PNO-78-004:on 780109,licensee Commenced Reactor Shutdown Following Notification That Installed Electrical Connector Failed Environ Qualification Testing.Licensee Had Planned to Replace Connectors During Main Outage on 780120
ML20249A136
Person / Time
Site: Pilgrim
Issue date: 01/10/1978
From: Blackwood E, Nolan F
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE)
To:
References
PNO-78-004, PNO-78-4, NUDOCS 9806160098
Download: ML20249A136 (1)


Text

_ _ _ _ _ _ _ _ - - _ - _ - _ _ __-__ _-_-__ - __ ____ _ _____ _ __ _ ._

l PRELIMINARY NOTIFICATION (n+ T V

January 10, 1978 PRELIMINARY NOTIFICATION OF EVENT OR UNUSUAL DCCURRENCE--PNO-78-04 l

This preliminary notification constitutes EARLY notice of an event of POSSIBLE safety or-public interest significance. The information presented is as initially received without verification or evaluation and is basically all that is known by IE staff on this date.

Facility: Boston Edison Company Pilgrim Nuclear Power Station, Unit 1 Plymouth, Massachusetts (DN 50-292)

Subject:

PLANT SHUTDOWN DUE TO AN ELECTRICAL CONNECTOR FAILING l ENVIRONMENTAL TEST An installed electrical connector had previously been removed from service and sent to the vendor, Bendix Corporation, Sydney, New York, as a sample for environmental qualification testing. The connector failed the test due. to separation of field applied potting material from the electrical cable insulation. The potting material forms the seal between the cables and the connector. This failure would allow moisture to enter the connector under post loss of coolant accident w~

environmental conditions of high temperature, pressure and humidity. '

f e. The licensee commenced a reactor shutdown at 9:00 p.m., January 9,

t. % . 1978, following notification of test results.

g The licensee had planned to replace connectors of the type tested during

((

a maintenance outage scheduled for January 20, 1978.

Media interest is expected due to the shutdown and attendant reduction of electrical generating capacity in New England during the winter. The h Commonwealth of Massachusetts has been informed. The licensee issued O!

a press release on January 9, 1978. NRC Region I will issue a press 2j release. i l

NRC, Region I (Philadelphia) received initial notification of this occurrence by telephone from the licensee at 5:15 p.m. , January 9,1978.

l

Contact:

EBBlackwood, IE, x38019 FJNolan, IE x28019

$ distribution: TransmittedHSt/2A7) l Chairman Hendrie Commissioner Bradford Commissioner Kennedy S. J. Chilk, SECY 7l Commissioner Gilinsky C. C. Kammerer, CA (For Distribution) e

[ Transmitted: MNBB /Mf} P Bldg tM [7 E. Volgenau, IE L. V. Gossick, EDO E. G. Case, NRR Region 1 /!0D g S. i H. Hanauer, EDO

. , g J. J. Fouchard, PA SS Bldg [ 2 i[f (MAIL)

E pi a.a. R. Hartfield, MIPC C. V. Smith, NMSS R. J. McTiernan, 0IA R. G. Ryan, OSP H. K. Shepar, ELD .v- -

4} R. Minogue, SD PRELIMINARY NOTIFICATION

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ -