ML19350A831
| ML19350A831 | |
| Person / Time | |
|---|---|
| Site: | Davis Besse |
| Issue date: | 02/09/1981 |
| From: | Heishman R NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III) |
| To: | Crouse R TOLEDO EDISON CO. |
| Shared Package | |
| ML19350A832 | List: |
| References | |
| NUDOCS 8103160948 | |
| Download: ML19350A831 (2) | |
See also: IR 05000346/1980034
Text
-_
'o
UNITED STATES
i
<
8
N
NUCLEAR REGULATORY COMMISSION
'
'
4
E
REGION lli
s
.
k
799 ROOSEVELT ROAD
%.....o
GLEN ELLYN, ILLINOIS Co137
February 9, 1981
4
0)
c
Docket No. 50-346
s
Toledo Edison Company
ff
I
U1
{
8.s.
J g$g7 g 7
ATTN:
Mr. Richard P. Crouse
-
Vice President
Y
Nuclear
%w$g
Edison Plaza
9
/
300 Madison Avenue
Toledo, OH 43652
co
co
Gentlemen:
This refers to the routine inspection conducted by Mr. J. D. Smith of
this office on December 10-12, 1980, and Mr. W. G. Rogers of this office
on December 5, 6, 8-12, 15-19 and 22, 23, 1980, of activities at Davis-Besse
Nuclear Power Station, Unit 1, authorized by NRC Operating License No. NPF-3
and to the discussion of our findings with Mr. T. D. Murray through the
course of the inspection.
The enclosed copy of our inspection report identifies areas examined
during the inspection. Within these areas, the inspection consisted
of a selective examination of procedures and representative records,
observations, and interviews with personnel.
No items of noncompliance with NRC requirements were identified during
the course of this inspection.
In accordance with Section 2.790 of the NRC's " Rules of Practice," Part 2,
Title 10, Code of Federal Regulations, a copy of this letter and the
enclosed inspection report will be placed in the NRC's Public Documant
Room, except as follows. If this report contains information that you
or your contractors believe to be proprietary, you must apply in writing
to this office, within twenty-five days of the date of this letter, to
withhold such information from public disclosure. The application must
include a full statement of the reasons for which the information is con-
sidered proprietary, and should be prepared so that proprietary information
identified in the application is contained in an enclosure to the application.
81031609.48
-
- - - .
-
.
-
...
-
_ ..
. .
Toledo Edison Company
-2-
We will gladly discuss any questions you have concerning this
inspection.
Sincerely,
,
9
. F. Heishman, Chief
Reactor Operations and Nuclear
Support Branch
Enclosure:
IE Inspection
Report No. 50-346/80-34
i
cc w/ enc 1:
T. D. Murray, Station
Superintendent
Central Files
Reproduction Unit NRC 20b
AE0D
Resident Inspector, RIII
Local PDR
Harold W. Kohn, Power
Siting Commission
Helen W. Evans, State of Ohio