Semantic search

Jump to navigation Jump to search
 Discovered dateReporting criterionTitleEvent description
ENS 5496827 October 2020 21:08:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessLoss of Emergency Plan Dose Assessment Capability

At 1608 CDT on 10/27/2020, Wolf Creek Unit 1, operating at 100 percent rated thermal power in Mode-1, experienced a loss of the on-site wired corporate network. During actions to restore, it was discovered the ability to access the dose assessment software was compromised due to a security program. Access to the program was established after some time using Wi-Fi connectivity, but was not able to be accessed without network access. Actions are being taken to rectify. The NRC Resident Inspector has been notified. The licensee believes this was not a cyber-event and that the Emergency Response Data System was available, but couldn't verify. Should the Wi-Fi network access be lost, there's no capability to perform a dose assessment. Standalone laptops are being provided but have not been placed onsite yet. That should restore the ability to have dose assessment capability at all times.

  • * * UPDATE ON 10/27/2020 AT 2220 FROM JOHN WEBER TO OSSY FONT * * *

The licensee notified the NRC that the network has been restored to the Technical Support Center building and the emergency plan dose assessment group was capable of performing dose assessment. The licensee also noted that the group is able to perform dose assessment without the network, if needed. The network is still unavailable in the control room. The licensee confirmed that ERDS is available. The licensee will notify the NRC Resident Inspector. Notified R4DO (Pick).

ENS 5392411 March 2019 12:51:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessPlanned Communication System MaintenanceOn 03/11/2019 planned maintenance activities will be performed on the Beaver Valley Power Station (BVPS) Unit 2 Digital Radiation Monitoring System's (DRMS) Communications System. The work includes upgrades to the DRMS hardware, software and computer peripherals. Components to be upgraded under this planned maintenance include: Redundant Servers, Operator Console, Health Physics Office Console/Workstation, Printers and Portable Mass Storage/Backup and Computer peripherals necessary to interface with the computer system. This planned upgrade on the Unit 2 DRMS Communications System will result in the loss of Unit 2 radiological monitoring capability in the Control Room and on the Plant Computer System (PCS). Neither the Emergency Response Facilities nor the Emergency Response Data System (ERDS) will receive radiological data. No actual radiation monitors are affected. The scheduled work duration is approximately three weeks. When the DRMS is out of service for the upgrade, compensatory actions will be in place. Radiation monitors will be continuously monitored for any increases in radiation levels. The Unit 2 Shift Manager will be notified of any increase in radiation monitor readings, including exceeding Emergency Action Levels (EAL). This is an eight-hour, non-emergency notification for a Loss of Emergency Assessment Capability. This event is reportable in accordance with 10 CFR 50.72(b)(3)(xiii) because the upgrade to the DRMS Communications System will result in the loss of the Unit 2 radiological monitoring capability in the Control Room and to the Unit 2 Plant Computer System that affects the functionality of an Emergency Response Facility. There is no impact on the health and safety of the public or plant personnel. The NRC Resident Inspector has been notified. The licensee is currently in a Technical Specification Action Statement, Limiting Condition for Operation for spent fuel pool radiation monitor and leakage rate monitor.
ENS 5304130 October 2017 06:47:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessSevere Weather Causes Loss of Power to Support BuildingsThere was a loss of power from the local grid which did not affect the power block. The support buildings lost power and a UPS failed which affects computers, switching, and telephones. This includes a loss of the Emergency Response Data System (ERDS). The Joint Information Center and Emergency Operations Facility were not affected. Though this is a major loss of communications ability, alternate communications methods are available. The licensee notified the NRC Resident Inspector.
ENS 5210418 July 2016 19:50:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessLoss of Offsite Communications CapabilityThis telephone notification is provided in accordance with the Exelon Reportability manual, 'Major Loss of Emergency Preparedness Capabilities', and 10 CFR 50.72(b)(3)(xiii). On July 18, 2016 at 1500 CDT, it was determined during testing of the Everbridge ERO (Emergency Response Organization) notification system that the system would not notify the corporate EOF (Emergency Operations Facility) individuals if the system had been activated. This constitutes a loss of offsite communication capability. Exelon and Everbridge have identified and corrected this issue. A follow-up test of the LaSalle Everbridge ERO notification system was completed satisfactorily on July 18, 2016 at 2100. The Emergency Response Data System (ERDS) capability was not lost. The licensee has notified the (NRC) Senior Resident Inspector of the issue. Compensatory measures were in place during this event.
ENS 5210218 July 2016 20:00:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessLoss of Offsite Communications CapabilityTesting of the Everbridge ERO (Emergency Response Organization) notification system identified the system cannot notify all ERO individuals. This constitutes a loss of offsite communications capability. The issue has subsequently been reported resolved by the vendor. Emergency Response Data System (ERDS) capability was not lost. The Everbridge system capability loss for the common ERF (EOF at Cantera) was identified at approximately 1500 CDT on July 18, 2016. Site and EOF testing verified resolution at 2029 CDT. This event is reportable under 10 CFR 50.72(b)(3)(xiii) as a loss of communications capability. The licensee will notify the NRC Resident Inspector.
ENS 5210118 July 2016 20:00:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessLoss of Offsite Communications CapabilityTesting of the Everbridge ERO (Emergency Response Organization) notification system identified the system was not able to notify all ERO individuals. This constitutes a loss of offsite communications capability. The issue was subsequently reported resolved by the vendor and site testing has verified resolution at 2037. The Everbridge system capability loss for Limerick was identified at approximately 1600 EDT on July 18, 2016, due to a loss of system communications. Emergency Response Data System (ERDS) capability was not lost. This event is reportable under 10 CFR 50.72(b)(3)(xiii) as a loss of communications capability. The NRC Resident inspector has been notified.
ENS 5210018 July 2016 20:00:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessLoss of Offsite Communications CapabilityDuring testing of the Everbridge Emergency Response Organization (ERO) notification system, it was found that the system may not have notified corporate ERO members within the required ten minutes from system initiation. This constitutes a loss of offsite communication capabilities. The Everbridge vendor has since restored and successfully tested the system. Additionally, the site successfully conducted an ERO call-in drill using the same Everbridge notification system. The Emergency Response Data System was not affected. This event is reportable per 10 CFR 50.72(b)(3)(xiii) as a loss of communications capability. The NRC Resident Inspector has been notified. The requirement is to have all ERO personnel receive the page within ten minutes. Compensatory measures were instituted while the system was not functional. The system was returned to service at 2100 CDT following repair and testing.
ENS 5209918 July 2016 19:50:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessLoss of Offsite Communications CapabilityTesting of the Everbridge ERO (Emergency Response Organization) notification system identified that the system cannot notify all ERO individuals. This constitutes a loss of offsite communications capability. The issue has subsequently been reported resolved by the vendor and both site testing and common ERF (Emergency Response Facility) (EOF (Emergency Operations Facility) at Cantera) has verified resolution. The Everbridge system capability loss for Quad Cities was identified at approximately 1450 (CDT) hours on July 18, 2016, due to an undetermined loss of system communications, which is currently being investigated. Emergency Response Data System (ERDS) capability was not lost. The Everbridge system capability loss for the common ERF (EOF at Cantera) was identified at approximately 1500 (CDT) on July 18, 2016. This event is reportable under 10 CFR 50.72(b)(3)(xiii) as a loss of EP offsite communications capability. The NRC Resident inspector has been notified. The site was developing compensatory measures when the event was terminated.
ENS 5209818 July 2016 20:00:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessLoss of Offsite Communications CapabilityTesting of the Everbridge ERO (Emergency Response Organization) notification system identified that the system cannot notify all ERO individuals. This constitutes a loss of offsite communications capability. Compensatory measures (ERO phone lists) were put in place. The Everbridge system capability loss for Dresden Station was identified at 1500 CDT on July 18, 2016, due to an undetermined loss of system communications. Emergency Response Data System (EROS) capability was not lost. This event is reportable under 10 CFR 50.72(b)3(xiii) as a major loss of communication capability. On July 18, 2016 at 1957 CDT, an Everbridge ERO call in drill was initiated and verified successful at 2030 CDT. The NRC Resident Inspector has been notified. Some of the ERO personnel did not receive a test page. The requirement is to have all ERO personnel receive the page within ten minutes and to be fully staffed within one hour.
ENS 517179 February 2016 14:12:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessPlanned Maintenance of the Plant Computer System

