| Q | CCA | Title |
---|
05000416/FIN-2015003-01 | 2015Q3 | | Failure to Have Appropriate Instructions for Preventative Maintenance on the Division II Diesel Generator Fuel Rack Control Lever |
05000416/FIN-2015405-01 | 2015Q3 | | Security |
05000416/FIN-2015004-02 | 2015Q4 | H.14 | Failure to Timely Enter Technical Specification Surveillance Requirement 3.0.1 |
05000416/FIN-2015007-03 | 2015Q4 | S.4(o) | Lack of Coordination of Division III HPCS Switchgear 127N Undervoltage Relays |
05000416/FIN-2015008-04 | 2015Q4 | | Failure to Make Required Event Notification |
05000416/FIN-2015007-08 | 2015Q4 | | Incomplete and Inaccurate Response to NRC Bulletin 88-04 |
05000416/FIN-2015007-07 | 2015Q4 | | Failure to Update the Final Safety Analysis Report |
05000416/FIN-2015007-05 | 2015Q4 | | Failure to Maintain a Safety-Related Cable Tray Overfill Analysis Record |
05000416/FIN-2015004-03 | 2015Q4 | | Failure to Make a Required Eight-Hour Report for Loss of Safety Function |
05000416/FIN-2015008-03 | 2015Q4 | H.12 | Failure to Declare Secondary Containment Inoperable Based on Failed Surveillance Testing |
05000416/FIN-2015404-03 | 2015Q4 | | Security |
05000416/FIN-2015404-02 | 2015Q4 | | Security |
05000416/FIN-2015404-01 | 2015Q4 | | Security |
05000416/FIN-2015004-04 | 2015Q4 | | Failure to Establish Adequate Maintenance Instructions to Perform Work Activities on the Division III Diesel Generator Overspeed Trip Limit Switch |
05000416/FIN-2015004-01 | 2015Q4 | H.6 | Failure to Have Appropriate Instructions for Preventative Maintenance on the Division I Diesel Generator Simulated Run |
05000416/FIN-2015301-01 | 2015Q4 | H.8 | Inadequate Plant Operating Procedures with Eight Examples |
05000416/FIN-2015008-02 | 2015Q4 | P.1 | Failure to Promptly Initiate Condition Reports |
05000416/FIN-2015008-01 | 2015Q4 | P.1 | Failure to Enter a Condition Adverse to Quality into the Corrective Action Program |
05000416/FIN-2015007-11 | 2015Q4 | H.12 | Failure to Implement Equipment Control Procedures for Loose Items in Containment |
05000416/FIN-2015007-10 | 2015Q4 | P.6 | Failure to Ensure Equipment Operability and Functionality of Allowable Alternating Current Frequency Range |
05000416/FIN-2015007-09 | 2015Q4 | | Failure to Obtain a License Amendment for Use of Probabilistic Methods to Evaluate Tornado Missile Hazards |
05000416/FIN-2015007-06 | 2015Q4 | | Failure to Perform Surveillance Requirement 3.8.1.9 |
05000416/FIN-2015007-04 | 2015Q4 | H.8 | Failure to Identify and Address Impacts of Revised Calculation Output Data |
05000416/FIN-2015007-02 | 2015Q4 | H.6 | Failure to Ensure that Electrical Interrupting Devices are Rated for Available Fault Current Levels |
05000416/FIN-2015007-01 | 2015Q4 | | Failure to Ensure Safety-Related Alternating Current and Direct Current Equipment Operability and Functionality at Maximum Allowable Voltage Levels |
05000416/FIN-2016404-01 | 2016Q1 | | Security |
05000416/FIN-2016404-02 | 2016Q1 | | Security |