Letter Sequence Approval |
---|
|
|
MONTHYEARML0205103442002-02-25025 February 2002 Issuance of Order for Interim Compensatory Security Measures Project stage: Approval ML0205103762002-02-25025 February 2002 Issuance of Order for Interim Safeguards & Security Compensatory Measures Project stage: Approval ML0205103652002-02-25025 February 2002 Issuance of Order for Interim Compensatory Security Measures Project stage: Approval ML0205102472002-02-25025 February 2002 Issuance of Order for Interim Compensatory Security Measures Project stage: Approval ML0213402552002-05-14014 May 2002 Reply to Licensee'S Response to Order for Interim Safeguards and Security Compensatory Measures Project stage: Other ML0212000472002-05-14014 May 2002 Reply to Response to Order for Interim Safeguards and Security Compensatory Measures Project stage: Other ML0224000282002-08-29029 August 2002 Reply to Response to Order for Interim Safeguards and Security Compensatory Measures (Tac No. MB4179) Project stage: Other ML0224604932002-09-10010 September 2002 Response to Security Order for Interim Safeguards & Security Compensatory Measures Project stage: Other 2002-05-14
[Table View] |
|
---|
Category:Letter
MONTHYEARML24009A1152024-01-29029 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L 2023 LLE-0043 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) L-2024-010, Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3)2024-01-25025 January 2024 Point Units 3 and 4, Seabrook, Duane Arnold, and Point Beach Units 1 and 2, Nuclear Property Insurance - 10 CFR 50.54(w)(3) ML24022A0652024-01-22022 January 2024 Senior Reactor and Reactor Operator Initial License Examinations L-2024-003, NextEra Energy Seabrook, LLC - 10 CFR 50.46 - Emergency Core Cooling System LBLOCA 30-Day Report2024-01-11011 January 2024 NextEra Energy Seabrook, LLC - 10 CFR 50.46 - Emergency Core Cooling System LBLOCA 30-Day Report ML23312A1822023-12-22022 December 2023 Issuance of Amendment No. 172 Revision to Cooling Tower Service Water Loop or Cell Requirements L-2023-173, Quality Assurance Topical Report (FPL-1) Revision 30 Update2023-12-15015 December 2023 Quality Assurance Topical Report (FPL-1) Revision 30 Update L-2023-180, Submittal of Changes to the Technical Specification Bases2023-12-13013 December 2023 Submittal of Changes to the Technical Specification Bases L-2023-177, Supplement to Seabrook Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule2023-11-29029 November 2023 Supplement to Seabrook Exemption Request Regarding Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Final Rule L-2023-155, Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-06542023-11-28028 November 2023 Supplement to Response to Request for Additional Information, Revised NextEra Common Emergency Plan, and Revised Site-Specific Emergency Plan Annexes Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, L-2023-160, Part 73 Exemption Request Regarding Enhanced Weapons, Firearms, Background Checks, and Security Event Notifications Final Rule2023-11-16016 November 2023 Part 73 Exemption Request Regarding Enhanced Weapons, Firearms, Background Checks, and Security Event Notifications Final Rule ML23318A0772023-11-14014 November 2023 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000443/2024011 IR 05000443/20234032023-11-0707 November 2023 Security Baseline Inspection Report 05000443/2023403 and Independent Spent Fuel Storage Installation 07200063/2023401 IR 05000443/20230032023-11-0606 November 2023 Integrated Inspection Report 05000443/2023003 IR 05000443/20230102023-10-19019 October 2023 Triennial Fire Protection Inspection Report 05000443/2023010 ML23346A1322023-10-0606 October 2023 Communication from C-10 Research & Education Foundation Regarding NextEra Common Emergency Fleet Plan License Amendment Request and Related Documents Subsequently Published ML23275A0522023-10-0202 October 2023 Requalification Program Inspection IR 05000443/20234012023-09-0808 September 2023 Cybersecurity Inspection Report 05000443/2023401 (Cover Letter Only) IR 05000443/20234202023-09-0505 September 2023 Security Baseline Inspection Report 05000443/2023420 IR 05000443/20230052023-08-31031 August 2023 Updated Inspection Plan for Seabrook Station (Report 05000443/2023005) L-2023-114, Proposed Turkey Point Units 6 and 7; Seabrook Station; Point Beach Units 1 and 2 - Official Service List Update2023-08-17017 August 2023 Proposed Turkey Point Units 6 and 7; Seabrook Station; Point Beach Units 1 and 2 - Official Service List Update IR 05000443/20233022023-08-16016 August 2023 Operator Licensing Retake Examination Report 05000443/2023302 IR 05000443/20230022023-08-0808 August 2023 Integrated Inspection Report 05000443/2023002 L-2023-098, and Point Beach Units 1 and 2 - Response to Request for Additional Information Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 22023-08-0707 August 2023 and Point Beach Units 1 and 2 - Response to Request for Additional Information Regarding License Amendment Request for Common Emergency Plan Consistent with NUREG-0654, Revision 2 ML23201A0872023-08-0303 August 2023 Audit Plan in Support of Review of License Amendment L-2023-104, Preparation and Scheduling of Operator