05000286/FIN-2016003-01 | 2016Q3 | P.1 | Failure to Adequately Assess Fire Risk Associated with Maintenance on the Unit 3 Appendix R Diesel Generator |
05000247/FIN-2016003-07 | 2016Q3 | P.3 | Inadequate Control of Floor Drains to Minimize Groundwater Contamination |
05000247/FIN-2016003-02 | 2016Q3 | | Missed Inspections on Automatic Voltage Regulator Cards Results in Emergency Diesel Generator Failure to Run |
05000286/FIN-2016003-03 | 2016Q3 | H.14 | Untimely Corrective Actions to Address Degraded Automatic Voltage Regulator Cards |
05000247/FIN-2016003-04 | 2016Q3 | H.8 | Entry into a High Radiation Area without Radiological Briefing |
05000247/FIN-2016003-05 | 2016Q3 | H.5 | Failure to Maintain Radiation Exposure ALARA During Unit 2 Reactor Cavity Liner Repairs |
05000247/FIN-2016003-06 | 2016Q3 | H.5 | Failure to Maintain Two Qualified AC Sources of Offsite Power |
05000286/FIN-2016009-01 | 2016Q4 | H.12 | 345 kV Insulator Failure Causes Reactor Trip |
05000247/FIN-2016404-01 | 2016Q4 | H.9 | Security |
05000286/FIN-2016004-01 | 2016Q4 | | Inadequate Preventive Maintenance Classification of Starting Air Relief Valve Led to Failure |
05000286/FIN-2016004-02 | 2016Q4 | H.12 | Inadequate Operability Evaluation of Leak in Service Water Pump Discharge Pipe |
05000286/FIN-2016004-03 | 2016Q4 | H.14 | Failure to Provide Indication of a Bypassed RPS Channel During Testing |
05000247/FIN-2016004-04 | 2016Q4 | H.2 | Failure to Follow RPS Logic Train B Actuation Logic Test |
05000247/FIN-2017405-01 | 2017Q1 | H.8 | Security |
05000286/FIN-2017001-01 | 2017Q1 | P.2 | Inadequate Standard Operation Procedure for the Backup Spent Fuel Pool Cooling System |
05000286/FIN-2017001-02 | 2017Q1 | P.2 | Operation in Mode 1 with Pressurizer Code Safety Valves in an Inoperable Condition |