Planned maintenance of the Plant Computer System (PCS) will cause a loss of emergency assessment capability. Beginning February 9, 2016, PCS data will not be available to the following Comanche Peak Nuclear Power Plant (CPNPP) facilities due to planned PCS software modifications: -Emergency Operations Facility (EOF) -Backup EOF -Operations Support Center The Emergency Response Data System (ERDS) will also be unavailable. The planned maintenance of the PCS is being reported as a loss of assessment capability in accordance with 10 CFR 50.72(b)(3)(xiii) because the duration is expected to be more than 72 hours and the data to the Backup EOF is also affected. CPNPP has compensatory measures in place to ensure timely emergency classification, protective action recommendation and emergency notification, as needed. The PCS modification is expected to be complete by February 18, 2016. A follow-up ENS (Emergency Notification System) communication will be made when the EOF assessment capability is restored. The Licensee has notified the NRC Resident Inspector.

  • * * UPDATE FROM RAUL MARTINEZ TO STEVEN VITTO ON 02/18/2016 AT 1541 EST * * *

The planned maintenance of the Comanche Peak Plant Computer System (PCS) that began on February 9, 2016 is complete. Assessment capability in the following facilities was restored effective 1300 (CST) February 18, 2016: -Emergency Operations Facility (EOF) -Backup EOF -Operations Support Center The Emergency Response Data System availability has also been restored. The Licensee has notified the NRC Resident Inspector. Notified the R4DO(Werner).

ENS 5126627 July 2015 14:02:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessPlanned Outage for Plant Computer SystemsOn July 27, 2015 at 0902 (CDT), (the site commenced) a planned outage of the Emergency Response Data System (ERDS) and Safety Parameter Display System (SPDS), referred to as 'plant computer'. The unavailability of ERDS and SPDS could significantly affect the site's ability to respond to an emergency if one were to occur. During this time, Operations will be utilizing the site's procedures 1C1.5 and 2C1.5, 'OPERATION WITHOUT COMPUTER', which requires additional operators for monitoring of equipment affected by the loss of the plant computer. Additionally, as this is a planned outage, the work week schedule has been modified to ensure limited interactions required by Operations during this time frame. The site expects ERDS and SPDS to be operational 1200 July 28, 2015. This event is reportable under 10 CFR 50.72(b)(3)(xiii), Any event that results in a major loss of emergency assessment capability, offsite response capability, or offsite communications capability (e.g., significant portion of Control Room indication, Emergency Notification System (ENS), or Offsite Notification System). The ENS and Offsite Notification System are not affected by this planned outage. The health and safety of the public are not impacted by this planned outage. The NRC Resident Inspector has been informed.
ENS 5122313 July 2015 12:30:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessPrimary and Backup Meteorological Towers to Be Removed from Service for Upgrade

On July 13, 2015, planned activities will be performed to upgrade the Vogtle Electric Generating Plant Meteorological Towers and its communication equipment. The emergency response data system will be affected. The work will be completed within approximately 5 days. This activity requires the meteorological tower to be out of service greater than 72 hours rendering equipment used for emergency assessment non-functional. The TSC and EOF remain functional during the outage. Compensatory measures exist within emergency plan implementing procedures to obtain meteorological tower data via Savannah River Site and with the National Weather Service. Meteorological information will be relayed via the emergency notification system to the NRC Operations Center. This event is reportable per 10 CFR 50.72(b)(3)(xiii) for 'any event that results in a major loss of emergency assessment capability.' The Emergency Response Organization has been notified of the upgrade and necessary compensatory actions. The NRC Resident Inspector has been notified.

  • * * UPDATE FROM DANIEL MONAHON TO DONALD NORWOOD AT 2013 EDT ON 7/18/2015 * * *

Vogtle primary and backup Meteorological Towers have been returned to service and functionality of equipment has been restored. The NRC Resident Inspector will be notified. Notified R2DO (King).

ENS 5040727 August 2014 13:05:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessLoss of Communications Due to Power Supply FailureThis notification is being made in accordance with 10 CFR 50.72(b)(3)(xiii) due to a loss of communications capability. On August 27, 2014 at 0805 hours CDT the internal phone system, Emergency Notification System (ENS), and Emergency Response Data System (ERDS) became nonfunctional because of a power supply failure. The ERDS has been restored to service and work is currently in progress to restore the internal phone system and ENS. It has not been determined at the time of this notification as to when the internal phones system and ENS will be restored to a fully functional status. The NRC Resident Inspector has been informed.
ENS 5022525 June 2014 05:00:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessVarious Telecommunication Lines and Erds Outage for Planned Maintenance

Planned preventive maintenance will render parts of telephone system and Emergency Response Data System (ERDS) nonfunctional. As a result, this represents a loss of emergency communications capability and is reportable under 10 CFR 50.72(b)(3)(xiii). The maintenance is scheduled to begin on 6/25/2014 at 00:00 (CDT), and is expected to last approximately 5 hours. During this maintenance window, various communication connections will be intermittently interrupted for short periods of time. Affected communication connections include some local telephone company lines, Federal Telephone System, ERDS, the Monticello's NRC office, and automatic ring down lines to the state of Minnesota's Emergency Operations Center. During the planned maintenance window, communications to offsite will be available via radios, cell phones, and satellite communications. This ensures that the plant can adequately communicate with the NRC, state, and local agencies to ensure protection of the health and safety of the general public. The NRC Resident Inspector has been notified of the planned telecommunications maintenance. Licensee also notified the Minnesota State Duty Officer and the Wright and Sherburne County Sheriff dispatchers.

  • * * UPDATE PROVIDED BY DAMON HESSIG TO JEFF ROTTON AT 1823 EDT ON 06/25/2014 * * *

At 0500 (CDT) on 6/25/2014, planned maintenance on the Monticello telecommunications system was completed. At 1630 (CDT) on 6/25/2014, testing of all telecommunications was completed. All systems are functioning properly. The NRC Resident Inspector has been notified that the telecommunications system is functional. The Minnesota State Duty Officer and the Wright and Sherburne County Sheriff dispatchers have been notified that the telecommunications system is functional. Notified R3DO (Lara).

ENS 4985123 February 2014 17:00:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessIntegrated Plant Computer System Removed from Service for Planned Maintenance

(On) February 23, 2014, at approximately 1200 (EST), the Fermi 2 Integrated Plant Computer System (IPCS) was removed from service outside of the Control Room to support planned system maintenance. The Safety Parameters Display System (SPDS) and Emergency Response Data System (ERDS) reside on the IPCS platform and (was rendered) out of service when the IPCS (was) removed from Emergency Response Facilities (ERFs). These systems will be unavailable to all Emergency Response Facilities (ERFs) for approximately 50 hours. During this time, dose assessment (Raddose) capability will only be available in the manual data input mode. The SPDS indications and Raddose remain available to the plant staff in the Control Room, and will be used for emergency response, if needed. Information will be communicated to the NRC using other available communication systems as needed. A follow-up notification will be submitted when the IPCS is completely restored, including SPDS and ERDS, to the Operational Support Center, the Technical Support Center, and alternate facilities. This 8-hour non-emergency notification is being made per the requirements of 10 CFR 50.72(b)(3)(xiii), as an event that results in a major loss of emergency assessment capability. The licensee has notified the NRC Resident Inspector.

  • * * UPDATE AT 0905 EDT ON 03/15/14 FROM PAUL GRESH TO S. SANDIN * * *

The following update was received from the licensee: On February 23, 2014, at approximately 1200 (EST), the Fermi 2 Integrated Plant Computer System (IPCS) was removed from service to support planned system maintenance. The Safety Parameters Display System (SPDS) and Emergency Response Data System (ERDS) reside on the IPCS platform and were out of service when IPCS was removed from service. On March 15, 2014 at approximately 0800 (EDT), planned maintenance on ERDS, SPDS, and IPCS is complete, restoring full Emergency assessment capabilities to the control room and all onsite emergency response facilities. The licensee informed the NRC Resident Inspector. Notified R3DO (Passehl).

ENS 496168 December 2013 15:00:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessLoss of Assessment Due to Technical Support Center Uninterruptable Power Supply Planned Replacement

The following event description is based on information currently available. If through subsequent reviews of this event additional information is identified that is pertinent to this event or alters the information being provided at this time a follow-up notification will be made via the ENS or under the reporting requirements of 10CFR50.73. At approximately 0800 Mountain Standard Time on December 8, 2013, Palo Verde Nuclear Generating Station (PVNGS) removed the Technical Support Center (TSC) uninterruptable power supply (UPS) from service for a planned replacement. The outage disables the Emergency Response Facility Data Acquisition and Display System (ERFDADS) inside the TSC, remote meteorological data display in the emergency response facilities and control rooms, and transmission of plant data to the Emergency Operations Facility (EOF) and to the NRC's Emergency Response Data System (ERDS). The outage is expected to be completed within five days. The TSC and EOF remain functional during the outage. The outage does not affect the availability of normal power to the TSC or back-up power from the TSC diesel generator. Existing telecommunication systems provided for the emergency response organization (ERO) remain functional to provide the ERO within the TSC and EOF the necessary emergency assessment capabilities, as described in the PVNGS Emergency Plan. The ERFDADS system in each of the three unit control rooms and unit satellite TSCs remain functional and are not affected by the TSC UPS outage. Compensatory measures exist within emergency plan implementing procedures to obtain meteorological tower data locally and from the National Weather Service. The ERO has been briefed on the effects of the planned TSC UPS outage. The NRC Resident Inspector has been informed. PVNGS will inform the NRC after the outage has been completed and the functionality of affected equipment has been restored.

  • * * UPDATE FROM DAVE HECKMAN TO HOWIE CROUCH AT 1632 EST ON 12/12/13 * * *

The following event description is based on information currently available. If through subsequent reviews of this event, additional information is identified that is pertinent to this event or alters the information being provided at this time, a follow-up notification will be made via the ENS or under the reporting requirements of 10CFR50.73. This notification is an update to EN 49616 which provided notification of pre-planned maintenance activities on the Palo Verde Nuclear Generating Station (PVNGS) Technical Support Center (TSC) uninterruptable power supply (UPS) that disabled various Emergency Plan (E-Plan) data systems. At approximately 0915 Mountain Standard Time on December 12, 2013, PVNGS restored the affected data systems to service such that the functions of the E-Plan can now be performed without the use of alternate methods. The NRC Resident Inspector has been informed. Notified R4DO (Werner).

ENS 4956321 November 2013 01:00:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessLoss of Emergency Preparedness Capabilities Due to Unit 2 Plant Process Computer Replacement

The Unit 2 DC Cook Nuclear Plant (CNP) Plant Process Computer (PPC) will be removed from service on Wednesday, November 20, 2013 at 2000 (EST) to support planned replacement. The Unit 2 PPC, including the Emergency Response Data System (ERDS), will be unavailable to the NRC Operations Center. Planned replacement also affects the Safety Parameter Display System (SPDS), the Real Time Data Repository (RDR), and PPC data to emergency response facilities at CNP. Safety system annunciators and indications in the control room remain available. The scheduled replacement, returning of equipment to service and post maintenance testing is expected to be completed by 1400 on Sunday, December 22, 2013. Compensatory measures exist within the DC Cook emergency response procedures to provide plant data via the Emergency Notification System to the NRC Operations Center until the ERDS can be returned to service. The licensee has notified the NRC Resident Inspector. This notification is being made in accordance with 10 CFR 50.72 (b)(3)(xiii) due to any event that results in a major loss of emergency assessment capability, offsite response capability, or offsite communications capability (e.g., significant portion of control room indication, Emergency Notification System, or offsite notification system).

  • * * UPDATE FROM DAN KURTH TO DONALD NORWOOD AT 1535 EST ON 12/21/2013 * * *

The Unit 2 DC Cook Nuclear Plant (CNP) Plant Process Computer (PPC) has been restored to service as of Saturday, December 21, 2013 at 1046 EST. The Unit 2 PPC, including the Emergency Response Data System (ERDS), Safety Parameter Display System (SPDS), Real Time Data Repository (RDR), and PPC data to the Emergency Response Facilities at CNP have been restored to normal operation. No further compensatory actions required. The licensee has notified the NRC Resident Inspector. Notified R3DO (Riemer).

ENS 4945519 October 2013 22:05:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessPartial Loss of Offsite Communications Due to a Blown FuseOn 10/19/2013 at 1705 CDT, Browns Ferry Nuclear Plant (BFN) experienced a partial loss of offsite communications, which included the NRC Emergency Notification System, the Emergency Plan Paging System and normal phone communication to offsite. Main control room indications and assessment capability were not affected. The Nextel cellular phone system and the satellite phones in the control rooms were unaffected. The plant radio system was also unaffected. The Emergency Response Data System is currently out of service due to planned maintenance on the associated offsite power supply. Operation of BFN Unit 1, Unit 2, and Unit 3 was not affected by the event. The BFN facilities personnel found a blown fuse in one of the temporary Diesel Generators (DGs) supplying the node associated with the outside phone communications. The fuse was replaced and the DG has been in-service with no issues. Normal communications and access have been restored. The NRC Senior Resident Inspector has been notified. This event is reportable under 10CFR50.72(b)(3)(xiii), 'Any event that results in a major loss of emergency assessment capability, offsite response capability, or offsite communications capability' (e.g., significant portion of control room indication, emergency notification system, or offsite notification system).
ENS 4928919 August 2013 13:00:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessLoss of Emergency Preparedness Capabilities Due to Unit 1 Ppc Replacement

The Unit 1 DC Cook Nuclear Plant (CNP) Plant Process Computer (PPC) will be removed from service on Monday, August 19, 2013 at 0900 EDT to support planned replacement. The Unit 1 PPC, including the Emergency Response Data System (ERDS), will be unavailable to the NRC Operations Center. Planned replacement also affects the Safety Parameter Display System (SPDS), the Real Time Data Repository (RDR), and PPC data to Emergency Response Facilities at CNP. Safety system annunciators and indications in the control room remain available. The scheduled replacement, returning of equipment to service and post maintenance testing is expected to be completed by 2000 EDT on Saturday, September 7, 2013. Compensatory measures exist within the DC Cook emergency response procedures to provide plant data via the Emergency Notification System to the NRC Operations Center until the ERDS can be returned to service. The licensee has notified the NRC Resident Inspector. This notification is being made in accordance with 10 CFR 50.72 (b)(3)(xiii) due to any event that results in a major loss of emergency assessment capability, offsite response capability, or offsite communications capability (e.g., significant portion of control room indication, Emergency Notification System, or offsite notification system).

  • * * UPDATE AT 1228 EDT ON 10/15/13 FROM BOWMAN TO HUFFMAN * * *

The Unit 1 DC Cook Nuclear Plant (CNP) Plant Process Computer (PPC) was restored to service on Tuesday, October 1, 2013 at 1649 EDT following the planned replacement of the PPC. The Unit 1 PPC is fully functional, including the Emergency Response Data System (ERDS), which is available to the NRC Operations Center. This also restores the Safety Parameter Display System (SPDS), the Real Time Data Repository (RDR), and PPC data to Emergency Response Facilities at CNP. The licensee has notified the NRC Resident Inspector. R3DO (Duncan) notified.

