05000397/FIN-2008002-01
From kanterella
Jump to navigation
Jump to search
Finding | |
|---|---|
| Title | Failure to Take Adequate Corrective Actions to Address Deficient Emergency Procedure |
| Description | An NRC identified noncited violation of Technical Specification 5.4.1.a was identified for an inadequate emergency support Procedure PPM 5.5.26, Overriding RHR [Residual Heat Removal] Shutdown Cooling Return Valve Isolations, Revision 5. The deficient procedure could have resulted in portions of the RHR Trains A and B injection lines inadvertently draining during emergency response to an anticipated transients without scram event. Although Energy Northwest identified the deficiency with Procedure PPM 5.5.26 in June 2006 and had taken action to implement a procedure change, it was not until the inspectors prompted Energy Northwest regarding status of the procedure change and lack of apparent timeliness in issuing a revision to the procedure that Energy Northwest issued the revision. Procedure PPM 5.5.26, Revision 6, was issued on February 6, 2008. As a result of the value added by the inspectors, this finding is considered to be NRC identified. The finding was more than minor because it was a procedure quality issue which affected the mitigating systems cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, implementation of Procedure PPM 5.5.26 during an anticipated transients without scram condition could have resulted in an inadvertent draining of RHR and subsequent damage to RHR piping and supports during subsequent initiation of injection. The finding was determined to be of very low risk significance (Green) because the finding did not represent an actual loss of safety function, did not represent a loss of system safety function, was not a design or qualification deficiency that resulted in a loss of operability, and was not risk significant due to external initiating events. The deficiency associated with Procedure PPM 5.5.26 would only occur during an anticipated transients without scram which is a non-design bases accident or event. A crosscutting aspect in problem identification and resolution with a corrective action program component P.1.d] was identified in that the inadequate procedure, although entered into the corrective action program, was not corrected in a timely manner commensurate with safety. This was attributed to a shortage of qualified operations department procedure writer |
| Site: | Columbia |
|---|---|
| Report | IR 05000397/2008002 Section 1R04 |
| Date counted | Mar 31, 2008 (2008Q1) |
| Type: | NCV: Green |
| cornerstone | Mitigating Systems |
| Identified by: | NRC identified |
| Inspection Procedure: | IP 71111.04 |
| Inspectors (proximate) | R Cohen Z Dunham C Johnson |
| CCA | P.3, Resolution |
| INPO aspect | PI.3 |
| ' | |
Finding - Columbia - IR 05000397/2008002 | |||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Columbia) @ 2008Q1
| |||||||||||||||||||||||||||||