ML19273B704
| ML19273B704 | |
| Person / Time | |
|---|---|
| Site: | Beaver Valley |
| Issue date: | 05/07/1979 |
| From: | Grier B NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
| To: | Woolever E DUQUESNE LIGHT CO. |
| References | |
| NUDOCS 7906120156 | |
| Download: ML19273B704 (2) | |
Text
~v 4 UNB1ED STATTd g>n arou
'g NUCLEAR REGU LATORY COMMISSION
+
[
F.EGION I o
Is f
$31 PARK AVENUE KING QF PRUSSI A. PENN5YLV ANI A l's406 Docket No. 50-412 Duquesne Light Company ATTN:
Mr. E. J. Woolever Vice President 435 Sixth Avenue Pittsburgh, PA 15219 Gentlemen:
This Information Notice is provided as an early notification of a possibly significant matter.
It is expected that recipients will review the information for possible applicability to their facili-ties.
No specific action or response is requested at this time.
If further NRC evaluations so indicate, an IE Circular or Bulletin will be issued to recommend or request specific licensee actions.
If you have question:. regarding this mater, please contact the Director of the appropriate NRC Regional Office.
Sincerely,
%)Ma_
h Boyce H. Grier i
Director
Enclosures:
1.
IE Information Notice 2350 5.i i
No. 79-11 2.
List of Information Notices Issued in 1979 7906120/ S.(.
')
3 Duquesne Light Company 2
cc w/encis:
R. J. Washabaugh, Quality Assurance Manager 2350 512
UNITED STATES NUCLEAR REGULATORY COMMISSION OFFICE OF INSPECTION AND ENFORCEMENT WASHINGTON, D.C.
20555 IE Information Notice No. 79-11 Date:
May 7, 1979 Page 1 of 1 LOWER REACTOR VESSEL HEAD INSULATION SUPPORT PROBLEM Virginia Electric and Power Company, North Anna Power Station No.
1 reported on November 8,1978, a field modification pertaining to the lower vessel head insulation support system which was not seismically analyzed at the time of modification.
A subsequent stress analysis indicated that the ASME Code allowable stress and the yield stress for the operating base earthquake (OBE) on some of the instrument guide tubes were exceeded.
For the North Anna No. 1 field modification, the lower vessel head insulation was supported by angle brackets that are clamped onto the gridwork to about 20 of the 53 instrument guide tubes.
This additional load on the guide tubes was not considered in the original stress analysis.
The maximum stress occurs in the socket welds between the Thimble guide tubes and the Instrumentation nozzles that penetrate the vessel.
The maximum stress was about 70 percent of the ultimate and, therefore, violation of the pressure boundary would not be expected.
VEPC0 plans to modify the supporting arrangement by building a framework underneath the insulation, which will take the loading off the guide tubes.
All holders of operating licenses and/or construction permits should be aware of the potential problem of exceeding the allowa-ble stress and the yield stress for OBE.
This Information Notice is provided as an early notification of a possibly significant matter.
It is expected that recipients will review the information for possible applicability to their facilities.
No specific action or response is requested at this time.
If further NRC evaluations so indicate, an IE Circular or Bulletin will be issued to recommend or request specific licensee actions.
If you have questions regarding the matter, please contact the Director of the appropriate NRC Regional Office.
No written response to this information notice is required.
Enclosure:
2350 313 List of IE Information Notices Issued in 1979 7906060158
IE Information Notice No. 79-11 Date:
May 7, 1979 Page 1 of 1 LISTING OF IE INFORMATION NOTICES ISSUED IN 1979 Information Subject Date Issued To Notice No.
Issued 79-01 Bergen-Paterson Hydraulic 2/2/79 All power reactor Shock and Sway Arrestor facilities with an Operating License (OL) or Constructinn Permit (CP) 79-02 Attempted Extortion -
2/2/79 All Fuel Facilities Low Enriched Uranium 79-03 Limitorque Valve Geared 2/9/79 All power reactor Limit Switch Lubricant facilities with an OL or CP 79-04 Degradation of 2/16/79 All power reactor Engineered facilities with an Safety Features OL or CP 79-05 Use of Improper Materials 3/21/79 All power reactcr in Safety-Related Components facilities with an OL or CP 79-06 Stress Analysis of 3/23/79 All power reactor Safety-Related Piping facilities with an OL or CP 79-07 Rupture of Radwaste Tanks 3/26/79 All power reactor facilities with an OL or CP 79-08 Interconnection of 3/28/79 All power reactor Contaminated Systems with facilities with an Service Air Systems Used OL and Pu Processing As the Source of Breathing fuel facilities Air 79-09 Spill of Radioactively 3/30/79 All power reactor Contaminated Resin facilities with an OL 79-10 Nonconforming Pipe 4/16/79 All power reactor Support Struts facilities with a CP 2350 H4