ENS 4919115 July 2013 13:34:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessUnplanned Loss of Communications Due to Offsite Fiber Optic Cable Damage

At approximately 0934 EDT on Monday, July 15, 2013, the Cook Nuclear Plant (CNP) experienced a loss of capability to transmit Emergency Response Data System (ERDS) information to the Nuclear Regulatory Commission (NRC). Emergency Plan Implementing Procedures provide direction to manually record ERDS data for transmission to the NRC via telephone or fax. Concurrent with the loss of ERDS was a loss of the NRC 'Red Phone' (FTS-2000). The suspected cause of the loss was a damaged fiber optic cable located offsite in Bridgman, Michigan unrelated to CNP. This caused the failure of the internet service provider to CNP. Communications via alternate phone lines and corporate service number remain available and have been tested. CNP has contacted offsite service providers for restoration of service. The estimated time for return to service is 2000 EDT on Monday, July 15, 2013. This notification is being made in accordance with 10CFR50.72(b)(3)(xiii) due to the loss of communications capability which includes events that would significantly impair the ability of the licensee to implement the functions of its emergency plans if an emergency were to occur. The licensee has notified the NRC Resident Inspector.

  • * * UPDATE ON 7/15/13 AT 2114 EDT FROM KELLY BAKER TO DONG PARK * * *

At 2050 EDT on Monday, July 15, 2013, DC Cook Operations Department was notified by Information Technology (IT) that the offsite fiber optic cable that was damaged had been repaired. Affected equipment was verified to be working properly, specifically, Emergency Response Data System (ERDS) data is transmitting and the NRC 'Red Phone' is functional. Communication capability has been restored. The licensee has notified the Senior NRC Resident Inspector." Notified R3DO (Hills).

ENS 491733 July 2013 07:00:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessLoss of Emergency Response Communications Due to a Loss of Ancillary Power

At 0156 PDT on July 3, 2013, Diablo Canyon Power Plant experienced a loss of power to ancillary facilities on site. This affected power supplies to data systems used by the Emergency Response Facilities (EOF). All plant status and performance data in the TSC (Technical Support Center) and EOF is available via telephone bridge line and control room phone talker. Additionally, the Emergency Response Data System (ERDS) has been determined to be unavailable. The data system loss occurred following depletion of backup batteries in the affected data center." The licensee notified the NRC Resident Inspector and will notify state and local agencies.

  • * * UPDATE FROM DAN STERMER TO JOHN SHOEMAKER AT 1948 EDT ON 7/3/13 * * *

At 2120 PDT on 6/23/13, Diablo Canyon Power Plant (DCPP) experienced a loss of the offsite 230 kV startup power source due to an offsite transmission system relay actuation (see EN# 49143). At 1000 PDT on 7/3/13, PG&E identified that the conditions present on 7/3/13 that resulted in loss of plant status and performance data in the Technical Support Center (TSC) and Emergency Operations Facility (EOF) (see EN# 49173) also existed on 6/23/13. This update reports the 6/23/13 loss of plant status and performance data in the TSC and EOF due to loss of power in the data center that supports those facilities. All plant status and performance data required for emergency assessment and communication remained available via a telephone bridge line and control room phone talker. The data became unavailable in the TSC and EOF following depletion of backup batteries in the affected data center. On 7/3/13 PG&E reconfigured the TSC workstations to ensure they would function and provide data for emergency assessment capability independent of the status of the data center power supplies. The Emergency Response Data System was also unavailable following the loss of 230 kV startup power on 6/23/13 due to loss of power to the data center. This unavailability was as designed and as expected. This delayed event notification has been entered into the DCPP corrective action program. The licensee has notified the NRC Resident Inspector. Notified the R4DO (Gaddy) and ERDS Group via email.

ENS 4890810 April 2013 13:30:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessLoss of Emergency Notification System TelephoneOn April 10, 2013 at 0930 (EDT) Hope Creek Operations personnel identified that the NRC ENS phone line was unavailable for Hope Creek Generating Station. The loss of the NRC ENS line was verified by the Hope Creek Shift Manager via backup land line communication to the NRC. The NRC Operations Center has an open repair ticket with the phone service provider. The loss of the phone line had no effect on plant operation and the unit remains at 100% power. Additionally, Emergency Response Data System (ERDS) capability was verified to remain intact and is available to transmit data. No personnel injuries resulted from the event. The NRC Resident Inspector has been informed.
ENS 489059 April 2013 17:15:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessLoss of Emergency Notification System TelephoneOn April 9, 2013 at 1315 (EDT) Hope Creek Operations personnel identified that the NRC ENS phone line was unavailable for Hope Creek Generating Station. The loss of the NRC ENS line was verified by the Hope Creek Shift Manager via backup land line communication to the NRC Operation Center at 1355 (EDT). At that time, the NRC Operations Center submitted a repair ticket to the phone service provider. NRC ENS phone availability was verified restored to service at 1618 (EDT) with the NRC Operations Center. The loss of the phone line had no effect on plant operations and the unit remains at 100% power. Additionally, Emergency Response Data System (ERDS) capability was verified to remain intact during this time period and was available to transmit data. No personnel injuries resulted from the event. The NRC Resident Inspector has been notified.
ENS 4878627 February 2013 00:30:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessLoss of Assessment Capability Due to Vital Inverter MaintenanceAt approximately 1630 PST on February 26, 2013, Pacific Gas & Electric (PG&E) will be performing repairs on a vital inverter. The clearance will remove power from various inputs to the Safety Parameter Display System (SPDS), Emergency Response Data System (ERDS), and Emergency Response Data and Recall Recorder Subsystem (ERFDS). PG&E expects to have the equipment repaired and returned to service within 12 hours. During this time, a dedicated licensed operator will be available to provide plant data to the NRC's Emergency Operations Center. DCPP is making this 8-hour, non-emergency notification under 10 CFR 50.72(b)(3)(xiii) as any event that results in a major loss of emergency assessment capability, offsite response capability, or offsite communications capability. The licensee notified the NRC Resident Inspector.
ENS 4870831 January 2013 07:10:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessLoss of Emergency Response Data System (Erds)On January 31, 2013, at approximately 0210 hours (EST), the ability to transfer plant parameter data via the Emergency Response Data System (ERDS) was lost. ERDS capability was restored at 0701 hours (EST). The cause is under investigation. In the event of an emergency while ERDS was unavailable, contingency plans were in place to transmit plant parameter data, This event is being reported in accordance with 10 CFR 50.72(b)(3)(xiii), The NRC Resident Inspector has been notified.
ENS 486483 January 2013 15:30:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessLoss of Erds Capability

At 0930 (CST) on January 03, 2013 NextEra Energy Duane Arnold discovered that the Emergency Response Data System (ERDS) was no longer capable of transmitting plant data to the NRC. The loss of ERDS is reportable per 50.72(b)(3)(xiii). At 1151 (CST) on January 03, 2013 Information Management personnel restored ERDS to working status. The NRC Resident (Inspector) has been notified. The licensee has the cause under investigation.

  • * * UPDATE AT 2136 EST ON 01/03/13 FROM STEPHEN SPEIRS TO S. SANDIN * * *

At 1725 (CST) on January 03, 2013 NextEra Energy Duane Arnold experienced a four minute interruption of the Emergency Response Data System (ERDS). During this time, ERDS was not capable of transmitting plant data to the NRC. The loss of ERDS is reportable per 10 CFR 50.72(b)(3)(xiii). The interruption of ERDS is related to a previous problem with the system reported under EN #48648. Troubleshooting of ERDS continues to ensure long-term reliability. Additional interruptions of ERDS are possible during this troubleshooting, and a follow-up notification will be made when ERDS reliability is assured. The licensee informed the NRC Resident Inspector. Notified R3DO (Skokowski), ERDS Group and CAT Group via email.

