Partial Response to FOIA Request for Three Categories of Documents Re Backfit Rule Published in 850920 Fr.App a & B Documents Available in Pdr.App C Documents Withheld (Ref FOIA Exemption 5).Search for Addl Documents Continuing
Date released: 06/02/2020 Download: ML20140B780


Comments on Draft Addl Improvements Needed in NRC Procedures for Backfitting Changes Into Nuclear Plants. Difficult Backfit Decisions Made W/Objective in Assuring Safe Design,Const & Operation of Plant
ML20140G774
Person / Time
Issue date: 09/13/1985
From: Dircks W
NRC OFFICE OF THE EXECUTIVE DIRECTOR FOR OPERATIONS (EDO)
To: PEACH J D
GENERAL ACCOUNTING OFFICE
References
FOIA-85-759
Download: ML20140G774 (5)
Expresses Pleasure That Backfit Rule Passed & Covers Generic Matters as Well as plant-specific Backfits.Nrc Should Not Waiver in Decision to Put Backfit Rule in Place Substantially as Passed
ML20140E452
Person / Time
Issue date: 08/21/1985
From: Tribble J
YANKEE ATOMIC ELECTRIC CO.
To: PALLADINO N J
NRC COMMISSION (OCM)
References
FOIA-85-759
Download: ML20140E452 (1)
Forwards Draft Gao Rept Entitled, Addl Improvements Needed in NRC Procedures for Backfitting Changes Into Nuclear Plants. Gao Requests NRC Comments by 850913.W/o Encl
ML20140E447
Person / Time
Issue date: 08/15/1985
From: Dircks W
NRC OFFICE OF THE EXECUTIVE DIRECTOR FOR OPERATIONS (EDO)
To: ASSELSTINE, PALLADINO, ROBERTS
NRC COMMISSION (OCM)
References
FOIA-85-759
Download: ML20140E447 (1)
Recommends Commission Specifically Identify & Thoroughly Document Existing Requirements Applicable to Facilities, Thereby Providing Adequate Baseline for Reviewing Proposed Changes,Per Review of Backfit Policy
ML20140E440
Person / Time
Issue date: 03/21/1985
From: Herrington J
ENERGY, DEPT. OF
To: PALLADINO N J
NRC COMMISSION (OCM)
References
FOIA-85-759
Download: ML20140E440 (2)
Forwards J Tourtellotte Rept & EDO Comments on Rept Re NRC Licensing & Backfitting Practices in General & Duquesne Light Co in Particular.Commission Has Not Reviewed Rept. Commission Will Provide Separate Comments.W/O Encl
ML20140E434
Person / Time
Site: Beaver Valley
Issue date: 03/15/1985
From: Kammerer C
NRC OFFICE OF CONGRESSIONAL AFFAIRS (OCA)
To: BROYHILL J T
HOUSE OF REP.
References
FOIA-85-759
Download: ML20140E434 (1)
Forwards J Tourtellotte Rept & EDO Comments on Rept Re NRC Licensing & Backfitting Practices in General & Duquesne Light Co in Particular.Commission Has Not Reviewed Rept. Commission Will Provide Separate Comments.W/O Encl
ML20140E423
Person / Time
Site: Beaver Valley
Issue date: 03/15/1985
From: Kammerer C
NRC OFFICE OF CONGRESSIONAL AFFAIRS (OCA)
To: MOOREHEAD C J
HOUSE OF REP.
References
FOIA-85-759
Download: ML20140E423 (1)
Suggests Asking ACRS for Comments on Backfitting Rule,Policy & Procedures,Per 841017 Ltr
ML20140E404
Person / Time
Issue date: 10/23/1984
From: Asselstine J
NRC COMMISSION (OCM)
To: PALLADINO
NRC COMMISSION (OCM)
References
FOIA-85-759
Download: ML20140E404 (1)
Submits Suggestion on 830622 Memo Setting Forth Commission Interim Backfitting Guidance to Staff Governing Imposition of Backfits Pending Completion of Full Rulemaking.Guidance Should Apply to near-term OL Plants
ML20140E392
Person / Time
Issue date: 06/23/1983
From: Counsil W
NUCLEAR UTILITY BACKFITTING & REFORM GROUP
To: CHILK S J
NRC OFFICE OF THE SECRETARY (SECY)
References
FOIA-85-759
Download: ML20140E392 (2)
Urges Commission to Take Necessary Action to Prepare Proposed Backfitting Rule for Public Comment as Expeditiously as Possible
ML20140E387
Person / Time
Issue date: 06/16/1983
From: Walske C
ATOMIC INDUSTRIAL FORUM
To: PALLADINO N J
NRC COMMISSION (OCM)
References
FOIA-85-759
Download: ML20140E387 (2)
Ack Receipt of 830225 Ltr Re Backfitting.Policy Statement or Internal Memo on Backfitting Needed While Final Rule Being Developed
ML20140E377
Person / Time
Issue date: 03/02/1983
From: Tribble J
YANKEE ATOMIC ELECTRIC CO.
To: PALLADINO N J
NRC COMMISSION (OCM)
References
FOIA-85-759
Download: ML20140E377 (1)
Partial Response to FOIA Request for Three Categories of Documents Re Backfit Rule Published in 850920 Fr.App a & B Documents Available in Pdr.App C Documents Withheld (Ref FOIA Exemption 5).Search for Addl Documents Continuing
ML20140E340
Person / Time
Site: Beaver Valley
Issue date: 02/14/1986
From: Grimsley D
NRC OFFICE OF ADMINISTRATION (ADM)
To: CURRAN D
HARMON & WEISS
References
FOIA-85-759
Download: ML20140E340 (5)
Responds to 830720 Ltr Inquiring Whether Commission Has Any Info Re Specific Instances Where Hearing Process Delayed Nuclear Power Plant Operation or Instances of Unnecessary Backfit Requirements.Answer to Both Inquiries Is No
ML20140B823
Person / Time
Issue date: 09/29/1983
From: Palladino N
NRC COMMISSION (OCM)
To: MITCHELL G J
SENATE
References
FOIA-85-759
Download: ML20140B823 (4)
Comments on Commission Internal Interim Guidance on Backfitting.Guidance Is Not Clear Mandate for More Rigorous & Systematic Analysis of Whether Backfit Needed
ML20140B809
Person / Time
Issue date: 08/24/1983
From: Walske C
ATOMIC INDUSTRIAL FORUM
To: PALLADINO N J
NRC COMMISSION (OCM)
References
FOIA-85-759
Download: ML20140B809 (3)
Forwards C-E 830317 Ltr Re Approach for 5-yr Backfitting Plan.Proposal Outlines Concept for Implementing New Regulatory Requirements on Operating Plants
ML20140B774
Person / Time
Issue date: 05/02/1983
From: Dircks W
NRC OFFICE OF THE EXECUTIVE DIRECTOR FOR OPERATIONS (EDO)
To: AHEARNE, GILINSKY, PALLADINO N
NRC COMMISSION (OCM)
References
FOIA-85-759
Download: ML20140B774 (1)