05000220/FIN-2012002-01 | 2012Q1 | H.14 | DID Not Correctly Implement Procedure During Power Supply Transfer |
05000220/FIN-2012002-02 | 2012Q1 | H.7 | Inadequate Torque Applied to Shutdown Cooling Isolation Valve Closure Bolts |
05000220/FIN-2012003-01 | 2012Q2 | H.7 | Loss of Spent Fuel Pool Cooling due to Inadequate Procedure. |
05000220/FIN-2012003-02 | 2012Q2 | P.3 | Inadequate Corrective Action for Instrument Fill and Vent Activities |
05000220/FIN-2012003-03 | 2012Q2 | H.7 | Inadequate Special Operating Procedure for Loss of Spent Fuel Pool Cooling |
05000220/FIN-2012004-01 | 2012Q3 | H.2 | Inadequate Implementation of Operational Decision Making Issues Monitoring Plan for EPR Results in Reactor Scram |
05000220/FIN-2012004-02 | 2012Q3 | H.7 | \\\"Inadequate Evaluation and Implementation of Design Modifications to the Turbine
Gland Seal Supply System |
05000220/FIN-2012004-03 | 2012Q3 | H.2 | Inadequate Installation Instructions for Control Rod Blade Storage Rack |
05000220/FIN-2012004-04 | 2012Q3 | H.5 | Failure to Maintain Radiation Exposure ALARA During Refueling Activities |
05000220/FIN-2012005-01 | 2012Q4 | H.2 | Failure to Develop Adequate Inspection Requirements for Main Transformer Modification Results in Reactor Scram |
05000220/FIN-2012005-02 | 2012Q4 | P.2 | Inadequate Post Maintenance Test Results in Subsequent Failure of 11 CREVS Fan |
05000220/FIN-2012404-01 | 2012Q4 | | Security |
05000220/FIN-2012005-03 | 2012Q4 | | Assessment of Containment Leakage Due to Containment Isolation Valve Failure |