Request for Additional Information Traveler TSTF-542, Revision 0, Reactor Pressure Vessel Water Inventory Control, Schedule Change
ML14350A039
Person / Time
Site: Technical Specifications Task Force
Issue date: 12/18/2014
From: Michelle Honcharik
Licensing Processes Branch (DPR)
To:
Technical Specifications Task Force
M Honcharik, 301-415-1774
References
TAC MF3487
Download: ML14350A039 (4)


Text

December 18, 2014 Technical Specifications Task Force 11921 Rockville Pike, Suite 100 Rockville, MD 20852

SUBJECT:

REQUEST FOR ADDITIONAL INFORMATION RE: TRAVELER TSTF-542, REVISION 0, "REACTOR PRESSURE VESSEL WATER INVENTORY CONTROL," SCHEDULE CHANGE (TAC NO. MF3487)

Dear Members of the Technical Specifications Task Force:

By letter dated October 10, 2014 (Agencywide Documents Access and Management System Accession No. ML14279A271), the U.S. Nuclear Regulatory Commission (NRC) staff transmitted request for additional information (RAI) questions for the review of Traveler TSTF-542. The originally scheduled response date was January 8, 2015. The NRC staff has determined that due to other priority work they will not be able to review the RAI responses during the month of January and are therefore granting an extension. On December 17, 2014, Brian Mann, Vice President of Industry Programs, EXCEL Services Corporation, and I agreed that the NRC staff will receive your response to the previously provided RAI questions by January 31, 2015. If you have any questions, please contact me at 301-415-1774 or via e-mail at Michelle.Honcharik@nrc.gov.

Sincerely,

/RA/

Michelle C. Honcharik, Sr. Project Manager Licensing Processes Branch Division of Policy and Rulemaking Office of Nuclear Reactor Regulation Project No. 753 cc: See next page

ML14350A039 *concurred via email NRR-106 OFFICE NRR/DPR/PLPB*

NRR/DPR/PLPB NRR/DPR/PLPB NRR/DPR/PLPB NAME MHoncharik DHarrison AMendiola MHoncharik DATE 12/18/14 12/17/14 12/18/14 12/18/14

Letter to Technical Specifications Task Force from M. Honcharik dated December 18, 2014.

SUBJECT:

REQUEST FOR ADDITIONAL INFORMATION RE: TRAVELER TSTF-542, REVISION 0, "REACTOR PRESSURE VESSEL WATER INVENTORY CONTROL," SCHEDULE CHANGE (TAC NO. MF3487)

DISTRIBUTION:

PUBLIC RidsNrrOd RidsNrrDpr RidsOgcMailCenter RidsOpaMail RidsAcrsAcnwMailCenter RidsNrrPMMHoncharik RidsNrrLADHarrison RidsNrrDprPlpb RidsNrrDeEicb RidsNrrDssSrxb RidsNrrDssStsb Kristy Bucholtz Matthew Hardgrove Eugene Eagle Terry Beltz RidsResOd

Technical Specifications Task Force Project No.753 cc:

Technical Specifications Task Force c/o EXCEL Services Corporation 11921 Rockville Pike, Suite 100 Rockville, MD 20852 Attention: Brian D. Mann E-mail: brian.mann@excelservices.com Robert A. Slough Comanche Peak Nuclear Power Plant P. O. Box 1002, Mail Code A08 Glen Rose, TX 76043 E-mail: robert.slough@luminant.com Joseph A. Clark Entergy Nuclear South 5485 Highway 61 St. Francisville, LA. 70775 E-mail: jclark@entergy.com Otto W. Gustafson Entergy Nuclear Operations, Inc.

Palisades Nuclear Power Plant 27780 Blue Star Memorial Highway Covert, MI 49043 E-mail: ogustaf@entergy.com Henry L. Hegrat FirstEnergy Nuclear Operating Company P. O. Box 97 Perry, OH 44081 Mail Stop A-210 E-mail: hlhegrat@firstenergycorp.com