  • * * UPDATE FROM ROB SPADING TO CHARLES TEAL ON 1/28/13 AT 1436 EST * * *

Maintenance is complete on the ERDS system. It was tested satisfactorily on 01/15/13 at 1130 CST and returned to fully functional status. The NRC Resident Inspector has been informed. Notified R3DO (Stone), ERDS Group and CAT Group via email.

ENS 4862021 December 2012 13:30:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessLoss of Emergency Response Data System (Erds)At approximately 0730 CST, Xcel Energy Prairie Island Nuclear Generating Plant was informed of a loss of internet and data services due to equipment problems with the Wide Area Network (WAN). The loss of data services resulted in the loss of ERDS communication capabilities with the NRC. The WAN and ERDS were restored at 0921 CST. The licensee has notified the NRC Resident Inspector.
ENS 4861821 December 2012 13:30:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessLoss of Emergency Response Data System (Erds)At approximately 0730 CST, Xcel Energy Monticello Nuclear Generating Plant was informed of a loss of internet and data services due to equipment problems with the Wide Area Network (WAN). The loss of data services resulted in the loss of ERDS communication capabilities with the NRC. Compensatory actions were established to communicate plant parameters verbally via the Emergency Notification System, which was verified functional at 0836 CST. The WAN and ERDS were restored at 0921 CST and ERDS was verified functional at 0948 CST. This issue is being reported as a loss of communications capability non-emergency event notification under 10CFR50.72(b)(3)(xiii) as defined in NUREG 1022, Rev. 2. The licensee has notified the NRC Resident Inspector.
ENS 4861020 December 2012 12:51:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessEmergency Response Data System (Erds) Out-Of-Service

Computer engineering personnel will be taking the plant integrated computer system (ICS) out-of-service for planned maintenance. During the time ICS is out-of-service, the Safety Parameter Display System (SPDS) and the Emergency Response Data System (ERDS) will be unavailable. The computer outage is scheduled for six hours. Contingency plans have been established to transmit plant parameter data and perform the dose assessment function in the event of an emergency while ERDS is unavailable. This event is being reported in accordance with 10 CFR 50.72(b)(3)(xiii). A follow-up notification will be made when the maintenance activities are complete and the equipment is restored. The licensee notified the NRC Resident Inspector.

  • * * UPDATE FROM JIM CASE TO HOWIE CROUCH AT 1309 EST ON 12/20/12 * * *

At 1300 EST, the plant integrated computer system was restored and SPDS and ERDS was returned to service. Notified R3DO (Cameron) and ERDS Group email.

ENS 4860318 December 2012 19:36:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessPartial Loss of Emergency Assessment During Planned Modifications

Calvert Cliffs Nuclear Power Plant will begin a planned modification of the Unit 1 and Unit 2 Plant Process Computers (PPC's) and associated network infrastructure on December 18, 2012. This includes the Emergency Response Data System (ERDS) communication with the NRC Operations Center. This work will require the TSC, OSC and subsequently EOF to lose data flow from the plant data network for a period of approximately 36 hours. During this time, the following systems will be impacted for the duration of maintenance: 1. ERDS will be out of service. 2. Plant Data will not reach the TSC and OSC from the plant data network. 3. TSC Computer data transfer to the EOF only will be out of service. 4. Chemistry DAS remote monitoring capability will be lost. 5. Plant parameter data will not be available on the site's LAN network. Once the schedule maintenance starts, the systems (listed above) can be returned to service within 1 hour. Should an emergency be declared during this period, the Control Room will continue to have the capability to retrieve plant data inputs to assess plant conditions and perform core damage assessment. Control Room Emergency response personnel will use emergency response procedures (ERPIP 106) to disseminate plant parameter data to the effected Emergency Response Facilities. MIDAS (Meteorological Data) will continue to be operational at the site. Compensatory measures exist within the Calvert Cliffs Emergency Response procedures to provide plant data in the event of an actual Emergency to the NRC Operations Center until the ERDS can be returned to service. The licensee notified the NRC Resident Inspector.

  • * * UPDATE FROM BRIAN HAYDEN TO S. SANDIN ON 12/20/2012 AT 1035 EST * * *

On 12/20/2012 at 0200 EST, the plant process computer and associated network infrastructure was restored to service. The licensee will notify the NRC Resident Inspector. Notified the R1DO (Hunegs).

ENS 4851818 November 2012 16:30:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessLoss of Assessment Capability Due to Integrated Plant Computer Planned Maintenance

On 11/18/2012 at approximately 1130 EST, the Summer Safety Parameter Display System (SPDS) and the Emergency Response Data System (ERDS) will be taken out of service for approximately 12 hours to support a planned maintenance on an inverter that feeds the station's Integrated Plant Computer System (lPCS). During this time frame. ERDS and SPDS will be unavailable. Should the need arise, plant status information will be communicated to the NRC using other available communication systems. SPDS and ERDS are expected to be restored on 11/18/2012 at 1800 EST. This event is reportable under 10 CFR 50.72(b)(3)(xiii). The NRC Resident Inspector has been notified.

  • * * UPDATE FROM MICHAEL MOORE TO DONALD NORWOOD AT 1003 EST ON 11/19/2012 * * *

On November 18, 2012, at approximately 1730, IPCS was returned to service. Completing this planned maintenance activity restored the VCSNS Safety Parameter Display System and the Emergency Response Data System (ERDS). ERDS was tested this morning, November 19, 2012, by VCSNS and the NRC ERDS Help Desk to verify system operability. The NRC Resident Inspector has been notified. Notified R2DO (Widmann).

ENS 4850413 November 2012 14:00:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessPartial Loss of Emergency Assessment During Planned Modifications

Cook Nuclear Power Plant will begin a cyber security modification of Unit 1 and Unit 2 Plant Process Computers (PPCs) and associated network infrastructure on Tuesday, November 13, 2012 at 0900 EST. This includes the Emergency Response Data System (ERDS) communication with the NRC Operations Center. The entire PPC for each unit will be out of service and unavailable for approximately 6 hours. During that time, the PPC satellite display systems in the Control Rooms, TSC and EOF will be unavailable. After approximately 9 hours, the ERDS will be restored to service along with the satellite display systems in the Control Rooms, TSC and EOF. Compensatory measures exist within the DC Cook Emergency Response procedures to provide plant data in the event of an actual Emergency to the NRC Operations Center until the ERDS can be returned to service. Unavailability of the ERDS and Control Room, TSC and EOF data is being reported in accordance with 10 CFR 50.72(b)(3)(xiii) as a major loss of emergency assessment capability. The NRC Resident Inspector has been notified. A follow-up ENS communication will be made when both units ERDS are fully restored to service. Unit 1 and Unit 2 PPC availability is expected to be restored on Tuesday, November 13, 2012 at 1500 EST. ERDS communication with the NRC Operations Center is expected to be restored on November 13, 2012 at 1800 EST.

  • * * UPDATE FROM BRADDOCK LEWIS TO HOWIE CROUCH @ 1559 EST ON 11/13/12 * * *

The licensee notified the Operations Center that the PPC work was delayed and, as a consequence, ERDS restoration will be delayed. Work on the PPC continues. The licensee has notified the NRC Resident Inspector. Notified R3DO (Giessner) and ERDS Group (via email).

  • * * UPDATE AT 1908 EST ON 11/13/12 FROM GREG KANDA TO MARK ABRAMOVITZ * * *

ERDS was declared operable at 1815 EST. The licensee notified the NRC Resident Inspector. Notified R3DO (Giessner) and ERDS Group (via email).

