05000348/FIN-2016003-01
From kanterella
Jump to navigation
Jump to search
Finding | |
|---|---|
| Title | |
| Description | An NRC-identified Severity Level IV NCV of 10 CFR 50.9(a), Completeness and accuracy of information, and an associated Green NCV of 10 CFR 50.48(c) and National Fire Protection Association Standard (NFPA) 805, Section 3.9.1, was identified for the licensees failure to accurately evaluate and report non-compliance with code requirements for the design and installation of the Unit 1 pre-action sprinkler system 1A-36. The licensees failure to comply with code requirements for the design and installation of the Unit 1 pre-action sprinkler system, 1A-36 was a performance deficiency. The licensee entered the issue into their corrective action program (CR 10261278). The performance deficiency was more than minor because it was associated with the protection against external factors (i.e. fire) attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the inadequate design and installation of the sprinkler system represented a degradation of a fire suppression component which degraded the fire protection defense in depth element to rapidly detect and suppress fires that occur. The inspectors determined that the finding was of very low safety significance (Green) because the affected fixed fire suppression system would still be able to suppress a fire such that no additional equipment important to safety would be affected by a fire. The inspectors determined the cause of this finding was not associated with a cross-cutting area because it was not reflective of current licensee performance. |
| Site: | Farley |
|---|---|
| Report | IR 05000348/2016003 Section 1R05 |
| Date counted | Sep 30, 2016 (2016Q3) |
| Type: | NCV: Green |
| cornerstone | Mitigating Systems |
| Identified by: | NRC identified |
| Inspection Procedure: | IP 71111.05 |
| Inspectors (proximate) | D Bacon J Dymek K Miller P Niebaum R Baldwin S Sandal |
| Violation of: | 10 CFR 50.9 10 CFR 50.48 |
| INPO aspect | |
| ' | |
Finding - Farley - IR 05000348/2016003 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Farley) @ 2016Q3