MONTHYEARML22306A0512022-10-27027 October 2022 Notification of Amended Post-Shutdown Decommissioning Activities Report (PSDAR) in Accordance with 10 CFR 50.82(a)(7), Revision 5 Project stage: Request ML23058A0642023-02-22022 February 2023 License Amendment Request - Three Mile Island, Unit 2, Historic and Cultural Resources Review Project stage: Request ML23121A2492023-05-0101 May 2023 License Amendment Request, Historic and Cultural Resources Review, Response to Request for Additional Information Project stage: Response to RAI ML23187A0332023-06-29029 June 2023 TMI Unit 2, PSDAR Rev. 5 RAIs Project stage: Other 2023-02-22
[Table View] |
|
---|
Category:Request for Additional Information (RAI)
MONTHYEARML24011A2352024-01-11011 January 2024 Eco Request for Additional Information for 2023 License Amendment Request 1-11-24 ML23187A0202023-06-29029 June 2023 TMI Unit 2 RAI Related to the Amended Post-Shutdown Decommissioning Activities Report ML23187A0332023-06-29029 June 2023 TMI Unit 2, PSDAR Rev. 5 RAIs ML23082A3432023-03-31031 March 2023 Enclosure - RAI - Three Mile Island, Unit 2 - Acceptance Review and Request for Additional Information for the Historic and Cultural Resources License Amendment Request - EPID: 2023-LLA-0026 ML22357A0142022-12-22022 December 2022 NRC Request for Additional Information Related to the TMI-2 Pdms Transition License Amendment Request ML22210A0882022-07-29029 July 2022 Enclosure - Three Mile Island, Unit No. 2 - Request for Additional Information for Requested Licensing Action Regarding Decommissioning Technical Specifications ML22143A8902022-05-23023 May 2022 Request for Additional information- TMI-1 ISFSI Only Physical Security License Amendment Request ML22125A0122022-04-28028 April 2022 Clarification RAI Partial Response Email from C Smith to a Snyder ML22110A0202022-04-19019 April 2022 Unit 1 Request for Additional Information ML22038A9362022-02-0707 February 2022 TMI2 Accident Analyses Questions ML21256A1902021-09-10010 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21144A2132021-05-24024 May 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML20164A0902020-06-10010 June 2020 Request for Additional Information Related to TMI-1 License Amendment Request to Delete Permanently Defueled Technical Specification 3/4.1.4 (L-2019-LLA-0250) ML19319B2082019-11-15015 November 2019 NRR E-mail Capture - Request for Additional Information Related to TMI-1 Request for Exemption from Portions of 10 CFR 50.47 and Part 50 Appendix E (L-2019-LLA-0216) ML19179A0612019-07-19019 July 2019 Three Mile Point 1 - Supplemental Information Needed to Proposed Alternative to Use ASME Code Case N-879 ML18220A7832018-08-0707 August 2018 NRR E-mail Capture - Request for Additional Information Related to TMI Fall 2017 Steam Generator Tube Inspection Report ML18212A2712018-07-31031 July 2018 NRR E-mail Capture - Request for Additional Information Related to Amendment Regarding Decommissioning ERO Staffing Changes ML17285B1962017-10-27027 October 2017 Request for Additional Information Regarding Generic Letter 2016-01, Monitoring of Neutron-Absorbing Materials in Spent Fuel Pools. ML17062A4912017-03-0303 March 2017 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Fleet Alternative to RPV Threads in Flange Examination (CAC Nos. MF8712-MF8729) ML16356A4802016-12-21021 December 2016 NRR E-mail Capture - RAIs on TMI License Amendment Request for Approval of Changes to the Three Mile Island Nuclear Station Emergency Plan Related to Staffing ML16337A0072016-12-0101 December 2016 NRR E-mail Capture - Draft RAIs Three Mile Island Nuclear Station, Units 1 and 2, License Amendment Request for Approval of Changes to the Three Mile Island Nuclear Station Emergency Plan Related to Staffing ML16287A4042016-10-11011 October 2016 Notification of Conduct of a Triennial Fire Protection Baseline Inspection ML15230A5332015-08-18018 August 2015 Draft Request for Additional Information ML15020A7372015-03-0808 March 2015 Request for Additional Information Regarding Related to December 22, 2014, Report Submitted Pursuant to 10 CFR 50.46 ML14307A1172014-11-14014 November 2014 Request for Additional Information Regarding Relief Request RR-14-01 Concerning Alternative Root Mean Square Depth Sizing Requirements ML14240A4122014-09-0404 September 2014 Request for Additional Information Regarding License Amendment Request to Eliminate Certain Technical Specification Reporting Requirements (Tac MF0628) ML14134A3222014-05-22022 May 2014 Request for Additional Information Regarding Review of Three Mile Island Nuclear Station Unit 1 Cycle 20 Core Operating Limits Report ML14134A1722014-05-14014 May 2014 Draft RAIs in Support of NRC Staff Review of TMI Cycle 20 COLR ML14052A2592014-02-27027 February 2014 Request for Additional Information Regarding Proposed License Amendment Request to Revise Technical Specification Reporting Requirements ML14030A5832014-01-29029 January 2014 Draft Request for Additional Information Proposed Revision to Technical Specifications Reporting Requirements Exelon Generation Company, LLC Three Mile Island Nuclear Station, Unit 1 ML13266A2852013-10-21021 October 2013 Request for Additional Information on Three Mile Island Nuclear Station Unit 2 - post-shutdown Decommissioning Activities Report ML13276A6492013-10-0303 October 2013 Notification of Conduct of a Triennial Fire Protection Baseline Inspection ML13269A1792013-09-25025 September 2013 Draft Request for Additional Information ML13253A2252013-09-10010 September 2013 Draft Request for Additional Information ML13249A2072013-09-0505 September 2013 Draft Request for Additional Information ML13193A1752013-07-22022 July 2013 Request for Additional Information Regarding Revision to Pressure and Temperature Limit Curves and Exemption Request for Initial Reference Temperature Values ML13196A3382013-07-15015 July 2013 2013 Decommissioning Fund Report RAI ML13193A1452013-07-12012 July 2013 Electronic Transmission, Draft Request for Additional Information Regarding Proposed Revision to Pressure and Temperature Limit Curves and Exemption Request for Initial Reference Temperature Values (TAC Nos. MF0425 & MF0426) ML13176A4702013-06-26026 June 2013 Request for Additional Information Regarding Overall Integrated Plan in Response to Order Number EA-12-051, Reliable Spent Fuel Pool Instrumentation ML13177A3902013-06-26026 June 2013 Electronic Transmission, Draft Request for Additional Information Regarding Overall Integrated Plan in Response to Order Number EA-12-051, Reliable Spent Fuel Pool Instrumentation ML13066A2442013-03-19019 March 2013 Request for Additional Information Regarding Fifth Inservice Test Interval Relief Request PR-01 Nuclear Services Closed Cooling Water Flow Measurement ML13066A1262013-03-0707 March 2013 Electronic Transmission, Draft Request for Additional Information Regarding Fifth Inservice Test Interval Relief Request PR-01 Nuclear Services Closed Cooling Water Flow Measurement ML13044A3212013-03-0505 March 2013 Request for Additional Information Regarding 30-Day Report for Emergency Core Cooling System Model Changes Pursuant to the Requirements of 10 CFR 50.46 ML13045A6432013-02-25025 February 2013 Request for Additional Information Regarding Relief Request VR-01, Associated with the Fifth Inservice Testing Interval ML13051A3852013-02-25025 February 2013 Request for Additional Information Regarding End-of-Interval Relief Request RR-12-01, Pressure Nozzle-to-Head Weld Exams ML13050A6362013-02-20020 February 2013 Draft RAI Memo ML13044A3122013-02-13013 February 2013 Electronic Transmission, Draft Request for Additional Information Regarding 30-Day Report for Emergency Core Cooling System Model Changes Pursuant to the Requirements of 10 CFR 50.46 ML13044A6652013-02-13013 February 2013 Electronic Transmission, Draft Request for Additional Information Regarding Relief Request VR-01, Associated with the Fifth Inservice Testing Interval ML12306A4812012-11-19019 November 2012 Request for Additional Information Regarding 2011 Steam Generator Tube Inspection Report ML12310A1752012-11-13013 November 2012 Request for Additional Information Regarding 30-Day Report for Emergency Core Cooling System Model Changes Pursuant to the Requirements of 10 CFR 50.46 2024-01-11
[Table view] |
Text
Request for Additional Information Related to Three Mile Island Station, Unit 2, Post-Shutdown Decommissioning Activities Report to Possession-Only License No. DPR-73 TMI-2 Solutions, LLC Three Mile Island Nuclear Station, Unit 2 Docket No. 50-320 TMI-2Solutions, LLC (TMI-2S) submitted the Post-Shutdown Decommissioning Activities Report (PSDAR), Revision 5 (ML22306A051) for Three Mile Island Nuclear Power Station, Unit 2 (TMI-2), to the U.S. Nuclear Regulatory Commission (NRC) on October 27, 2022. In this document, TMI-2 Solutions describes major decommissioning activities as occurring in Phase 1b and Phase 2, including demolishing plant structures to nominally three feet below grade (PSDAR Section 3.2). The PSDAR indicates that Phase 2 is expected to be completed in 2037, the year in which license termination is scheduled to occur.
Requirement:
Paragraph 50.82(a)(4)(i) of Title 10 of the Code of Federal Regulations (10 CFR) states that a PSDAR must contain a description of the planned decommissioning activities along with a schedule for their accomplishment, a discussion that provides the reasons for concluding that the environmental impacts associated with site-specific decommissioning activities will be bounded by appropriate previously issued environmental impact statements, and a site specific DCE, including the projected cost of managing irradiated fuel.
In the TMI-2, Decommissioning Fund Status Report (ML23094A116) submitted on March 30, 2023, TMI-2S states:
Due to market conditions as of December 31, 2022, the TMI-2 Funding Analysis (Table II) shows a forecasted delay between Source Term Reduction and Demolition from 2029 to 2045 as a financial mitigation measure for the Nuclear Decommissioning Trust Fund (NDTF).
Thus, based on the March 30, 2023, report, significant portions of TMI-2Ss decommissioning plans, as presented in the PSDAR, appear to be out of date and are in need of revision.
In order to determine if the decommissioning schedule, environmental impacts associated with the site-specific decommissioning activities are bounded, and the site specific DCE is reflective of the change of schedule, the NRC staff is requesting additional information:
RAI-1
Is the description of planned decommissioning activities and the associated schedule accurate given that TMI-2S plans to delay building demolition until 2045. Please provide your plans to update the PSDAR to reflect any change decommissioning method, decommissioning activities, and the schedule. This should also include when TMI-2S plans to move from DECON to SAFSTOR, as the Decommissioning Fund Status Report states there will be a gap between 2029 1
and 2045 before building demolition.
RAI-2
Before NRC staff will evaluate the site specific TMI-2 DCE, please provide an updated site-specific DCE that reflects your change in decommissioning strategy after 2029 and any other changes. Once submitted, the NRC staff will evaluate it for acceptability.
Environmental RAI
RAI-3
PSDAR Section 6.1.14 Cultural, Historic, and Archeological Resources does not reflect the latest information submitted in the January 20, 2023 RAI responses (ML23121A249) and the February 22, 2023 LAR (ML23058A064), that was submitted for review major decommissioning activities, as defined in 10 CFR 50.2, that would diminish the historic integrity (e.g., physical demolition) of the TMI-2 Solutions owned buildings previously deemed eligible for the National Register of Historic Places. Please confirm that this information remains accurate and your plans to update the PSDAR due to the change in major decommissioning activities.