Final Safety Analysis Report Rev. OL-27 and Technical Specification Bases Rev. 25, Chapter 13, Conduct of Operations
ML24191A224
Person / Time
Site: Callaway Ameren icon.png
Issue date: 05/06/2024
From:
Ameren Missouri, Union Electric Co
To:
Office of Nuclear Reactor Regulation
Shared Package
ML24191A265 List: ... further results
References
ULNRC-06877
Download: ML24191A224 (1)


Text

CALLAWAY - SP 13.0-i TABLE OF CONTENTS CHAPTER 13.0 CONDUCT OF OPERATIONS Section Page 13.1 ORGANIZATIONAL STRUCTURE OF THE APPLICANT............................ 13.1-1 13.2 TRAINING..................................................................................................... 13.1-1 13.3 EMERGENCY PLANNING............................................................................ 13.1-1 13.4 REVIEW AND AUDIT.................................................................................... 13.1-1 13.5 PLANT PROCEDURES................................................................................ 13.1-1 13.6 INDUSTRIAL SECURITY.............................................................................. 13.1-1 13.7 RISK INFORMED CATEGORIZATION AND TREATMENT......................... 13.1-1

CALLAWAY - SP 13.1-1 Rev. OL-27 4/24 CHAPTER 13.0 CONDUCT OF OPERATIONS This chapter provides information relating to the conduct of operations for the Callaway Plant. In the Site Addendum, Chapter 13.0 also describes the Union Electric Co.

organizational structure, the training programs employed, emergency plans, review and audit activities, plant procedures, the industrial security program, and the risk informed categorization and treatment process employed at the plant.

13.1 ORGANIZATIONAL STRUCTURE OF THE APPLICANT Refer to Section 13.1 of the Site Addendum.

13.2 TRAINING Refer to Section 13.2 of the Site Addendum.

13.3 EMERGENCY PLANNING The emergency plans will adequately provide for the health and safety of the public during and following plant emergencies. These plans meet the elements required by Appendix E of 10 CFR 50 and Paragraph 50.34 of 10 CFR 50. Refer to Section 13.3 of the Site Addendum.

13.4 REVIEW AND AUDIT Refer to Section 13.4 of the Site Addendum.

13.5 PLANT PROCEDURES Refer to Section 13.5 of the Site Addendum.

13.6 INDUSTRIAL SECURITY Refer to Section 13.6 of the Site Addendum.

13.7 RISK INFORMED CATEGORIZATION AND TREATMENT Refer to Section 13.7 of the Site Addendum.