| Q | CCA | Title |
---|
05000445/FIN-2014404-01 | 2014Q3 | | Security |
05000445/FIN-2014004-03 | 2014Q3 | P.2 | Maintenance of a Standard Action Level Scheme for Main Steam Line Monitors |
05000445/FIN-2014004-04 | 2014Q3 | | Failure to Install an Insulated Bushing on a Generator Current Transformer Circuit Results in an Automatic Reactor Trip |
05000445/FIN-2014004-01 | 2014Q3 | H.8 | Failure to Establish Goals and Monitor the Performance of the Uninterruptible Power Supply Air Conditioning System |
05000445/FIN-2014004-02 | 2014Q3 | | Inadequate Acceptance Criteria for Inservice Testing of Auxiliary Feedwater Discharge Check Valves |
05000445/FIN-2014404-02 | 2014Q3 | | Security |
05000446/FIN-2014005-01 | 2014Q4 | H.11 | Failure to Follow Procedure for Boundary Valve Leakage Testing |
05000446/FIN-2014005-02 | 2014Q4 | H.7 | Failure to Follow the Troubleshooting Activities Procedure in a Plant Transient |
05000445/FIN-2015001-01 | 2015Q1 | | Failure to Evaluate Operability When Breeching Hazard Barriers |
05000446/FIN-2015001-02 | 2015Q1 | | Failure to Have an Adequate Procedure for Vendor Information |
05000445/FIN-2015001-03 | 2015Q1 | H.5 | Failure to Follow Work Planning Procedure |
05000445/FIN-2015001-04 | 2015Q1 | H.12 | Failure to Follow Procedure Damages a Centrifugal Charging Pump |
05000446/FIN-2015001-07 | 2015Q1 | H.9 | Inadequate Centrifugal Charging Pump Lubricating Oil Pump Installation Procedure |
05000445/FIN-2015404-01 | 2015Q1 | H.1 | Security |
05000445/FIN-2015001-05 | 2015Q1 | H.12 | Failure to Provide an Accurate Shipping Manifest |
05000445/FIN-2015001-06 | 2015Q1 | H.13 | Failure to Follow Procedure for Addressing Significant Conditions Adverse to Quality |