ENS 484681 November 2012 12:00:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessIntegrated Plant Computer System Out-Of-Service Outside the Control Room for Planned Maintenance

Beginning November 01, 2012, at approximately 1000 (EDT), the Fermi 2 Integrated Plant Computer System (IPCS) will be removed from service outside of the Control Room to support installation of a Cyber Security Modification. The Safety Parameters Display System (SPDS) and Emergency Response Data System (ERDS) reside on the IPCS platform and will be out of service when the IPCS is removed from Emergency Response Facilities (ERFs). These systems will be unavailable to all Emergency Response Facilities (ERFs) for approximately 196 hours. By 1600 (EDT) on November 9, 2012 it is planned to restore IPCS, including SPDS and ERDS, to the Operational Support Center, the Technical Support Center, and alternate facilities. During this time dose assessment (Raddose) capability will only be available in the manual data input mode. The SPDS indications and Raddose remain available to the plant staff in the Control Room, and will be used for emergency response, if needed. Information will be communicated to the NRC using other available communication systems as needed. A follow-up notification will be submitted when the IPCS is completely restored. This 8-hour non-emergency notification is being made per the requirements of 10 CFR 50.72(b)(3)(xiii), as an event that results in a major loss of emergency assessment capability. ERDS previously reported out of service under event number EN 48451 . The licensee informed the NRC Resident Inspector.

  • * * UPDATE ON 11/9/12 AT 2056 EST FROM BRETT JEBBIA TO DONG PARK * * *

This is a follow up to EN #48468 & EN #48451. On October 29, 2012, Fermi experienced a failure of a data server within the process computer system which feeds data to Emergency Response Data System (ERDS), and EN #48451 was made to the NRC. On November 1, 2012, planned maintenance for Cyber Security Modification began which removed ERDS, SPDS, and IPCS from service, and EN #48468 was made to the NRC. On November 9, 2012, planned maintenance on ERDS, SPDS, and IPCS is complete, restoring full emergency assessment capabilities to all onsite emergency response facilities (EN #48468). The maintenance also repaired the data server within the process computer system which feeds data to ERDS (EN #48451). The licensee has notified the NRC Resident Inspector. Notified R3DO (Lipa).

ENS 4845129 October 2012 21:00:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessErds Lost Due to Process Computer System Data Server Failure

At 1700 EDT on October 29, 2012, Fermi 2 discovered a failure occurred with a data server within the Process Computer system at 0115 EDT on October 28, 2012. The failure of the data server affects data input to the server providing information to the Emergency Response Data System (ERDS). ERDS is currently not receiving updated information from Fermi data systems. This loss in capability is being reported as a loss of assessment capability in accordance with 10 CFR 50.72(b)(3)(xiii). Indications of related plant variables are available in the Main Control Room. The Visual Annunciator System (VAS) and other portions of the Process Computer system remain functional. Meteorological and process effluent radiological monitor indications are available and dose assessment capability is available. Fermi 2 personnel will use normal phone communications to update NRC Operations Center in the case of an event declaration. Information normally provided by ERDS can be transmitted via the notification system as described in the Radiological Emergency Response Preparedness Plan. Fermi 2 will notify the NRC when ERDS is returned to service. The licensee has notified the NRC Resident Inspector.

  • * * UPDATE ON 11/9/12 AT 2056 EST FROM BRETT JEBBIA TO DONG PARK * * *

This is a follow up to EN #48468 & EN #48451. On October 29, 2012, Fermi experienced a failure of a data server within the process computer system which feeds data to Emergency Response Data System (ERDS), and EN #48451 was made to the NRC. On November 1, 2012, planned maintenance for Cyber Security Modification began which removed ERDS, SPDS, and IPCS from service, and EN #48468 was made to the NRC. On November 9, 2012, planned maintenance on ERDS, SPDS, and IPCS is complete, restoring full emergency assessment capabilities to all onsite emergency response facilities (EN #48468). The maintenance also repaired the data server within the process computer system which feeds data to ERDS (EN #48451). The licensee has notified the NRC Resident Inspector. Notified R3DO (Lipa).

ENS 4844928 October 2012 14:08:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessEquipment Failure Affecting Spds and ErdsAt approximately 1008 EDT on October 28th, 2012, a failure between the Plant Computer and the MMI (Man Machine Interface) occurred. The cause is due to a failure of the data diode. The Plant Computer is still working however the MMI is not, therefore Safety Parameter Display System (SPDS) outside of the Control Room and the Emergency Response Data System (ERDS) is unavailable. In the event of an emergency, plant parameter data will be communicated to the facilities through the status board ring down circuit with back-up by the Private Branch Exchange (PBX), Off Premise Exchange (OPX), and various redundant intra-facility circuits throughout the emergency facilities. The dose assessment function is maintained during this out of service time period by manual input of data into the Meteorological Information and Dose Assessment System (MIDAS). The ability to open and maintain an 'open line' using the Emergency Notification System is not affected and will be the primary means for transferring plant data to the NRC as a contingency until the ERDS can be returned to service. At 1548 EDT on October 28th, 2012, a re-start of the data diode was successful in restoring the connection between the Plant Computer and the MMI. SPDS and the ERDS are functioning as designed. This event is being reported in accordance with 10 CFR 50.72(b)(3)(xiii). The NRC Resident Inspector has been notified. The licensee has notified the State and local agencies.
ENS 4844827 October 2012 19:15:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessLoss of Offsite Communications

On 10/27/2012 at 1415 CDT, the control room was notified of a loss of telephone communications. Reason is unknown at this time. Offsite communications lost includes the state and county ring down lines, the NRC ring down line. The ability to transfer information from the Emergency Response Data System (ERDS) to offsite agencies is believed not to be available. Satellite phones remain available. At approximately 1500 CDT, the NRC Operations Center was notified via satellite communications of alternate phone numbers to contact the Unit 1 Control Room and that Unit 2 Control Room satellite phone is not available to receive calls. This is a follow up to make the notification of this event to the NRC pursuant 10 CFR 50.72(b)(3)(xiii). The NRC Senior Resident Inspector was notified of the issue." State and local agencies were notified via alternate means.

  • * * UPDATE FROM CHRIS VANFLEET TO HOWIE CROUCH AT 0003 EDT ON 10/28/12 * * *

Emergency Notification System has been returned to service. The cause of the loss of communications was a cut fiber optic line. Notified R4DO (Hagar).

ENS 4844225 October 2012 14:30:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessPartial Loss of Emergency Assessment During Planned Modifications

On October 25, 2012, Callaway Plant will begin implementation of a modification to the plant computer system. The Emergency Response Data System (ERDS) and plant computer stations in the Technical Support Center (TSC) and Emergency Operations Facility (EOF) will be unavailable during the modification. Plant computer stations will remain available in the Control Room. The period of unavailability is anticipated to be approximately 12 hours on October 25, 2012, with an additional 8 hours for system testing on October 26, 2012. During the modification process, the TSC and EOF will remain functional and available for use. Plant procedures provide guidance for manual data collection and sending ERDS data to the NRC. This notification is being made in accordance with 10 CFR 50.72(b)(3)(xiii). The NRC Resident Inspector has been notified.

* * * UPDATE FROM SHANNON GAYDOS TO PETE SNYDER AT 2123 ON 10/25/12 * * * 

Based on the current work progress on the plant computer system, the Emergency Response Data System (ERDS) and the plant computer stations in the Technical Support Center (TSC) and Emergency Operations Facility (EOF) will not be available until early evening on October 26, 2012. The NRC Resident Inspector will be notified. Notified R4DO (Hagar).

* * * UPDATE FROM DAVID LANTZ TO DONG PARK AT 2033 EDT ON 10/26/12 * * * 

Modification has been completed on the plant computer system. The Emergency Response Data System (ERDS) and the plant computer stations in the Technical Support Center (TSC) and Emergency Operations Facility (EOF) have been restored to normal operation. The NRC Resident Inspector will be notified. Notified R4DO (Hagar).

