ENS 46898
ENS Event | |
---|---|
21:44 Apr 3, 2011 | |
Title | 60-Day Optional Notification of Invalid Start of the 'A' Emergency Diesel Generator |
Event Description | The following event description is based on information currently available. If through subsequent reviews of this event, additional information is identified that is pertinent to this event or alters the information being provided at this time, a follow-up notification will be made via the ENS or under the reporting requirements of 10CFR50.73.
This report is being made under 10 CFR 50.73 (a) (2) (iv) (A) for a reportable invalid actuation. On April 3, 2011, at approximately 1444 Mountain Standard Time, Palo Verde Nuclear Generating Station Unit 2 experienced an invalid actuation (start) of the 'A' Emergency Diesel Generator (EDG). EDG 'A' inadvertently started during integrated safeguards surveillance testing to demonstrate that the EDG overspeed trip is not bypassed. Prior to the test, the EDG overspeed governor was actuated, but the butterfly valve was not verified to be fully closed as required. The valve closure actuates a limit switch which activates the interlock that prevents the EDG start following an overspeed trip. The test requires the operator to ensure the butterfly valve is fully closed because it may not fully close as the EDG is not running when it is actuated for the overspeed test. When the demand signal was inserted, the EDG started unexpectedly since the butterfly valve was not fully closed and the limit switch was not engaged. EDG 'A' Train completely actuated in the Emergency Mode and the EDG came up to rated speed and voltage as designed. The supporting 'A' train Essential Spray Pond System, used for engine cooling, was already running prior to the test. The Essential 'A' Train EDG Exhaust Room air handling unit started as required. No damage occurred to the EDG or related equipment as a result of the unplanned actuation. The EDG was secured and the test was successfully re-performed. This report is not considered an LER. The licensee has notified the NRC Resident Inspector. |
Where | |
---|---|
Palo Verde Arizona (NRC Region 4) | |
Reporting | |
10 CFR 50.73(a)(1), Submit an LER, Invalid Actuation | |
Time - Person (Reporting Time:+1289.48 h53.728 days <br />7.675 weeks <br />1.766 months <br />) | |
Opened: | Jorge Rodriguez 15:13 May 27, 2011 |
NRC Officer: | Howie Crouch |
Last Updated: | May 27, 2011 |
46898 - NRC Website
Loading map... {"minzoom":false,"maxzoom":false,"mappingservice":"leaflet","width":"350px","height":"250px","centre":false,"title":"","label":"","icon":"","lines":[],"polygons":[],"circles":[],"rectangles":[],"copycoords":false,"static":false,"zoom":6,"defzoom":14,"layers":["OpenStreetMap"],"image layers":[],"overlays":[],"resizable":false,"fullscreen":false,"scrollwheelzoom":true,"cluster":false,"clustermaxzoom":20,"clusterzoomonclick":true,"clustermaxradius":80,"clusterspiderfy":true,"geojson":"","clicktarget":"","imageLayers":[],"locations":[{"text":"\u003Cb\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003E\u003Ca class=\"mw-selflink selflink\"\u003EENS 46898\u003C/a\u003E - \u003Ca href=\"/Palo_Verde\" title=\"Palo Verde\"\u003EPalo Verde\u003C/a\u003E\n\u003C/p\u003E\u003C/div\u003E\u003C/b\u003E\u003Cdiv class=\"mw-parser-output\"\u003E\u003Cp\u003E60-Day Optional Notification of Invalid Start of the 'A' Emergency Diesel Generator\n\u003C/p\u003E\u003C/div\u003E","title":"ENS 46898 - Palo Verde\n","link":"","lat":33.386894444444444,"lon":-112.86263333333333,"icon":"/w/images/9/93/Arizona_Public_Service_icon.png"}],"imageoverlays":null} | |
Unit 2 | |
---|---|
Reactor critical | Not Critical |
Scram | No |
Before | Cold Shutdown (0 %) |
After | Cold Shutdown (0 %) |
WEEKMONTHYEARENS 559262022-04-12T03:45:00012 April 2022 03:45:00
[Table view]10 CFR 50.73(a)(1), Submit an LER Invalid System Actuation ENS 550322020-12-11T07:00:00011 December 2020 07:00:00 10 CFR 50.73(a)(1), Submit an LER 60-Day Option Telephonic Notification of an Invalid Specified System Actuation ENS 547012020-03-14T19:44:00014 March 2020 19:44:00 10 CFR 50.73(a)(1), Submit an LER Invalid Actuation of Spray Pond Pump System - 60 Day Reports ENS 524132016-10-17T22:19:00017 October 2016 22:19:00 10 CFR 50.73(a)(1), Submit an LER Invalid Engineered Safety Features Actuation System (Esfas) Signal ENS 522282016-07-12T12:50:00012 July 2016 12:50:00 10 CFR 50.73(a)(1), Submit an LER Invalid Actuation of Both Trains Essential Spray Pond System ENS 498072013-12-12T03:11:00012 December 2013 03:11:00 10 CFR 50.73(a)(1), Submit an LER 60 Day Report for an Invalid Main Steam Line Actuation ENS 486152012-10-26T04:08:00026 October 2012 04:08:00 10 CFR 50.73(a)(1), Submit an LER 60-Day Optional Telephonic Notification for an Invalid Actuation of the Essential Spray Pond System ENS 468982011-04-03T21:44:0003 April 2011 21:44:00 10 CFR 50.73(a)(1), Submit an LER 60-Day Optional Notification of Invalid Start of the 'A' Emergency Diesel Generator ENS 427342006-06-06T01:44:0006 June 2006 01:44:00 10 CFR 50.73(a)(1), Submit an LER Invalid Emergency Diesel Generator Start ENS 418042005-04-29T07:43:00029 April 2005 07:43:00 10 CFR 50.73(a)(1), Submit an LER Invalid System Actuation 2022-04-12T03:45:00 | |