ULNRC-05165, Withdrawal of License Amendment Request OL-1225 Regarding Proposed Changes to Technical Specifications for Extension of Required Action Completion Times for Diesel Generators
| ML051890045 | |
| Person / Time | |
|---|---|
| Site: | Callaway |
| Issue date: | 06/28/2005 |
| From: | Keith Young AmerenUE, Union Electric Co |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| ULNRC-05165 | |
| Download: ML051890045 (3) | |
Text
Union Electric One Ameren Plaza 1901 Chouteau Avenue PO Box 66149 St. Louis, MIO 6316-6149 314.621.3M June 28, 2005 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Mail Stop P1 -137 Washington, DC 20555-0001 wAmeren UE Ladies and Gentlemen:
ULNRC-05165 DOCKET NUMBER 50-483 CALLAWAY PLANT UNIT 1 UNION ELECTRIC CO.
WITHDRAWAL OF LICENSE AMENDMENT REQUEST OL-1225 REGARDING PROPOSED CHANGES TO TECHNICAL SPECIFICATIONS FOR EXTENSION OF REQUIRED ACTION COMPLETION TIMES FOR DIESEL GENERATORS Reference 1: AmerenUE Letter ULNRC-04866, "License Amendment Request OL-1225 - Revision to Technical Specifications for Extension of Required Action Completion Time for Diesel Generators," dated June 27, 2003 Reference 2:
Reference 3:
AmerenUE Letter ULNRC-04917, "Revision of License Amendment Request OL-1225 Regarding Proposed Changes to Technical Specification for Extension of Required Action Completion Times for Diesel Generators," dated December 19, 2003 AmerenUE Letter ULNRC-04911, "Response to Request for Additional Information Regarding License Amendment Request OL-1225 (Revision to Technical Specifications for Extension of Required Action Completion Time for Diesel Generators)," dated January 30, 2004 Per the letter of Reference 1, and as supplemented and/or revised by the letters identified as References 2 and 3, Union Electric Company (AmerenUE) submitted to the NRC an application for amendment of the Callaway Facility Operating License (License No. NPF-30) to incorporate proposed changes to the Technical Specifications. The essential change that was proposed would have revised Technical Specification (TS) 3.8.1, "AC Sources - Operating," to allow a longer Required Action Completion Time (allowed outage time) for an inoperable diesel generator, based on a risk-informed evaluation of the longer Completion Time, when removing the diesel generator from service to perform voluntary, planned maintenance.
a subsidiary ofAmeren Corporation
ULNRC-05 165 June 28, 2005 Page 2 The subject amendment request is still under review by the NRC staff.
However, a telephone conversation was conducted between AmerenUE and NRC personnel on May 26, 2005 to discuss the status and continued NRC review of AmerenUE's amendment application, and it was determined that the amendment request should be withdrawn. This letter is therefore submitted to request withdrawal of AmerenUE's amendment application, based on the May 26 discussion.
Please contact us for any questions you may have regarding the requested action.
Very truly yours, vdi Keith D. Young Manager - Regulatory Affairs TBE/jdg
ULNRC-05165 June 28, 2005 Page 3 cc:
U.S. Nuclear Regulatory Commission (Original and 1 copy)
Attn: Document Control Desk Mail Stop P1-137 Washington, DC 20555-0001 Mr. Bruce S. Mallett Regional Administrator U.S. Nuclear Regulatory Commission Region IV 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-4005 Senior Resident Inspector Callaway Resident Office U.S. Nuclear Regulatory Commission 8201 NRC Road Steedman, MO 65077 Mr. Jack N. Donohew (2 copies)
Licensing Project Manager, Callaway Plant Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Mail Stop 7EI Washington, DC 20555-2738 Missouri Public Service Commission Governor Office Building 200 Madison Street PO Box 360 Jefferson City, MO 65102-0360 Deputy Director Department of Natural Resources P.O. Box 176 Jefferson City, MO 65102