Title | Project Manager Instructed Plant Workers to Reach Across a Contamination Boundary Without Radiation Protection Approval |
Description | During an NRC investigation and subsequent in-office inspection completed on May 13, 2008, a violation of NRC requirements was identified. In accordance with the NRC Enforcement Policy, the violation is listed below: Technical Specification 5.4.1.a states, that written procedures shall be established, implemented, and maintained covering the applicable procedures recommended in Regulatory Guide 1.33, Revision 2, Appendix A, February 1978. Regulatory Guide 1.33, Appendix A, Section 7.e (1), specifies procedures for Access Control to Radiation Areas Including a Radiation Work Permit System. Columbia Generating Station Procedure GEN-RPP-04, Entry into, Conduct in, and Exit from Radiologically Controlled Areas, Revision 14, states, in part, Do not reach over, or cross contaminated area boundaries without RP approval. Contrary to the above, during repair of the HPCS-P-1 flange on June 16, 2007, a project manager instructed plant workers to reach across a contamination boundary without radiation protection approval. This is a Severity Level IV violation. (Supplement IV |
Site: | Columbia |
---|---|
Report | IR 05000397/2008008 Section 2OS1 |
Date counted | Jun 30, 2008 (2008Q2) |
Type: | TEV: Severity level IV |
cornerstone | Or Safety |
Identified by: | NRC identified |
Inspection Procedure: | IP 71121.01 |
Inspectors (proximate) | R Caniano |
INPO aspect | |
' | |
Finding - Columbia - IR 05000397/2008008 | |||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Columbia) @ 2008Q2
| |||||||||||||||||||||||||||||||||||||||||||||