ML20134C082

From kanterella
Revision as of 05:43, 12 December 2024 by StriderTol (talk | contribs) (StriderTol Bot change)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
Submits Response to GL 96-06, Assurance of Equipment Operability & Containment Integrity During Design-Basis Accident
ML20134C082
Person / Time
Site: Comanche Peak  
Issue date: 01/27/1997
From: Terry C
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
GL-96-06, GL-96-6, TXX-97019, NUDOCS 9701310227
Download: ML20134C082 (5)


Text

.

I a

1 a Nmmer Log # TXX-97019 i

MM File # 10010 i

Ref # 10035

~

]

GL 96 06 1UELECTRIC' 1

January 27, 1997 C. Lance Terry Cup Mce President U. S. Nuclear Regulatory Commission i

Attn: Document Control Desk j

Washington, DC 20555 l

SUBJECT:

COMANCHE PEAK STEAN ELECTRIC STATION (CPSES) i DOCKET NOS. 50-445 AND 50 446 RESPONSE TO NRC GENERIC LETTER 96 06

" ASSURANCE OF EQUIPMENT OPERABILITY AND CONTAINHENT INTEGRITY DURING DESIGN BASIS ACCIDENT" REF:

Letter logged TXX 96485, dated October 30. 1996, j

from C. L. Terry to the NRC i

j On October 1. 1996, the NRC issued Generic Letter 96 06. " Assurance of Equipment Operability and Containment Integrity during Design Basis Accident." TU Electric provided the initial response to the.NRC request in j

the referenced letter.

Following are the results of the completed review to address the subject Generic Letter and the actions taken.

l TU Electric has determined that:

1 i

(1)

The containment air cooler cooling water system on each unit may be j

susceptible to water hammer; however, operability of post accident i

containment cooling and containment isolation would not be affected.

The two phase flow condition issue is not applicable to CPSES.

(2)

Piping systeis that penetrate the containment of each unit have been provided with overpressure protection for thermal expansion of trapped fluid between containment isolation valves and overpressurization of containment penetration piping should not occur.

Further action is required in three cases.

Operability of containment isolation has been evaluated in each of these cases as described below.

In the initial response TU Electric identified that CPSES does not employ containment air coolers for post accident containment heat removal.

Instead, the containment spray system is sized to carry the full containment heat removal function for post accident conditions. Therefore, the issue of two phase flow is not applicable to CPSES.

The containment air coolers are non safety related and are cooled by a non-I A OM f

9701310227 970127 PDR ADOCK 05000445 P

PDR g

P. O. Box 1002 Glen Rose Texas 76043

_. _ _ _ _ _ _. - _ ~.... _ _ _

1 I

TXX 97019 j

Page 2 of 4 safety related cooling water system.

Each unit's fan is de energized and the common cooling water supply and return isolated by the Containment i

Isolation Phase A actuation signal during LOCA and MSLB accidents.

However, the water hammer issue is applicable because CPSES emergency procedures allow restoration of cooling water flow to aid in containment i

heat ren. oval. This is a desirable function even though not credited in i

i safety analyses.

)

Because the containment air coolers are normally operating, fan coast down 4

could add sufficient heat for steam formation in the cooling water coils of

)

f the containment air coolers.

If the cooling system were put in service i

during recovery and a water hammer resulted, the layout of the system j

inside containment is such that the hydrodynamic loads would be expected to occur in the cooling coils and to be dissipated in the local piping and l

fittings such that the containment penetration operability would not be l

affected. Any resultant leakage would be into containment and would be i

detectable by a level alarm from the cooling water system's surge tank.

The containment isolation valves are redundant MOVs which are i

environmentally qualified for the duration of the accident and would be capable of re 1solating containment as needed.

The applicable procedures have been reviewed for this potential condition.

l Shift operations have been cautioned that they should contact the emergency l

response organization TSC engineering team prior to restoring cooling water j

to the containtant air coolers.

Emergency procedures will be revised to require an evaluation by the TSC engineering team prior to reestablishing chilled water to containment.

No additional action beyond that identified above is required.

TV Electric also identified, in the initial response, that CPSES has thermal r?1ief valves between containment isolation valves in penetrations i

where the potential for over pressurization of isolated piping during and after a LOCA was determined. A review of overpressure protection provisions was performed for both Unit 1 and Unit 2 to confirm each penetration has adequate relief. Three cases have been identified where further action is required.

In each case, overpressure protection design features exist; however, there are circumstances under which the relief valves may be isolated from the containment penetrations during and after a design basis accident.

In the first thermal expansion case, either of two relief valves are normally available to protect the component cooling water loop to two heat i

exchangers in containment. Under unusual circumstances, one or both of these valves could be isolated by manual valves if the heat exchangers were taken out of service. Shift operations have been informed of this situation.

A design change will be issued to lock open the isolation valves to ensure a relief path is available in Modes 1 through 4.

Based on the direction provided to shift operations, no additional action beyond that identified above is required.

l

TXX 97019

{.

Page 3 of 4 In the second thermal expansion case, any of four relief valves are available to protect the component cooling water return from the Reactor i

Coolant Pump Thermal Barriers. An automatic isolation valve is located i

between the penetration and each relief valve.

Each valve receives a close i

signal on high temperature in the cooling water return lines from each i

pump. Because the lines are insulated and the containment temperature i

drops below the setpoint in less than 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />, it is not likely that the fluid temperature would exceed the setpoint. Although overpressure to the a

point of failure is unlikely based on conservatisms in the design, containment integrity would not be lost if it occurred. The thermal expansion /over pressure scenario assumes the CCW piping to be intact and leak tight even though it is not required to be for containment isolation.

A failure or increased leakage due to the pressure increase would not result in a containment breach. Design modification and analysis options are being considered. The CCW piping barrier is found to be operable, as discussed above, however, TV Electric is continuing to evaluate the design regarding this condition and anticipates design changes to address the effect of thermal expansion on the CCW piping.

No additional action beyond that identified above is required.

In the third thermal expansion case, the Unit 1 personnel airlock hydraulic system penetrates the containment boundary and has been classified as a closed system inside containment. The system is isolated by locked closed manual valves outside containment when the airlock is not in use. This isolates the relief valve and lines trapping the hydraulic fluid in the closed system. An analysis of thermal expansion overpressure is in progress and has not been completed. Operability has been evaluated.

If the pressure increased significantly due to thermal expansion, the system contains mechanical seals which would begin to leak and relieve the pressure. A failure or increased leakage due to the pressure increase would not result in a containment breach. The isolation barrier is found to be operable, as discussed above, however, TV Electric is continuing to evaluate the design regarding this condition and anticipates design chances to address the effect of thermal expansion on the hydraulic system.

No additional action beyond that identified above is required.

TXX 97019 3

Page 4 of 4 i

If you have any questions regarding the above information, please contact Mr. J. D. Seawright at (817)897 0140.

l S ncerely, i

C. L.

err JDS/jds 4

Attachment u

\\

c-Mr. L. J. Callan. Region IV Mr. T. J. Polich. NRR (3 copies) i Mr. J. I. Tapia. Region IV Resident Inspector. CPSES j

0

Attachment to TXX 97019 Page 1 of 1 UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION 1

In the Matter of

)

)

Texas Utilities Electric Company

)

Docket Nos.

50 445

)

50 446 (Comanche Peak Steam Electric

)

License Nos. NPF 87 Station, Units 1 & 2)

)

nr'F 89 i

AFFIDAVIT s

C. L. Terry being duly sworn, hereby deposes and says that he is 1

Group Vice President, Nuclear Production of the Comanche Peak Steam Electric Station, that he is duly authorized to sign and file with the Nuclear Regulatory Commission this response to Generic Letter 96 06; that he is familiar with the content thereof: and that the matters set forth therein are true and correct to the best of his knowledge, information and i,

belief.

I i

./Ndue C. 1. Terry 1

Group Vice resident.

Nuclear Pro u6 tion STATE OF TEXAS

)

)

2 COUNTY OF5 4*rve// )

Subscribed and sworn to before me, a Notary Public, on this J74 day of Gh/

, 1997.

ML e 8

g' e.

2 SUSAN C.GRAVATT

/ Notary Publicy

.e NOTARY PUBLIC

/

\\ ^/

STATE: OF TEXAS Commission Expires 3-24 97 i