Description TSTF Number Applicability Active Travelers Summary Report (See Topics Report for More Information)
Add Exceptions to Surveillance Requirements When the Safety Function is Being Performed TSTF-541, Rev. 0 All Actions and Schedule Responsibility Date NRC Review Fees To Date: $74,621.02 (Shared)
Topic Number: 1249 Originally Submitted: 9/10/2013 Originally Scheduled for Approval: 9/30/2016 Age: 31 Months Number of Times Approval Date has been Rescheduled:
1 TSTF-541 submitted to the NRC on September 10, 2013.
9/10/2013 TSTF NRC transmitted the acceptance and schedule letter on August 13, 2015.
8/13/2015 NRC NRC transmitted a Request for Additional Information on August 13, 2015.
11/11/2015 TSTF TSTF responded to request for additional information on November 11, 2015.
11/12/2015 TSTF NRC to provide revised review schedule.
12/3/2015 - a new review schedule was provided:
Second round RAIs to be provided in mid-February, 2016.
Draft safety evaluation to be provided by November 7, 2016.
12/3/2015 NRC NRC provided a second round RAI on February 26, 2016. Of the 21 questions, approximately half appear to be repetitive of the first round RAI.
TSTF to evaluate the draft RAI and, if needed, request an executive meeting to discuss the RAIs.
4/29/2016 TSTF Page 1 of 3 28-Apr-16
Description TSTF Number Applicability Active Travelers Summary Report (See Topics Report for More Information)
Reactor Pressure Vessel Water Inventory Control TSTF-542, Rev. 2 BWRs Actions and Schedule Responsibility Date NRC Review Fees Waived Topic Number: 1331 Originally Submitted: 12/31/2013 Originally Scheduled for Approval: 12/31/2014 Age: 28 Months Number of Times Approval Date has been Rescheduled:
2 TSTF-542 and fee exemption request submitted to the NRC on 12/31/2013.
12/31/2013 TSTF NRC to issue fee exemption.
2/24/2014 - Fee exemption granted.
2/24/2014 NRC At the July 10, 2014 TSTF/NRC meeting, the NRC stated their schedule for reviewing TSTF-542 is:
(1)NRC to provide an RAIs 10/1/2014 (2)Industry to respond 12/31/2014 (3)Notice for Comment 3/31/2015 (4)Notice of Availability 6/30/2015 7/10/2014 NRC NRC RAI received on 10/10/2014.
10/16/2014 NRC Responding to the RAI required extensive revision to the Traveler and multiple rounds of industry review to ensure accuracy. TSTF-542, Revision 1, and RAI response submitted.
9/15/2015 TSTF A public meeting discussing the draft RAI was held on November 5. NRC provided the RAI on December 3, 2015.
12/31/2015 NRC TSTF responded to the RAI on March 14, 2016.
3/8/2016 TSTF NRC to provide the draft safety evaluation.
7/14/2016 NRC Revise APRM Channel Adjustment Surveillance Requirement TSTF-546, Rev. 0 BWRs Actions and Schedule Responsibility Date No NRC Review Fees Received Topic Number: 1350 Originally Submitted: 4/21/2016 Originally Scheduled for Approval: Not Provided Age: 0 Months Number of Times Approval Date has been Rescheduled:
0 NRC to provide acceptance and review schedule.
7/22/2016 NRC Page 2 of 3 28-Apr-16
Description TSTF Number Applicability Active Travelers Summary Report (See Topics Report for More Information)
Revise Secondary Containment Surveillance Requirements TSTF-551, Rev. 1 BWRs Actions and Schedule Responsibility Date NRC Review Fees To Date: $136,360.75 (BWROG)
Topic Number: 1386 Originally Submitted: 10/30/2014 Originally Scheduled for Approval: 3/8/2016 Age: 18 Months Number of Times Approval Date has been Rescheduled:
1 TSTF-551, Revision 0, "Address Transient Secondary Containment Conditions" was submitted on October 30, 2014.
10/30/2014 TSTF On March 12, 2015, the NRC provided a revised review schedule.
NRC to provide RAIs 5/8/15 TSTF response 8/6/15 Notice for Comment 1/3/16 Notice of Availability 5/2/16 5/8/2015 NRC On a May 7, 2015 teleconference, the TSTF agreed to revise the Traveler in lieu of NRC sending a formal RAI.
6/30/2015 TSTF TSTF submitted TSTF-551, Revision 1, on September 3, 2015.
9/3/2015 TSTF NRC to provide RAI. Teleconference to discuss RAIs held on 10/19/15.
On 11/5/15, TSTF agreed to a 45 day response time for the RAI.
RAI provided on 11/18/2015. It included a new review schedule:
Issue Draft Safety Evaluation by May 26, 2016 Issue Final Safety Evaluation by July 23, 2016.
11/30/2015 NRC The TSTF responded to the NRC RAI on January 26, 2016.
1/26/2016 TSTF TSTF and NRC held a teleconference to discuss the wording of the proposed SR 3.6.4.1.1 Note. The TSTF agreed to submit a revision to address the staff concerns.
5/13/2016 TSTF Add Action for Two Inoperable CREATCS Trains TSTF-553, Rev. 0 B&W W Actions and Schedule Responsibility Date NRC Review Fees To Date: $82,047.86 (PWROG)
Topic Number: 1423 Originally Submitted: 10/31/2015 Originally Scheduled for Approval: 10/31/2016 Age: 6 Months Number of Times Approval Date has been Rescheduled:
0 TSTF submitted TSTF-553 on October 31, 2015.
10/31/2015 TSTF NRC provided acceptance and schedule letter on December 15, 2015.
Issue RAI - February 23, 2016 Issue Draft SE - August 26, 2016 Issue Final SE - October 31, 2016 12/15/2015 NRC NRC provided RAI on February 23, 2016.
2/23/2016 NRC NRC and TSTF held a teleconference to discuss a draft RAI response on 4/20/16. TSTF to revise the response and share with NRC prior to submittal.
5/31/2016 NRC Active Travelers: 5 Page 3 of 3 28-Apr-16