ENS 4841517 October 2012 12:00:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessEmergency Response Data System (Erds) Out of Service

At approximately 0800 hours EDT on October 17, 2012, computer engineering personnel will be taking the plant integrated computer system (ICS) out-of-service for planned maintenance. During the time ICS is out-of-service, the Safety Parameter Display System (SPDS) and the Emergency Response Data System (ERDS) will be unavailable. The computer outage is scheduled for twelve hours. In the event of an emergency, plant parameter data will be communicated to the facilities through the Status Board Ring Down circuit with back-up by the Private Branch Exchange, Off Premise Exchange, and various redundant intra-facility circuits throughout the emergency facilities. The dose assessment function will be maintained during the out-of-service time period by manual input of data into the Meteorological Information and Dose Assessment System (MIDAS). The ability to open and maintain an 'open line' using the Emergency Notification System will not be affected and will be the primary means of transferring plant data to the NRC as a contingency until the ERDS can be returned to service. This event is being reported in accordance with 10 CFR 50.72(b)(3)(xiii). A follow-up notification will be made when the maintenance activities are complete and the equipment is restored. The (NRC) Resident Inspector has been notified.

  • * * UPDATE FROM THOMAS MORSE TO VINCE KLCO ON 10/17/12 AT 2146 EDT * * *

As of 2140 EDT on 10/17/12, the ERDS system was tested and restored to service. The licensee notified the NRC Resident Inspector. Notified the R3DO (Orth).

ENS 483815 October 2012 12:00:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessLoss of Emergency Response Facility Information System Due to Planned ModificationAt approximately 0800 EDT, on October 5, 2012, the Emergency Response Facility Information System (ERFIS) will be removed from service to perform a planned modification for the improvement of site wide data communications between various plant process computing platforms. The expected duration of ERFIS non-functionality should not exceed 24 hours and during this time would not be able to be restored within one hour. The ERFIS computer system provides monitoring and communications capability for plant data systems including the Emergency Response Data System (ERDS) and the Safety Parameter Display System (SPDS). The loss of ERFIS requires alternate methods, as described in plant procedures, to be used for the above described functions. Therefore, assessment of plant conditions, notifications, and communications could still be made, if required, during the time that the ERFIS computer system is non-functional. The on call Emergency Response Organization has been notified of the ERFIS outage. This report is being made in accordance with 10 CFR 50.72(b)(3)(xiii) as described in NUREG-1022, Rev. 2. The NRC Resident Inspector has been notified.
ENS 483631 October 2012 08:24:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessEmergency Response Data System Is Unavailable for Service

Seabrook personnel determined that the Emergency Response Data System (ERDS) is unavailable due to a malfunction of its process computer. The condition occurred around 0430 EDT today after a plant electrical bus was de-energized and subsequently reenergized during a maintenance activity. The plant is presently in a refueling outage with the reactor vessel defueled. Following repair of the process computer, Seabrook expects to return ERDS to service later today. This event is being reported in accordance with 10 CFR50.72(b)(3)(xiii), loss of emergency preparedness capabilities, for loss of the ERDS function. The NRC Resident Inspector has been notified of this event.

  • * * UPDATE FROM MIKE TAYLOR TO HOWIE CROUCH AT 1333 EDT ON 10/1/12 * * *

The ERDS system has been returned to service. The licensee will be notifying the NRC Resident Inspector. Notified R1DO (Schmidt).

ENS 4833824 September 2012 08:07:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessEmergency Response Data System Process Computer Data Server Failure

At 04:07 EDT on September 24, 2012, Fermi 2 experienced a failure of a data server within the Process Computer system. The failure of the data server does affect data input to the server providing information to the Emergency Response Data System (ERDS). ERDS is currently not receiving updated information from Fermi data systems. This loss in capability is being reported as a loss of assessment capability in accordance with 10 CFR 50.72(b)(3)(xiii). Indications of related plant variables are available in the Main Control Room. The Visual Annunciator System (VAS) and other portions of the Process Computer system remain functional. Meteorological and process effluent radiological monitor indications are available and dose assessment capability is available. Fermi 2 personnel will use normal phone communications to update NRC Operations Center in the case of an event declaration. Information normally provided by ERDS can be transmitted via the notification system as described in the Radiological Emergency Response Preparedness Plan. The licensee has notified the NRC Resident Inspector.

  • * * UPDATE FROM MARK EGHIGIAN TO CHARLES TEAL AT 1435 EDT ON 10/6/12 * * *

On September 24, 2012, Fermi experienced a failure of a data server within the process computer system which feeds data to Emergency Response Data System (ERDS), and report #48338 was made to the NRC. On October 6, 2012, corrective maintenance is complete, which repaired the data server and ERDS functionality is restored. The licensee has notified the NRC Resident Inspector. Notified R3DO (Valos).

ENS 4831818 September 2012 15:55:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessOutage of Plant Radiation Monitoring System Remote Readout Due to Planned Modification

On September 18, 2012, power was removed from SCADA A of the Radiation Monitoring System (RMS) to perform a planned system modification. During this period, data for most Unit 1 radiation monitors will not be electronically available in the emergency response facilities and will not be supplied to the Emergency Response Data System (ERDS), if activated. System alarms and data displays will still be available to the plant operators in the Control Room. The expected duration of RMS remote data partial inoperability is approximately 72 hours. The loss of Unit 1 remote readout capability requires compensatory measures to be used for the acquisition of radiological data in the emergency response facilities. These compensatory measures have been communicated to the emergency response organization, Therefore, it is expected that appropriate assessment of plant conditions, notifications, and communications could still be made, if required, during the time that the portions of the RMS are inoperable. This report is being made in accordance with 10 CFR 50.72(b)(3)(xiii), which is any event that results in a major loss of emergency assessment capability, offsite response capability, or offsite communications capability. An update message will be provided when the RMS is restored." The NRC Resident has been notified.

  • * * UPDATE FROM TONY SIROIS TO JOHN KNOKE AT 1749 EDT ON 09/20/12 * * *

The Radiation Monitoring System alarms and data displays have been restored to the Comanche Peak Emergency Response Facilities (ERFs) following completion of planned system modifications. The emergency assessment capability of the Comanche Peak ERF have been re-established. The licensee has notified the NRC Resident Inspector. Notified the R4DO (Geoffrey Miller)

ENS 4825229 August 2012 23:30:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessPrimary Plant Computer Out of ServiceCalvert Cliffs Unit 2 Primary Plant Computer (PPC) is out of service. The PPC provides monitoring capability for the Emergency Response Data System and Safety Parameter Display System. The loss of the PPC requires alternate monitoring methods, as described in plant procedures, to be used. Therefore, appropriate assessment of plant conditions, notifications and communications can still be made, if required, during the time that the PPC is unavailable. This report is being made in accordance with 10 CFR 50.72(b)(3)(xiii) which is any event that results in major loss of emergency assessment capability, offsite response capability, or offsite communications capability. As previously stated, alternate means remain available to assess plant conditions, make notifications and accomplish required communications, as necessary. The licensee has notified the NRC Resident Inspector.
ENS 4824729 August 2012 13:57:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessPartial Loss of Plant Radiation Monitoring System Remote Readout

On August 29, 2012, power was removed from SCADA B of the Radiation Monitoring System (RMS) to perform a planned system modification. During this period, data for most Unit 2 radiation monitors will not be electronically available in the emergency response facilities and will not be supplied to the Emergency Response Data System (ERDS), if activated. System alarms and data displays will still be available to the plant operators in the Control Room. The expected duration of RMS remote data partial inoperability is approximately 72 hours. The loss of Unit 2 remote readout capability requires compensatory measures to be used for the acquisition of radiological data in the emergency response facilities. These compensatory measures have been communicated to the emergency response organization. Therefore, it is expected that appropriate assessment of plant conditions, notifications, and communications could still be made, if required, during the time that the portions of the RMS are inoperable. This report is being made in accordance with 10 CFR 50.72(b)(3)(xiii), which is any event that results in a major loss of emergency assessment capability, offsite response capability, or offsite communications capability. An update message will be provided when the RMS is restored. The NRC Resident and Region IV EP Inspectors have been notified.

  • * * UPDATE FROM ALAN MARZLOFF TO DONALD NORWOOD AT 1921 EDT ON 8/31/2012 * * *

This is a follow-up to ENS report number 48247. The Radiation Monitoring System (RMS) alarms and data displays have been restored to the Comanche Peak emergency response facilities (ERFs) following completion of planned system modifications. The emergency assessment capability of the Comanche Peak emergency response facilities have been re-established (as of 1821 CDT). The NRC Resident has been notified. Notified R4DO (Azua).

