Title | Reactor Trip Due to Loss of Two 120 Volt Ac Instrument Busses |
Event Description | At 1506 EDT, while the electricians were working on the left train DC bus, a bus bar slipped causing an arc and a loss of the left train DC busses D-10 L and D-10 R. This resulted in the loss of two preferred AC [120 Volt Instrument] busses Y-10 and Y-30. The loss of both preferred AC busses caused a reactor trip, a safety injection signal, auxiliary feedwater actuation signal, containment high radiation isolation signal, and main steam isolation signal.
All systems responded as expected. Electric power has been restored to the affected DC busses and preferred AC busses. The plant is stable in Mode 3 at NOT and NOP, and controlling temperature using Atmospheric Dump Valves. Pressurizer level is high due to the loss of letdown (result of containment isolation signal), however, it is recovering slowly. All rods fully inserted and the electrical lineup is back to normal. The licensee has notified the NRC Resident Inspector, and will be notifying local agencies. The licensee will also be issuing a press release. |
Where | |
---|---|
Palisades Michigan (NRC Region 3) | |
Reporting | |
10 CFR 50.72(b)(2)(iv)(B), RPS Actuation 10 CFR 50.72(b)(3)(iv)(A), System Actuation | |
Time - Person (Reporting Time:+-0.75 h-0.0313 days <br />-0.00446 weeks <br />-0.00103 months <br />) | |
Opened: | Bruce Bauer 18:21 Sep 25, 2011 |
NRC Officer: | John Knoke |
Last Updated: | Sep 25, 2011 |
47290 - NRC Website | |
Unit 1 | |
---|---|
Reactor critical | Critical |
Scram | A/R |
Before | Power Operation (100 %) |
After | Hot Standby (0 %) |
Palisades with 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation | |
WEEKMONTHYEARENS 538192019-01-09T05:00:0009 January 2019 05:00:00
[Table view]10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Reactor Trip from Full Power Due to Rps Testing ENS 538132019-01-03T05:00:0003 January 2019 05:00:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Reactor Trip Due to Cycling of Turbine Governor Valve ENS 527642017-05-19T06:06:00019 May 2017 06:06:00 10 CFR 50.72(b)(3)(iv)(A), System Actuation Valid Reactor Protection System Actuation While Shutdown ENS 513972015-09-16T05:17:00016 September 2015 05:17:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Reactor Trip Due to Turbine Trip ENS 475232011-12-14T20:10:00014 December 2011 20:10:00 Other Unspec Reqmnt, 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Manual Reactor Trip Due to Loss of Both Main Feedpumps ENS 472902011-09-25T19:06:00025 September 2011 19:06:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Reactor Trip Due to Loss of Two 120 Volt Ac Instrument Busses ENS 465642011-01-22T22:35:00022 January 2011 22:35:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Reactor Trip Due to Loss of Generator Load ENS 442372008-05-23T16:49:00023 May 2008 16:49:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Reactor Trip on Possible Generator Lockout ENS 439002008-01-13T10:21:00013 January 2008 10:21:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Manual Reactor Trip After Loss of Main Feedwater Pump ENS 433512007-05-08T17:22:0008 May 2007 17:22:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Automatic Reactor Trip on Low Steam Generator Water Level ENS 425692006-05-11T19:14:00011 May 2006 19:14:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation Manual Actuation of Reactor Protection System Due to Failure of Control Rod to Withdraw ENS 425552006-05-04T21:50:0004 May 2006 21:50:00 10 CFR 50.72(b)(3)(iv)(A), System Actuation Unexpected Reactor Protection System (Rps) Actuation During Testing ENS 419672005-09-01T14:25:0001 September 2005 14:25:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Reactor Trip Due to Main Generator Hydrogen Leak ENS 413192005-01-09T16:27:0009 January 2005 16:27:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Manual Reactor Trip Due to Lowering Main Condenser Vacuum ENS 410022004-08-31T11:18:00031 August 2004 11:18:00 10 CFR 50.72(b)(2)(iv)(B), RPS System Actuation, 10 CFR 50.72(b)(3)(iv)(A), System Actuation Rps Actuation Due to Fire in 2B Condensate Pump 2019-01-09T05:00:00 | |
Retrieved from "https://kanterella.com/w/index.php?title=ENS_47290&oldid=424350"