running Continuous Containment Purge Supply or Exhaust Fan.

At 1311, Primary to Secondary Containment differential pressure was reported to be +0.411 psid. The Technical Specifications (TS) Limiting Condition for Operation (LCO) 3.6.1.4, Primary Containment Pressure, condition states, "Primary containment,to secondary containment differential pressure shall be greater than or equal to -025 psid and less than or equal to +0.25 psid.

This event caused CPS to enter a one hour Required Action A.1 under TS LCO 3.6.1.4, due to primary to secondary containment differential pressure being greater than +0.25 psid.

At 1317, Operations completed shutdown of CCP per site procedure CPS 3408.01, CONTAINMENT BUILDING DRYWELL HVAC (VR, VQ).

At 1320, breaker OAP52E-5D was racked back into the Unit Substation.

At 1327,. Operations completed startup of CCP per site procedure CPS 3408.01.

At 1339, Primary to Secondary Containment differential pressure was reported to be +0.24 psid and improving.

Primary to Secondary Containment differential pressure was restored within the required TS LCO 3.6.1.4 conditions and the Required Action A.1 was exited at 1339. Event Notification#51669 was transmitted to the NRC on January 20, 2016 at 1731.

C. CAUSE OF EVENT

An Issue Report (IR) was entered into the station's Corrective Action Program as IR 2614832. The station did not validate assumptions which resulted in an inadequate work package. Additionally, procedure OP-CL-108-101-1003, Operations Department Standards and Expectations, step 4.10.2 was not followed to ensure Shift Management reviews were performed along with two Senior Reactor Operators (SR0s) and approval by the Shift Manager.

D. SAFETY ANALYSIS

This event is reportable in accordance with 10 CFR 50.73(a)(2)(ii)(B) as an unanalyzed condition and 10 CFR 50.73(a)(2)(v)(D) as a condition that could have prevented fulfillment of a safety function.

The secondary containment pressure is kept slightly negative relative to the atmospheric pressure to prevent leakage to the atmosphere.

The primary containment to secondary containment differential pressure can affect the initial containment internal pressure. The initial pressure limitation requirements ensure that peak primary containment pressure for a Design Bases Accident (DBA) Loss of Coolant Accident (LOCA) does not exceed the design value of 15 psig and that peak negative pressure for an inadvertent containment spray event does not exceed the design value of 3.0 psid. This event resulted in a loss of Primary to Secondary Containment Differential Pressure safety function due to Primary to Secondary Containment differential pressure being outside the initial conditions for a Design Basis Accident Loss of Coolant Accident.

No actual consequences occurred as a result of these conditions.. Containment did not exceed the peak _ primary containment pressure design value of 15 psig or exceed the peak negative pressure design value of value 3 psid.

E. CORRECTIVE ACTIONS

Primary to Secondary Containment Differential Pressure was restored within the TS LCO requirements.

Corrective Actions scheduled to be performed include 1) Update the Maintenance Planner Checklist to ensure steps are created to validate initial conditions for each new emergent task, 2) Perform a read and sign with all active Operations Senior Reactor Operators to reinforce the requirements of OP-CL-108-101-1003 and MA-AA-716-011, Work Execution and Close Out, 3) Implement recommendations from a review of the current Operator Aid on breaker cubicle doors, and 4) Develop and present a case study on this event to Maintenance Planning personnel.

F. PREVIOUS SIMILAR OCCURRENCES

Clinton Power Station had a similar event occur on November 9, 1999 documented in station Condition Report CR 1-99-11-077, involving automatic trip of CCP supply fan B and an unplanned entry into ITS Required Actions caused by maintenance activities. The maintenance work order package

  • at the time- - not have an impact matrix, nor did it identify the potential to cause the fan trip within any of the job steps. One of the corrective actions from this event was to affix an Operator Aid to the compartment door of the breaker. A corrective action from the January 20, 2016 event is to implement recommendations from a review of the current Operator Aid since this Operator Aid may not have been as effective as it could have been.

G. COMPONENT FAILURE DATA

Not applicable since this was a human performance related event.