ENS 4821120 August 2012 15:06:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessLoss of Emergency Response Data SystemAt 1106 EDT, on August 20, 2012 Computer Engineering personnel discovered a computer component failure which would have prevented the transmission of Emergency Response Data (ERDS) to the NRC if the system were to be activated. The actual component failure was determined to have occurred at approximately 2000 EDT on 8/19/12. This resulted in an out of service duration of greater than 8 hours, which was not discovered until after the fact. The system was repaired and returned to service at 1720 EDT on 8/20/12. Since Unit 1 and Unit 2 ERDS was unavailable for greater than 8 hours, this is considered a Loss of Emergency Assessment Capability and reportable under 10CFR50.72(b)(3)(xiii). The licensee has notified the NRC Resident Inspector.
ENS 481719 August 2012 17:00:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessEmergency Operations Facility Data Network MaintenanceAt about 1000 PDT on August 9, 2012, Pacific Gas and Electric Company (PG&E) will disconnect the Diablo Canyon Power Plant (DCPP) Plant Data Network to the Emergency Operations Facility (EOF) and redirect the data via the Utility Data Network for hosting the emergency facility data systems. These systems include the Safety Parameter Display System, Plant Process Computer, Emergency Response Facility Display System, and Emergency Assessment and Response System in the EOF. PG&E expects to have the Emergency Response Data System and the EOF data network unavailable for about 8 hours. During this time, if needed, the TSC will have command and control once staffed, and will have classification, notification and dose assessment responsibility until the display systems are restored to the EOF. Also, if required, a dedicated licensed operator will be available in the control room to provide plant data to the NRC's Emergency Operations Center. DCPP is making this 8-hour, non-emergency notification under 10 CFR 50.72(b)(3)(xiii) as any event that results in a major loss of emergency assessment capability, offsite response capability, or offsite communications capability. The licensee has notified the NRC Resident Inspector.
ENS 4812321 July 2012 02:30:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessAnticipatory Loss of Spds and Erds Due to Possible Loss of Integrated Plant Computer System During Troubleshooting

Beginning July 20, 2012, at approximately 2230, troubleshooting of MUX A components and fiber optic cables on the Fermi 2 Integrated Plant Computer System (IPCS) will be performed. A loss of IPCS during the troubleshooting is possible. The Safety Parameters Display System (SPDS) and Emergency Response Data System (ERDS) reside on the IPCS platform and will be out of service if IPCS is lost. These systems would be unavailable to the Control Room and all other Emergency Response Facilities (ERFs). During this time dose assessment capability would only be available in the manual data input mode. The majority of the Control Room indications will remain available to the plant staff, and would be used for emergency response, if needed. Information would be communicated to the NRC using other available communication systems as needed. A follow-up notification will be submitted when the IPCS troubleshooting is complete. This notification is being made per the requirements of 8 Hour Non-Emergency Notification 10CFR50.72(b)(3)(xiii), any event that results in a major loss of emergency assessment capability. The licensee notified the NRC Resident Inspector.

  • * * RETRACTION FROM BRETT JEBBIA TO VINCE KLCO ON 7/24/2012 AT 2243 EDT * * *

Troubleshooting and repairs have been completed to the Fermi 2 Integrated Plant Computer System (IPCS) as of July 24, 2012 at 1855 (EDT). No loss of communication ability occurred from initial notification while repairs and restoration were in progress. Event 48123 is retracted. (The initial anticipatory) notification was made per 10 CFR 50.72(b)(3)(xiii), any event that results in a major loss of emergency assessment capability. The licensee notified the NRC Resident Inspector. Notified the R3DO (Bloomer).

ENS 4810614 July 2012 06:06:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessUnexpected Integrated Plant Computer System FailureAt approximately 0206 EDT on July 14, 2012, the Femi 2 Integrated Plant Computer System (IPCS) failed. The Safety Parameters Display System (SPDS) and Emergency Response Data System (ERDS) reside on the IPCS platform. At 0525 EDT, plant personnel were able to reboot IPCS and restore the system to normal with prime and backup CPUs. Emergency assessment capabilities have been restored to all onsite emergency response facilitates. This notification is being made per the requirements of 8 hour non-emergency notification 10 CFR 50.72(b)(3)(xiii), any event that results in a major loss of emergency assessment capability. The licensee notified the NRC Resident Inspector.
ENS 480736 July 2012 06:32:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessEmergency Response Data System Out of Service

Calvert Cliffs Tech Support Computer power supply failed rendering the ERDS system incapable of transmitting data to the NRC. ERDS is out of service for both Unit-1 and Unit-2. Should an emergency be declared during this period, the Control Room will continue to have the capability to retrieve plant data inputs to assess plant conditions and perform core damage assessment. Control Room Emergency Response Organization personnel will use backup methods already captured in emergency response procedures to disseminate plant parameter data to the effected Emergency Response Facilities and NRC during the plant data network outage. The licensee notified the NRC Resident Inspector.

  • * * UPDATE FROM JOE JIOFFRE TO HOWIE CROUCH AT 1528 EDT ON 7/7/12 * * *

ERDS was returned to service at 1528 EDT after replacing the computer power supply. The licensee has notified the NRC Resident Inspector. Notified R1DO (Henderson).

ENS 480612 July 2012 12:00:0010 CFR 50.72(b)(3)(xiii), Loss of Emergency PreparednessSpds and Erds Out of Service for Maintenance

Beginning July 2, 2012, at approximately 0800, the Fermi 2 Integrated Plant Computer System (IPCS) will be removed from service to support installation of a Cyber Security Modification. The Safety Parameters Display System (SPDS) and Emergency Response Data System (ERDS) reside on the IPCS platform and will be out of service when the IPCS is removed from service. These systems will be unavailable to the Control Room and all other Emergency Response Facilities (ERFs) for approximately 20 hours. By 0300 on July 3, 2012, it is planned to restore IPCS, including SPDS and ERDS, to the Control Room, Operational Support Center, the Technical Support Center, and alternate facilities. During this time dose assessment capability will only be available in the manual data input mode. The majority of the Control Room indications remain available to the plant staff, and will be used for emergency response, if needed. Information will be communicated to the NRC using other available communication systems as needed. A follow-up notification will be submitted when the IPCS is completely restored. This notification is being made per the requirements of 8 Hour Non-Emergency Notification 10 CFR 50.72(b)(3)(xiii), any event that results in a major loss of emergency assessment capability. The licensee has notified the NRC Resident Inspector.

  • * * UPDATE ON 7/03/12 AT 0113 EDT FROM GROFF TO HUFFMAN * * *

On July 3, 2012, at 01:00, the Fermi 2 Integrated Plant Computer System (IPCS) has been returned to service. Emergency assessment capabilities have been restored to all onsite emergency response facilities. Due to equipment problems, the Cyber Security Modification was not installed and the original IPCS configuration was restored. The licensee has notified the NRC Resident Inspector. R3DO (Daley) notified.

  • * * UPDATE ON 7/03/12 AT 0556 EDT FROM GROFF TO HUFFMAN * * *

At approximately 02:04 on July 3, the Fermi 2 Integrated Plant Computer System (IPCS) failed. The Safety Parameters Display System (SPDS) and Emergency Response Data System (ERDS) reside on the IPCS platform. IPCS had previously been removed from service on 7/2/12 for a Cyber Security Modification and restored at 0100 on 7/3/12. At 0354, plant personnel were able to reboot IPCS and restore the system to normal with a Prime and Backup CPUs. Emergency assessment capabilities have been restored to all onsite emergency response facilities. This notification is being made per the requirements of 8 Hour Non-Emergency Notification 10 CFR 50.72(b)(3)(xiii), any event that results in a major loss of emergency assessment capability. The licensee has notified the NRC Resident Inspector. R3DO (Daley) notified.