June 03, 2025 Phil Hansett, Site Vice President Entergy Operations, Inc.
5485 U.S. Highway 61N St. Francisville, LA 70775
SUBJECT:
RIVER BEND STATION - NOTIFICATION OF NRC FOLLOW-UP INSPECTION FOR THREE OR MORE SEVERITY LEVEL IV TRADITIONAL ENFORCEMENT VIOLATIONS ISSUED IN THE SAME AREA BETWEEN SEPTEMBER 2022 AND DECEMBER 2024 AND REQUEST FOR INFORMATION
Dear Phil Hansett:
By letter dated April 22, 2025 (ML251111A069), the U.S. Nuclear Regulatory Commission (NRC) communicated to you receipt of your acknowledgement of readiness for infrequent inspection procedure 92723 for twelve Severity Level IV Traditional Enforcement Violations that were issued between September 30, 2022, and December 31, 2024.
Accordingly, we plan to conduct a follow-up on-site inspection from July 14, 2025, through July 18, 2025, at River Bend Station, Unit 1 using Inspection Procedure 92723, Follow-Up For One Severity Level III and Two Severity Level IV Traditional Enforcement Violations or For Three or More Severity Level IV Traditional Enforcement Violations in the Same Area in a 12-Month Period.
In order to minimize the impact to your on-site resources and to ensure a productive inspection for both organizations, we have enclosed a request for documents needed for this inspection.
The documents identified are those the inspectors will need prior to and upon their arrival on site. It is important that all the documents are up-to-date and complete to minimize the number of additional documents requested during the on-site portion of the inspection. To the extent possible, please organize the information as specified in the request for documents. Experience has shown that poorly organized files can lead to a less efficient inspection and places an additional burden on licensee staff. Secure file server access such as Certrec or SharePoint is preferred.
During the inspection, the inspectors may request additional documents. If there are questions regarding the documents or material requested, or if the documents cannot be provided by the due date, please do not hesitate to contact lead inspector Christopher Highley at (240) 704-4264 or (817) 200-1933. We have discussed the schedule for these inspection activities with your staff and understand that our regulatory contact for this inspection will be Hayley Kunzli of your organization.
P. Hansett 2
This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information requirements were approved by the Office of Management and Budget, under Control Number 3150-0011.
The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information for an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control number.
In accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records System (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS).
ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Your cooperation and support during this inspection is appreciated.
Sincerely, Douglas E. Dodson II, Chief Projects Branch C Division of Operating Reactor Safety Docket No. 05000458 License No. NPF-47
Enclosure:
Follow-Up Inspection Document Request cc: Distribution via LISTSERV Signed by Dodson, Douglas on 06/03/25
ML25150A239 SUNSI Review ADAMS:
Non-Publicly Available Non-Sensitive Keyword:
By: CJH Yes No Publicly Available Sensitive NRC-002 OFFICE SRI:DORS/PBA BC:DORS/PBC NAME CHighley DDodson SIGNATURE
/RA/
/RA/
DATE 05/30/25 06/03/25
Enclosure FOLLOW-UP INSPECTION DOCUMENT REQUEST Inspection Report: 05000458/2025003 Inspection Dates:
July 14, 2025, through July 18, 2025 Inspection Procedure:
92723 Lead Inspector:
Christopher Highley, DORS/PBA/SRI CGS (240) 704-4264 (C) and (817) 200-1933 (W)
Christopher.Highley@nrc.gov Please assemble the following documents and upload them to your secure file server as soon as possible, but no later than July 3, 2025. For any electronic documents, we kindly ask that you make the documents text or word searchable. If there is any documentation that can only be provided as a hard copy, please have the documents available for the inspectors to review on and by the first date of inspection. Any documents that are provided during the onsite inspection time frame, please provide them in hard copy if possible. The information assembled should be current as of the date of your compilation, unless otherwise specified. Information provided on site should be the latest approved documentation and/or revision, unless otherwise specified.
For the requested procedures, please provide a tabular list of the procedures that have changed or been updated in the last two years. Proprietary information should be clearly marked and listed as such. Draft documentation should not be provided as part of this information request.
The inspectors also request that internet and printer access be provided for the inspectors during the inspection. As a part of the document request, we ask that you include a summary of contents page to describe the contents of each document/folder for ease of inspection. If there are any duplicate requests in the list below, please do not hesitate to reach out to the team lead, Christopher Highley.
Pertaining to the Severity Level IV violations for the following:
(A) NCV 05000458/2022003-02, Failure to Maintain Accurate Information in the Updated Final Safety Analysis Report (B) NCV 05000458/2022004-04, Failure to Obtain License Amendment Prior to Implementing a Proposed Change (C) NCV 05000458/2022010-01, Failure to Obtain Prior Approval for a Change Which Adversely Affected the Approved Fire Protection Program (D) NCV 05000458/2023001-02, Failure to Maintain Accurate Information in the Updated Final Safety Analysis Report (E) NCV 05000458/2023001-04, Failure to Maintain Environmental Qualification of Standby Liquid Control Tank Level Instrument (F) NCV 05000458/2023003-02, Failure to Obtain an Amendment for Technical Specification Bases Change
2 (G) NOV 05000458/2023003-04, Notice of Violation of 10 CFR 50.59, Changes, Tests and Experiments, for the Failure to Obtain a License Amendment for a Change to [the]
Licensing Basis for the Ultimate Heat Sink (H) NCV 05000458/2023003-05, Failure to Maintain Accurate Information in the Updated Final Safety Analysis Report (I) NCV 05000458/2024002-04, Installed Power Supply in Division 1 Emergency Diesel Generator Does Not Meet Updated Safety Analysis Report Requirements (J) NCV 05000458/2024003-05, Failure to Meet Surveillance Requirement 3.0.1 for Control Room Envelope Habitability Failed Surveillance Test (K) NCV 05000458/2023402-01, Failure to Maintain Information Required by the Commissions Regulations Complete and Accurate in All Material Respects (L) NCV 05000458/2024403-01, [Redacted Title]
Please provide the following documentation for the above Severity Level IV violations A -J; for Severity Level IV violations K and L, please have the following information available on the first day of the on-site inspection:
(1) Corrective action program documents associated with each of the violations (2) Causal product documents associated with each of the violations (3) Evaluation(s) for extent of condition and extent of cause for each of the violations (4) Schedule for planned corrective actions that have not been completed and documentation and evidence of completed corrective actions for each of the violations and any common causes, etc.
(5) Any assessments performed for each of the violations (6) Any audits performed for each of the violations (7) Any safety culture evaluations and assessments performed for each of the violations (8) Provide a list of any commitments made in response to the Severity Level IV violations (9) The common cause analysis performed for the Severity Level IV violations (10) Any additional documents of relevance to the events that describe causal factors, extent of condition, extent of cause, programs or procedures enhanced, or corrective actions.
This would include any wholistic reviews, causal products, evaluations, common cause analyses, trend evaluations, etc.