 Issue dateTitle
ML20302A28225 September 20203 to Updated Final Safety Analysis Report, Section 3, Design Criteria - Structures, Components, Equipment, and Systems, Part 3 of 3
L-19-189, 54010-CALC-01, Davis-Besse Nuclear Power Station: Evaluation of Risk Significance of Permanent ILRT Extension.29 July 201954010-CALC-01, Davis-Besse Nuclear Power Station: Evaluation of Risk Significance of Permanent ILRT Extension.
ML18114A1673 May 2018Request to Extend Enforcement Discretion Provided in Enforcement Guidance Memorandum 15-002 for Tornado-Generated Missile Protection Non-Conformances Identified in Response to RIS 2015-06, Tornado Missile Protection:
L-18-108, Request to Extend Enforcement Discretion Provided in Enforcement Guidance Memorandum 15-002 for Tornado-Generated Missile Protection Non-Conformance Identified in Response to Regulatory Issue Summary 2015-06, Tornado Missile....12 April 2018Request to Extend Enforcement Discretion Provided in Enforcement Guidance Memorandum 15-002 for Tornado-Generated Missile Protection Non-Conformance Identified in Response to Regulatory Issue Summary 2015-06, Tornado Missile....
05000346/LER-2017-00118 September 2017Emergency Diesel Generator Fuel Oil Storage Tank Vents Not Adequately Protected from Tornado-Generated Missiles
LER 17-001-00 for Davis-Besse, Unit 1, Regarding Emergency Diesel Generator Fuel Oil Storage Tank Vents Not Adequately Protected from Tornado-Generated Missiles
ML17017A34031 January 2017Safety Evaluation Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-051 and EA-12-049
L-16-322, Revision 31 to Updated Final Safety Analysis Report, Section 10 (Redacted)21 November 2016Revision 31 to Updated Final Safety Analysis Report, Section 10 (Redacted)
IR 05000346/201600722 June 2016NRC Component Design Bases Inspection Report 05000373/2016007; 05000346/2016007
ML15280A2876 October 2015Additional Information for the Advisory Committee on Reactor Safeguards Review of License Renewal Application
IR 05000346/201500810 April 2015IR 05000346/2015008, 01/26/2015 - 02/27/2015; Davis-Besse Nuclear Power Station; Component Design Bases Inspection
ML15082A1251 April 2015Final TIA Response-Laminar Cracks in the Shield Building
ML14136A48616 May 2014Fenoc'S Answer Opposing Intervenors'S Motion for Admission of Contention No. 6
ML14122A02921 April 2014Comment (21) of Keven Kamps on License Renewal Application for Davis-Besse Nuclear Power Station, Unit 1; Draft Supplemental Generic Environmental Impact Statement
ML14080A18421 March 2014Summary of Webinar Meeting to Discuss NRC Inspection Activities Associated with the Davis-Besse Nuclear Power Station Installation of Two New Steam Generators
ML12254A13810 September 2012NRC Staff'S Answer to Intervenors' Fifth Motion to Amend And/Or Supplement Proposed Contention No. 5 (Shield Building Cracking)
ML12131A03110 May 2012NRC Staff Transmittal of Inspection Report Regarding Cracks Found in the Shield Building for Davis-Besse, Unit 1
ML14251A6108 May 2012Riley E-mail Re Current Licensing Basis
ML12187A4768 May 2012E-mail from Timothy Riley on NRC Inspection Report for Davis Besse
IR 05000346/20120077 May 2012IR 05000346-12-007 (Drs), 07/18/2011 - 04/17/2012, Davis-Besse Nuclear Power Station; Reactor Vessel Head Replacement and Shield Building Cracking
ML11091056620 April 2011Request for Additional Information for the Review of the Davis-Besse Nuclear Power Station, Unit 1, License Renewal Application
IR 05000346/200900719 February 2010IR 05000346-09-007; 11/03/2009 - 01/14/2010; Davis-Besse Nuclear Power Station; Component Design Bases Inspection
