| Q | CCA | Title |
---|
05000390/FIN-2009004-01 | 2009Q3 | H.2(a) H.6 | Failure to Incorporate Existing Design Criteria Into Temporary Secondary Containment Boundary Doors |
05000390/FIN-2009004-02 | 2009Q3 | P.2 | Inadequate Corrective Actions to Preclude Additional Temporary Secondary Containment Boundary Doors Failure |
05000390/FIN-2009005-02 | 2009Q4 | | Failure to Adequately Update the UFSAR for the Removal of the Additional Diesel Generator Unit. |
05000390/FIN-2009005-01 | 2009Q4 | H.2 | Failure to Implement Analysis for Failed Auxiliary Charging Pumps |
05000390/FIN-2010002-03 | 2010Q1 | | Failure to Submit Complete and Accurate Information for a Requested License Amendment |
05000390/FIN-2010002-01 | 2010Q1 | H.4 H.5 | Failure to Assure that Test Requirements Were Satsified Following a Design Change |
05000390/FIN-2010002-02 | 2010Q1 | H.13 | Failure to Establish Adequate Instructions or Procedure for Determining Vital Inverter Frequency |
05000390/FIN-2010003-03 | 2010Q2 | | B-train Main Control Room Chiller Temperature Control Valve Failure |
05000390/FIN-2010006-02 | 2010Q2 | | Worst Case 6900 VAC Bus Voltage in Design Calculations |
05000390/FIN-2010006-01 | 2010Q2 | | Inadequate Assessment of Seismic Qualification of ERCW Strainers |
05000390/FIN-2010003-01 | 2010Q2 | H.4 H.5 | Failure to Assure that Adequate Test Requirements Were Developed and Implemented Following a Repair |
05000390/FIN-2010003-02 | 2010Q2 | H.11 H.12 | Lack of Procedure Implementation Results in 1B EDG being started with 15 Cylinder Plugs Open |
05000390/FIN-2010402-01 | 2010Q2 | | Security |