Finding | |
---|---|
Title | Licensee-Identified Violation |
Description | TS 5.4.1.a requires written procedures be established, implemented and, maintained covering the activities specified in Regulatory Guide 1.33, Appendix A. Items 2g and 4a of Appendix A requires procedures for general power operation and operation of the reactors recirculation system to be established and implemented. Contrary to the above, Unit 2 operated at a core flow higher than that allowed on the power/flow map described in licensee procedure 34GO-OPS-005-2, Power Changes. This issue was documented in the licensees corrective action program as CR 2009108237. Because the finding is associated with the fuel barrier and sufficient fuel thermal limit margin was maintained during the time core flow was outside the bounds of the power/flow map, this finding is of very low safety significance. |
Site: | Hatch |
---|---|
Report | IR 05000321/2010003 Section 4OA7 |
Date counted | Jun 30, 2010 (2010Q2) |
Type: | NCV: Green |
cornerstone | Barrier Integrity |
Identified by: | Licensee-identified |
Inspection Procedure: | |
Inspectors (proximate) | S Shaeffer A Nielsen S Walker T Steadham R Lewis E Morris P Niebaum R Williams D Hardage J Dymek |
INPO aspect | |
' | |
Finding - Hatch - IR 05000321/2010003 | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Finding List (Hatch) @ 2010Q2