Forwards List of Weld Overlays & Inconel Butler Welds to Be Inspected During Mar 1985 Outage.Actions to Be Taken During 850331 Outage,Listed.Weld Joints Repaired in Oct 1984 W/No IGSCC Will Not Be Reinspected
ML20102B653
Person / Time
Site: Brunswick Duke Energy icon.png
Issue date: 02/26/1985
From: Cutter A
CAROLINA POWER & LIGHT CO.
To: Vassallo D
Office of Nuclear Reactor Regulation
References
GL-84-11, WLS-85-045, WLS-85-45, NUDOCS 8503040243
Download: ML20102B653 (4)


Text

.

CD&L Carol!na Power & Light Company FEB 2 01985 SERIAL: NLS-85-045 Director of Nuclear Reactor Regulation Attention: Mr. D. B. Vassallo, Chief Operating Reactors Branch No. 2 Division of Licensing United States Nuclear Regulatory Commission Washington, DC 20535 BRUNSWICK STEAM ELECTRIC PLANT, UNIT NO.1 DOCKET NO. 50-325/ LICENSE NO. DPR-71 IGSCC INSPECTIONS

Dear Mr. Vassallo:

In October 1984, Carolina Power & Light Company (CP&L) performed full scope inspections on Brunswick Unit I for intergranular stress corrosion cracking (IGSCC).

These inspections were performed in accordance with NRC Generic Letter No. 84-11 i

dated April 19,1984. The results of these inspections were submitted to you by our i letter dated December 5,1984 (Serial No. NLS-84-502). By letter dated December 6, 1984, the Staff requested that CP&L submit future inspection plans for Brunswick-1 30 days prior to the start of the next refualing outage. The purpose of this letter is to describe these inspection plans and mitigating actions that will be taken for Brunswick-l'.

The following actions will be taken during the Brunswick-1 refueling outage scheduled to start on March 31,1985:

1. The overlay repai:s that were made prior to October 1984 will be re-inspected by i ultrasound (UT). The weld overlays to be inspected are listed in Table 1.

{ 2. Weld number 1-B32-RECIRC-28"-B-12 will be re-inspected and re-evaluated. This

! weld contains an IGSCC indication, but was not repaired.

! 3. The Inconel butter welds listed in Table 2 will be inspected. This is in accordance with recommendations given in IE Notice No. 84-41.

l E 4.

! Induction Heating recirculation system Stress and residualImprovement heat removal (IHSI)

(RHR willsystem be p)erformed weld joints.on selected Industry l accepted methods will be utilized and the welds will be UT inspected af ter treatment. Joint selection will be based on accessibility, geometry, and IGSCC susceptibility.

l D 5 0 P  ; (

411 Fayettevitie Street e P. O. Box 1$51

  • Raleigh. N C 27602

^

Mr. D. B, Vassallo P:ge 2

5. The isolable portion of the Class I 6-inch reactor water cleanup (RWCU) system piping will be replaced with Nuclear Grade materials and long-term corrective action will be taken to fix the RWCU containment penetration.

Due to the short period of time Brunswick-1 will have operated between the October 1984 inspection outage and the upcoming refueling outage (less than four months), the Company does not intend to re-inspect the weld joints that did not have IGSCC indications or those joints that were repaired during the October 1984 outage. The results of the inspections described above, the specific scope of the IHS1 program and a description of any further corrective actions will be submitted prior to Brunswick-1 start-up. The Company is continuing to assess the application of hydrogen water chemistry at Brunswick, as well as other IGSCC control measures.

Should you have any questions regarding this matter please contact Mr. Sherwood R.

Zimmerman at (919) 836-6242.

Yours very truly

[

A. B. Cutter - Vice President Nuclear Engineering & Licensing RWS/ccc (Ill8NLU) cc: Dr. 3 "elson Grace (NRC-Ril)

Mr. D. O. Myers (NRC-BNP)

Mr. M. Grotenhuis (NRC)

TABLE 1 WELD OVERLAYS TO BE INSPECTED DURING MARCH 1985 0UTAGE 1-B32-12"-AR-E2 Riser Pipe to Elbow 1-B3 2-12"-BR-H4 Risec Pipe to Safe-end Extension 1-B32-28"-A-15 Discharge Elbow to Piping 1-B3 2-28"-A-14 Discharge Valve to Elbow 1-B32-28"-B-8 Vaive to Elbow i

I (1118NLU/crs)

e

, TABLE 2 INCONEL BUTTER WELDS TO BE INSPECTED DURING MARCH 1985 OUTACE l-B3 2-RECIRC-28"-B-1 Nozzle to Safe-end Inconel Butter 1-B32-RECIRC-12"-AR-A-6 Nozzle to Safe-end Inconel Butter 1-B3 2-RECIRC-12"-AR-B-6 Nozzle to Safe-end Inconel Butter 1-B32-RECIRC-12"-AR-C-6 Nozzle to Safe-end Inconel Butter 1-B32-RECIRC-12"-AR-D-6 Nozzle to Safe-end Inconel Butter 1-B32-RECIRC-12"-BR-F-6 Nozzle to Safe-end Inconel Butter '

1-B32-RECIRC-12"-BR-C-6 Nozzle to Safe-end Inconel Butter l-B32-RECIRC-12"-BR-H-6 Nozzle to Safe-end Inconel Butter 1-B3 2-RECIRC-12"-B R-K-6 Nozzle to Safe-end Inconel Butter 1-B11-JPI-4"-N8B Nozzle to Safe-end Inconel Butter (Ill8NLU/crs)