Licensing Examinations2023-08-0303 August 2023 Preparation and Scheduling of Operator Licensing Examinations L-2023-103, Inservice Inspection Examination Report2023-08-0303 August 2023 Inservice Inspection Examination Report ML23192A0782023-07-11011 July 2023 Operator Licensing Retake Examination Approval L-2023-087, Florida Power & Light/Nextera Energy, Results of the Safety Culture Program Effectiveness Review, March 20, 2023 (ADAMS Accession No. ML22340A452)2023-06-29029 June 2023 Florida Power & Light/Nextera Energy, Results of the Safety Culture Program Effectiveness Review, March 20, 2023 (ADAMS Accession No. ML22340A452) SBK-L-23053, Radiological Emergency Plan (Ssrep), Revision 802023-06-22022 June 2023 Radiological Emergency Plan (Ssrep), Revision 80 ML23157A0722023-06-0606 June 2023 Notification of Conduct of a Fire Protection Team Inspection L-2023-074, Addendum to 2021 Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation Ctsfsi) Financial Assurance Update2023-06-0202 June 2023 Addendum to 2021 Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation Ctsfsi) Financial Assurance Update L-2023-071, NextEra Energy Quality Assurance Topical Report (FPL-1) Revision 29 and Florida Power and Light Company Quality Assurance Program Description for 10 CFR Part 52 Licenses (FPL-2) Revision 11, Annual Submittal2023-05-22022 May 2023 NextEra Energy Quality Assurance Topical Report (FPL-1) Revision 29 and Florida Power and Light Company Quality Assurance Program Description for 10 CFR Part 52 Licenses (FPL-2) Revision 11, Annual Submittal IR 05000443/20233012023-05-15015 May 2023 Initial Operator Licensing Examination Report 05000443/2023301 L-2023-064, License Amendment Request 23-01, Revision 1, Update the Period of Applicability (Poa) for the Pressure-Temperature Limits (PTL) and Low Temperature Overpressure Protection (L Top) Curves2023-05-11011 May 2023 License Amendment Request 23-01, Revision 1, Update the Period of Applicability (Poa) for the Pressure-Temperature Limits (PTL) and Low Temperature Overpressure Protection (L Top) Curves IR 05000443/20230012023-05-11011 May 2023 Integrated Inspection Report 05000443/2023001 ML23129A0312023-05-0909 May 2023 Reactor Operator Retake License Examination ML23117A3652023-05-0404 May 2023 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment Request to Remove Period of Applicability from PTL and Low Temperature Over Pressure Protection Curves SBK-L-23044, 2022 Annual Radiological Environmental Operating Report2023-04-28028 April 2023 2022 Annual Radiological Environmental Operating Report SBK-L-23031, 2022 Annual Radioactive Effluent Release Report2023-04-28028 April 2023 2022 Annual Radioactive Effluent Release Report SBK-L-23033, 2022 Annual Environmental Operating Report2023-04-11011 April 2023 2022 Annual Environmental Operating Report L-2023-053, Core Operating Limits Report for Cycle 232023-04-0505 April 2023 Core Operating Limits Report for Cycle 23 ML23088A1522023-03-29029 March 2023 Summary of Meeting Between Nrc/Region I and C-10 - Questions Regarding Seabrook 4Q2022 Inspection Report L-2023-021, Units, 1 and 2, Turkey Point, Units 3 and 4, Seabrook Station and Point Beach, Units 1 and 2 - Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update2023-03-28028 March 2023 Units, 1 and 2, Turkey Point, Units 3 and 4, Seabrook Station and Point Beach, Units 1 and 2 - Decommissioning Funding Status Reports / Independent Spent Fuel Storage Installation (ISFSI) Financial Assurance Update L-2023-028, and Point Beach Units 1 and 2, 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications2023-03-27027 March 2023 and Point Beach Units 1 and 2, 10 CFR 50.46 Annual Reporting of Changes to, or Errors in Emergency Core Cooling System Models or Applications ML23073A1562023-03-23023 March 2023 Relief Request 4RA-22-01, Relief from the Requirements of the ASME Code L-2023-012, License Amendment Request 23-01, Remove Period of Applicability (Poa) from Pressure Temperature Limits (PTL) and Low Temperature Overpressure Protection (L Top) Curves2023-03-15015 March 2023 License Amendment Request 23-01, Remove Period of Applicability (Poa) from Pressure Temperature Limits (PTL) and Low Temperature Overpressure Protection (L Top) Curves L-2023-025, Fleet Relief Request (Frr) 23-01, Proposed Alternative to ASME Section XI Authorizing Implementation of ASME Code Case N-752-12023-03-15015 March 2023 Fleet Relief Request (Frr) 23-01, Proposed Alternative to ASME Section XI Authorizing Implementation of ASME Code Case N-752-1 L-2023-029, and Point Beach Units 1 and 2 Nuclear Property Insurance - 10 CFR 50.54(w)(3)2023-03-10010 March 2023 and Point Beach Units 1 and 2 Nuclear Property Insurance - 10 CFR 50.54(w)(3) L-2023-023, Revised Steam Generator Tube Inspection Report2023-03-0303 March 2023 Revised Steam Generator Tube Inspection Report ML23020A1002023-03-0303 March 2023 OEDO-22-00419 - 2.206 Petition for Seabrook Station Structure Concrete Concerns (EPID L-2022-CRS-0000)- Closure Letter 2024-01-29
[Table view] |
Text
SAFEGUARDS INFORMATION February 25, 2002 Ted C. Feigenbaum Executive Vice President & Chief Nuclear Officer Seabrook, Unit 1 North Atlantic Energy Service Corp.
