05000301/LER-2010-003, Point Peach, Unit 2, Regarding Technical Specification Required Shutdown

From kanterella
Jump to navigation Jump to search
Point Peach, Unit 2, Regarding Technical Specification Required Shutdown
ML110390083
Person / Time
Site: Point Beach NextEra Energy icon.png
Issue date: 02/07/2011
From: Meyer L
Point Beach
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NRC 2011-001 8 LER 10-003-00
Download: ML110390083 (4)


LER-2010-003, Point Peach, Unit 2, Regarding Technical Specification Required Shutdown
Event date:
Report date:
Reporting criterion: 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown

10 CFR 50.73(a)(2)(vii), Common Cause Inoperability

10 CFR 50.73(a)(2)(viii)(A)

10 CFR 50.73(a)(2)(viii)(B)
3012010003R00 - NRC Website

text

February 7,201 1 NRC 201 1-001 8 10 CFR 50.73 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555 Point Beach Nuclear Plant, Unit 2 Docket 50-301 Renewed License No. DPR-27 Licensee Event Report 3011201 0-003-00 Technical Specification Required Shutdown Enclosed is Licensee Event Report (LER) 30112010-003-00 for Point Beach Nuclear Plant (PBNP), Unit 2. This LER documents the completion of a Technical Specification required shutdown. Pursuant to 10 CFR 50.73(a)(2)(i)(A), the event is reportable as a completion of any nuclear plant shutdown required by the plant's Technical Specifications.

This submittal contains no new or revised regulatory commitments.

If you have questions or require additional information, please contact Mr. James Costedio at 9201755-7427.

Very truly yours, NextEra Energy Point Beach, LLC Enclosure cc:

Administrator, Region Ill, USNRC Project Manager, Point Beach Nuclear Plant, USNRC Resident Inspector, Point Beach Nuclear Plant, USNRC PSCW NextEra Energy Point Beach, LLC, 6610 Nuclear Road, Two Rivers, WI 54241

LICENSEE EVENT REPORT (LER) 20.2203(a)(3)(i)

II] 50.73(a)(2)(vii) 50.73(a)(2)(viii)(A) 50.73(a)(2)(viii)(B)

A degraded field connection for the F-6 control rod caused control rod fuse 21 to blow, which ultimately resulted in the urgent and non-urgent alarms being received during performance of control rod exercises and the inability to complete the surveillance test. Following the shutdown, when a connection on a patch panel in containment was opened, checked and re-seated, the fault condition cleared as validated by numerous megger readings.

Additional corrective actions include inspections of the connections during each unit's 201 1 refueling outage. These actions are being tracked in the site's corrective action program.

This 60-day licensee event report is being submitted in accordance with the requirements of 10 CFR 50.73(a)(2)(i)(A), the completion of any nuclear plant shutdown required by the plant's Technical Specifications.

NCR FORM 366 (10-2010)

Point Beach Nuclear Plant - Unit 2

Event Description

On December 13, 201 0, at 1205 CST, preparations for a Technical Specification (TS) required shutdown were initiated on Unit 2. TS Limiting Condition for Operation (LCO) 3.1.4, Rod Group Alignment Limits, was not met as a result of Surveillance Requirement (SR) 3.1.4.2 not being met. The shutdown was subsequently completed at 1703 CST, December 13, 201 0.

This 60-day licensee event report is being submitted in accordance with the requirements of 10 CFR 50.73(a)(2)(i)(A), the completion of any nuclear plant shutdown required by the plant's Technical

Event Analysis

On December 10,201 0, at 1350 CST, during performance of TS surveillance procedure TS-06, Rod Exercise Test, rod control urgent and non-urgent failure alarms occurred while stepping Control Bank B rods [ A 4 out.

Power cabinet 2AC had an urgent alarm locked in, and power cabinets 2AC and 1 BD had the non-urgent alarm locked in. These alarms were verified locally in the Unit 2 rod drive room. Unit 2 remained at 100%

Initial troubleshooting and repair reset the power supply crowbars and replaced the blown fuse, FU 21. The test was recommenced on December 10,2010, at 2212 CST and Control Bank B was stepped out one step as procedurally required with no alarms. When Control Bank B was subsequently stepped inward one step, both rod control urgent and non-urgent failure alarms were received. Both of the times that Control Bank B rods failed to move, the movable gripper coil power supply fuse (FU 21) blew for control rod F-6. When the F-6 control rod fuse failed, it resulted in outward rod motion of one additional step. Troubleshooting continued through the weekend of December I I and 12,2010.

Discussions with NSSS support engineers suggested a short between cables or a short to ground affecting the F-6 control rod movable gripper coil circuit which caused the FU 21 fuse to blow. Initial megger checks from cable to station ground determined that the resistance was as low as 5 ML!. Subsequent megger readings varied but were as low as 18 L!.

At 21 43 CST on December 12,201 0, the surveillance procedure for Control Banks A, C and D and Shutdown Banks A and B was completed. However, the failure of Control Bank B rods to step in correctly resulted in the inability to satisfy SR 3.1.4.2. Unit 2 was shut down on December 13, 2010, when LC0 3.1.4 was not met because of SR 3.1 -4.2 not being met. Troubleshooting and repairs had been unsuccessfully attempted between receipt of the alarms on December 10,201 0, and the shutdown on December 13,201 0.

Safety Significance

When the F-6 control rod fuse failed, it resulted in outward rod motion of one additional step. The outward step occurred outside of the active fuel region and had no impact on core reactivity. Additionally, control rods tripped as required during the shutdown on December 13, 201 0. Thus, the safety significance of the event was low. There was no impact on the health and safety of the public as a result of this event. This is not a safety system functional failure.

Point Beach Nuclear Plant - Unit 2 A degraded field connection for the F-6 control rod caused control rod fuse 21 to blow, which ultimately resulted in the urgent and non-urgent alarms being received during performance of control rod exercises and the inability to complete the surveillance test. Following the shutdown, when a connection on a patch panel in containment was opened, checked and re-seated, the fault condition cleared as validated by numerous megger readings indicating the field connection had become degraded.

Corrective Actions

The following corrective actions were taken:

e All system cards were tested, repaired, and returned to the system.

e All rod control cables were tested, and cable issues were addressed.

e All +24 and -24 V DC power supplies in all power cabinets were replaced.

0 Post-maintenance testing demonstrated that the system now performs as designed.

The following corrective actions will be taken and are being tracked in the site's corrective action program:

0 Unit 2 control rod drive mechanism (CRDM) head and patch panel connections will be inspected during the Unit 2 spring 201 1 refueling outage.

e Unit I CRDM head and patch panel connections will be inspected during the fall 201 I refueling 0

MeggarIECAD testing will be added to the CRDM PM schedule.

e The Unit 1 24 V DC power supplies will be replaced during the fall 201 1 refueling outage.

Previous Occurrences

Failed Components Identified: