ML20302A295

From kanterella
Revision as of 23:38, 20 January 2022 by StriderTol (talk | contribs) (StriderTol Bot insert)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
3 to Updated Final Safety Analysis Report, Section 17, Quality Assurance Program for Station Operation
ML20302A295
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 09/25/2020
From:
Energy Harbor Nuclear Corp
To:
Office of Nuclear Reactor Regulation
Shared Package
ML20302A348 List:
References
L-20-234
Download: ML20302A295 (2)


Text

Davis-Besse Unit 1 Updated Final Safety Analysis Report SECTION 17 TABLE OF CONTENTS Section Title Page 17.0 QUALITY ASSURANCE PROGRAM FOR STATION OPERATION 17.0-1 17.1 DELETED 17.2 DELETED (Refer to the QAPM) 17-i UFSAR Rev 33 9/2020

Davis-Besse Unit 1 Updated Final Safety Analysis Report SECTION 17 17.0 QUALITY ASSURANCE PROGRAM FOR STATION OPERATION FSAR Section 17.1 described the Quality Assurance Program that was implemented during the design and construction period at the Davis-Besse Plant. This section was deleted from the first update of the Davis-Besse Updated Safety Analysis Report (USAR).

Section 17.2 contained a description of the Toledo Edison Nuclear Quality Assurance Program which had been established by the Toledo Edison Company to provide assurance that the operation of the Davis-Besse Nuclear Power Station Unit No. 1 conformed with applicable regulatory requirements, with the design bases specified in the license application, and with Toledo Edisons policy statement. This section was deleted and replaced by the Quality Assurance Program Manual.

The Quality Assurance Program Manual (QAPM) is incorporated by reference into the Davis-Besse Updated Safety Analysis Report (USAR). The QAPM contains a description of the quality assurance program which has been established to provide assurance that the operation of the Davis-Besse Nuclear Power Station conforms with applicable regulatory requirements and with the design bases specified in the operating license.

17.2 QUALITY ASSURANCE DURING THE OPERATIONS PHASE 17.2.0 DELETED. Refer to the QAPM The remaining section of USAR Section 17.2 (pages 17.2-3 through 17.2-74 and Figures 17.2-1 and 17.2-2) has been deleted.

17.0-1 UFSAR Rev 33 9/2020