05000321/FIN-2012008-01 | 2012Q3 | | Failure to Report a Degraded Primary Safety Barrier per 10 CFR 50.72(b)(3)(ii)(A) |
05000321/FIN-2012008-05 | 2012Q3 | | Failure to Provide Appropriate Acceptance Criteria for EDG Air-Start System Check Valves |
05000321/FIN-2012008-04 | 2012Q3 | | Failure to Incorporate Appropriate Test Acceptance Criteria to Assure Satisfactory Steady State EDG Performance |
05000321/FIN-2012008-03 | 2012Q3 | | Failure to Ensure Adequacy of Intake Structure Ventilation Design |
05000321/FIN-2012008-02 | 2012Q3 | H.7 | Failure to Adequately Account for Potential Pump Discharge Check Valve Back-leakage |
05000321/FIN-2012004-04 | 2012Q3 | H.12 | Failure to follow clearance procedures for returning the A main control room air conditioning unit to service following maintenance |
05000321/FIN-2012004-03 | 2012Q3 | P.5 | Failure to establish adequate preventative maintenance for the safety related main control room air conditioning units |
05000321/FIN-2012004-02 | 2012Q3 | H.9 | Licensed Operator Requalification Annual Operating Test Administration Issues |
05000321/FIN-2012004-01 | 2012Q3 | H.8 | Failure to follow transient combustible control requirements within the sites intake structure. |
05000321/FIN-2012005-01 | 2012Q4 | | Low Voltage Safety-related Cables Subjected to Water Submersion |
05000321/FIN-2012005-03 | 2012Q4 | H.7 | Installation of a transformer for the TSC cooling coil and condensing unit control circuit not adequately designed to provide full system load |
05000321/FIN-2012005-02 | 2012Q4 | | Failure to Report a Degraded Primary Safety Barrier in accordance with 10 CFR 50.72 and 10 CFR 50.73 |
05000321/FIN-2013002-02 | 2013Q1 | H.14 | Unit 1 Under Vessel Leak Source Not Identified |
05000321/FIN-2013002-01 | 2013Q1 | H.9 | Failure to perform appropriate post maintenance test on 2A EDG |
05000321/FIN-2013201-04 | 2013Q2 | | Security |
05000321/FIN-2013201-03 | 2013Q2 | H.7 | Security |
05000321/FIN-2013201-02 | 2013Q2 | H.5 | Security |
05000321/FIN-2013201-01 | 2013Q2 | H.8 | Security |
05000321/FIN-2013003-02 | 2013Q2 | | Operation with Potential to Drain Reactor Pressure Vessel in Mode 5 Without Secondary Containment |