Advises That Major Excavation for Containment 1 General Svcs Bldg Complete.Logs & Maps Will Be Available by 751024. Installation of Ground Grid Will Begin 751103 & Mud Mat Pouring Will Begin 751113.Record of 751017 Telcon Encl
ML20198F921
Person / Time
Site: Washington Public Power Supply System
Issue date: 10/16/1975
From: Strand N
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
To: Boyd R
Office of Nuclear Reactor Regulation
Shared Package
ML20198F879 List:
References
CON-WNP-1098 601-75-227, NUDOCS 8605290144
Download: ML20198F921 (2)


Text

-

12 3 Woshington Public Power Suppl System fw ,

A JCINT OPCRATING AGENCY P.Ca. Sea ese 3000 Gao Wassenorers way ftscu6ans. Wasmanc.roN 99333 PosONt (5098 946 9681 October 16, 1975 Docket Nos. 50-460 G01-75-227 E0-513 Mr. Roger Boyd, Acting Director Division of Reactor 1.icensing Office of fluclear Reactor Regulation U. S. Nuclear Regulatory Commission -

Washington, D. C. 20555

Subject:

WPPSS HUCLEAR PROJECTS NOS.1 & 4 W?iP-1 EXCAVATION

Dear Mr. Boyd:

In response to PSAR Question 2.54, the Supply System co.mEtted to notify the Regulatory Staff when major excavations were completed and logs and maps of these excavations were available. The major excavation for the WNP-1 Containment and General Services Building (GSB) is now complete. The logs and maps of these excavations will be available by October 24, 1975.

The installation of the ground grid under the Containment and GSB J will begin about November 3 and the pouring of the Containment and GSB mud mats will begin about November 13, 1975. If the Staff desires l to view the exposed Ringold Formation, they will need to be at the I site before this time. The backfilling around the W:!P-1 Containment

, and GSB will not begin until mid-1976.

We expect the excavation for the WNP-1 spray pond to be completed by November 4,1975, and the logs and maps to be available about two weeks later.

Very truly yours, 8605290144 751022 b N PDR ADOCK 05000460 A PDR N. O. STRAND Assistant Director Generation & Technology cc: CR Bryant - Bonneville Power Administration tillCoxj- fluclear Regulatory Commission JB Knotts - Conner, Hadicek & Knotts EG Uard - Babcock & Wilcox HW Phillips - United Engineers & Constructors

15 WASHINGTON PUBLIC POWER SUPPLY SYSTEM

.'- RF"')RD OF TELEPHONE CONVERSATir Date '10-17-75 Time 4:00 p.m. I } Y

To be confirrned

( ) No F R O fA TO Name A. G. Hosler Name T. H. Cox s uw os. .. , .w Company or Dept. WPPSS company or Dept. NRC SUBJECT (S) OLSCUSSED WflP-1 EXCAVATION REMARKS

'IGSB explained to Tom that on about October 22 backfilling under part of the would begin.

If the Staff visits the site on November 11, they can examine the exposed Ringold Formation under all of the Containment but under only part of the GSB.

Also, the latest schedule for the excava' tion of the spray pond is to have it completed by October 29.

Backfilling would begin immediately after density checks and proof rolling; about is to 2 days.

AGH:km

  • cc: JP Thomas JE Woolsey DD Tillson TH Cox - NRC J. King - UE&C G. Valentenyi 'UE&C