ENS 57243
ENS Event | |
|---|---|
04:00 Jul 23, 2024 | |
| Title | Part 21 Report - NON-COMPLAINT Insulated Conductor |
| Event Description | The following is a synopsis of information received via fax:
A reel of insulated conductor was found non-compliant due to failure of insulation tensile and elongation at break test following air oven aging. Wire from the non-compliant reel was delivered to nine plants. Affected plants: Wolf Creek, Dresden, LaSalle, Limerick, Peach Bottom, Arkansas Nuclear One, Waterford, Susquehanna, and Davis Besse. Reporting company point of contact: dba Marmon Industrial Energy and Infrastructure 20 Bradley Park Road East Granby, CT 06026 Phillip Sargenski - Quality Assurance Manager Phone: 860-653-8376 Fax: 860-653-8301 Phillip.sargenski@marmoniei.com
The vendor provided the final report for this event listing corrective actions and the estimated completion dates. Notified R1DO (Lilliendahl), R3DO (Skokowski), R4DO (Vossmar), and Part 21 group (Email).
The vendor notified the NRC that they plan to send additional finding data regarding this notification via fax and/or email within the next day or two. Notified R1DO (Ferdas), R3DO (Hills), R4DO (Drake), and Part 21 group (Email).
The vendor identified an additional non-compliant shipment of insulated conductor. Affected plant: Calvert Cliffs Notified R1DO (Ferdas), R3DO (Hills), R4DO (Drake), and Part 21 group (Email).
The vendor identified an additional non-compliant shipment of insulated conductor. Affected customer: Curtiss-Wright Nuclear Division. Notified R1DO (Werkheiser), R3DO (Ziolkowski), R4DO (Azua), and Part 21 group (Email).
The vendor is continuing to conduct inventory sampling which involves a 14 day aging test. Due to the length of testing, the vendor plans on submitting their final report the week of October 7, 2024. Notified R1DO (Dimitriadis), R3DO (Havertape), R4DO (Young), and Part 21 group (Email).
The vendor has decided to expand the scope and breadth of the review to ensure they have identified and corrected for the full extent of the matter. Additional time is needed to complete this review. Notified R1DO (Eve), R3DO (Edwards), R4DO (Warnick), and Part 21 group (Email).
The vendor has decided to expand the scope and breadth of the review to ensure they have identified and corrected for the full extent of the matter. RSCC is reviewing shipments from the past 18 months to ensure it has accounted for all non-conforming products. Additional cables related to this scope have been identified and impacted customers have been notified.
The vendor has identified cable(s) that could be affected and have advised customers of the issue and requested that samples be returned to the vendor facility for further verification testing, which is a process that remains ongoing. This testing will confirm the cable's safety related function. Once the testing is complete, the vendor will notify the NRC with an updated and final Part 21 report. Notified R1DO (Arner), R3DO (Gilliam), R4DO (Deese), and Part 21 group (Email).
The vendor provided an update on their ongoing evaluation. The vendor continues to receive product from their customers and perform their evaluations. The process is still ongoing. Notified R1DO (Eve), R3DO (Ruiz), R4DO (Dodson), and Part 21 group (Email).
The vendor provided an update on their ongoing evaluation. The vendor continues to receive product from their customers and is performing evaluations. Test results for completed testing have been forwarded to customers. The process is still ongoing. Notified R1DO (Dimitriadis), R3DO (Orlikowski), R4DO (Dodson), and Part 21 group (Email).
The vendor provided an update on their ongoing evaluation. The vendor continues to receive product from their customers to perform evaluations. Test results for completed testing have been forwarded to customers. The process is still ongoing. Notified R1DO (Carfang), R3DO (Havertape), R4DO (Warnick), and Part 21 group (Email).
The vendor provided an update on their ongoing evaluation. The vendor continues to receive product from their customers to perform testing and evaluations. Test results for completed testing have been forwarded to customers. The process is still ongoing. Notified R1DO (Ford), R3DO (Sanchez Santiago), R4DO (Deese), and Part 21 group (Email).
The vendor provided an update on their ongoing evaluation. The vendor continues to work with customers requesting product be returned for evaluation testing. Test results for completed testing have been forwarded to customers. The process is still ongoing. Notified R1DO (Warnek), R3DO (Ziolkowski), R4DO (Vossmar), and Part 21 group (Email).
The vendor provided an update on their ongoing evaluation. The vendor continues to receive product from their customers to perform testing and evaluations. Test results for completed testing have been forwarded to customers. The process is still ongoing. Notified R1DO (Lilliendahl), R3DO (Ziolkowski), R4DO (Vossmar), and Part 21 group (Email).
The vendor provided an update on their ongoing evaluation. The vendor continues to receive product from their customers to perform testing and evaluations. Test results for completed testing have been forwarded to customers. The process is still ongoing. Notified R1DO (Schussler), R3DO (Hills), R4DO (Deese), and Part 21 group via email. |
| Where | |
|---|---|
| Rscc Dba Marmon East Granby, Connecticut (NRC Region 1) | |
| Organization: | Rscc Dba Marmon |
| Reporting | |
| 10 CFR 21.21(d)(3)(i), Failure to Comply or Defect | |
| Time - Person (Reporting Time:+55.08 h2.295 days <br />0.328 weeks <br />0.0754 months <br />) | |
| Opened: | Phillip Sargenski 11:05 Jul 25, 2024 |
| NRC Officer: | Adam Koziol |
| Last Updated: | Dec 4, 2025 |
| 57243 - NRC Website | |
Rscc Dba Marmon with 10 CFR 21.21(d)(3)(i), Failure to Comply or Defect | |
WEEKMONTHYEARENS 572432024-07-23T04:00:00023 July 2024 04:00:00
[Table view]10 CFR 21.21(d)(3)(i), Failure to Comply or Defect Part 21 Report - NON-COMPLAINT Insulated Conductor 2024-07-23T04:00:00 | |