ML07029025030 January 2007Withdrawal of an Amendment Request
ML07031031226 January 2007Withdrawal of License Amendment Application to Change Design Requirements for Tornado Missile Protection
ML06262044523 October 2006Draft Request for Additional Information Regarding Diesel Requirements for Tornado Missile Protection
ML06108012625 May 2006Request for Additional Information Related to Tornado Missile Protection
ML05014027611 January 2005License Amendment Application to Change Design Requirements for Tornado Missile Protection (License Amendment Request No. 04-0024)
IR 05000346/20040103 August 2004IR 05000346-04-010(DRS) on 6/28/2004 - 7/2/2004 for Davis-Besse Nuclear Power Station; Evaluations of Changes, Experiments or Tests, and Permanent Plant Modifications
ML0416200771 June 2004(Revised) Minutes of Internal Meeting of the Davis-Besse Nuclear Power Station IMC 0350 Oversight Panel (Revised Comment)
ML0406800705 March 2004IR 05000346-03-010(DRS); 03/17/2003 - 01/07/2004; Davis-Besse Nucler Power Station; Corrective Action Program Implementation Effectiveness
ML03240043525 August 2003G20030508 - James P. Riccio Ltr Re Petition Pursuant to 10 CFR 2.206: a Request for Enforcement Action Against First Energy Nuclear Operating Company (Davis-Besse)
ML03260098725 August 2003G20030508 - James P. Riccio Ltr Re Petition Pursuant to 10 CFR 2.206: a Request for Enforcement Action Against First Energy Nuclear Operating Company (Davis-Besse)
ML03071016610 February 2003Questions for Davis-Besse Manual Chapter 0350 Panel from the Union of Concerned Scientists
ML03049004310 February 2003Questions for Davis-Besse Manual Chapter 0350 Panel
ML20212D35021 September 1999Forward Copy of Final Accident Sequence Precursor Analysis of Operational Event at Plant,Unit 1 on 980624,reported in LER 346/98-006
ML20134F18130 January 1997Proposed Tech Specs Re Possession & Use of SNM as Reactor Fuel
ML20215C23929 August 1986Responds to Violations Noted in Insp Rept 50-346/85-40. Corrective Actions:Sys Engineering Group Formed to Develop Detailed Sys Knowledge,Including Design Basis & Surveillance Test Requirements
ML20206T10430 June 1986Safety Evaluation Report Related to the Restart of DAVIS-BESSE Nuclear Power Station,Unit 1,FOLLOWING the Event of June 9,1985.Docket No. 50-346.(Toledo Edison Company)
NUREG-1117, Forwards Draft NUREG-1117, SER Re Restart of Davis-Besse Nuclear Power Station, Per Response to NRC & Info Submitted W/Course of Action.Schedule for Resolution of Open Issues Listed in Section 1 Requested29 January 1986Forwards Draft NUREG-1117, SER Re Restart of Davis-Besse Nuclear Power Station, Per Response to NRC & Info Submitted W/Course of Action.Schedule for Resolution of Open Issues Listed in Section 1 Requested
ML20083Q40713 April 1984Responds to 840326 Request for Addl Info Re Tornado Missile Protection for Chlorine Detectors.Missiles Considered for Tornado Analysis Described in Table 3.5-2 of Fsar/Usar & Reviewed in Section 3.5.2 of SER (NUREG-0136)
ML20023C59529 April 1983Discusses Results of Analysis Performed to Determine Probability of Postulated Tornado Generated Missile Contacting Gratings Covering Ventilation Openings. Probability Acceptably Small.Condition Not RO
ML19319C10229 July 1977Safety Evaluation Supporting Change to Tech Specs
ML19329B18117 December 1975Responds to NRC 751114 Ltr.Forwards Info Re Tornado Missile Protection
ML19329C46717 July 1970Review of Seismic Design Criteria for Davis-Besse.