c/o Mr. James M. Peschel Rt. 1 Lafayette Road Seabrook, NH 03874
SUBJECT:
ISSUANCE OF ORDER FOR INTERIM SAFEGUARDS AND SECURITY COMPENSATORY MEASURES FOR - SEABROOK, UNIT 1
Dear Mr. Feigenbaum:
The U.S. Nuclear Regulatory Commission (NRC) has issued the enclosed Order that modifies the current operating license for your facility to require compliance with the specified interim safeguards and security compensatory measures. The Order applies to all Addressees listed in to the enclosed Order. These interim compensatory measures are listed in (contains Safeguards Information) to the enclosed Order. The Commission recognizes that you have voluntarily and responsibly implemented additional security measures following the events of September 11, 2001, but, in light of the continuing generalized high-level threat environment, the Commission concludes that the security measures should be embodied in an Order, consistent with the established regulatory framework. The Commission has determined that the generalized high-level threat environment requires that the enclosed Order be effective immediately.
These actions are interim and the basis for the Order is the need to take prudent actions to address security requirements in the present generalized high-level threat environment. This Order does not obviate the need for licensees to continue to meet the objectives of Security Level III described in NRC Information Notice 98-35, and maintain the effectiveness of existing security measures taken in response to the events of September 11, 2001. The requirements will remain in effect pending notification from the Commission that a significant change in the threat environment has occurred, or until the Commission determines that other changes are needed following a more comprehensive re-evaluation of current safeguards and security programs.
The enclosed Order calls for responses and actions within specified time frames. Please contact your Licensing Project Manager to facilitate resolution of any issues related to compliance with the requirements in the enclosed Order, or if you have any other questions.
NOTICE: Attachment 2 to the Order (Interim Compensatory Measures) contains "Safeguards Information." Upon separation of Attachment 2 to the Order, this letter, the enclosed Order, and Attachment 1 to the Order (Address List) are "DECONTROLLED."
SAFEGUARDS INFORMATION
T. Feigenbaum The enclosed Order has been forwarded to the Office of the Federal Register for publication.
Sincerely,
/RA/
Samuel J. Collins, Director Office of Nuclear Reactor Regulation Docket No. 50-443
Enclosures:
- 1. Order
- 2. Order Attachment 1 - Address List
- 3. Order Attachment 2 - Interim Compensatory Measures for High Threat Environment (Safeguards Information) cc w/enclosures 1 and 2 only: See next page
Seabrook Station, Unit No. 1 cc:
William J. Quinlan, Esq. Mr. Stephen McGrail, Director Assistant General Counsel ATTN: James Muckerheide Northeast Utilities Service Company Massachusetts Emergency Management Agency P.O. Box 270 400 Worcester Road Hartford, CT 06141-0270 Framingham, MA 01702-5399 Mr. Peter Brann Philip T. McLaughlin, Attorney General Assistant Attorney General Steven M. Houran, Deputy Attorney State House, Station #6 General Augusta, ME 04333 33 Capitol Street Concord, NH 03301 Resident Inspector U.S. Nuclear Regulatory Commission Mr. Woodbury Fogg, Director Seabrook Nuclear Power Station New Hampshire Office of Emergency P.O. Box 1149 Management Seabrook, NH 03874 State Office Park South 107 Pleasant Street Town of Exeter Concord, NH 03301 10 Front Street Exeter, NH 03823 Mr. Daniel G. Roy Nuclear Training Manager Regional Administrator, Region I Seabrook Station U.S. Nuclear Regulatory Commission North Atlantic Energy Service Corp.
475 Allendale Road P.O. Box 300 King of Prussia, PA 19406 Seabrook, NH 03874 Office of the Attorney General Mr. James M. Peschel One Ashburton Place Manager - Regulatory Programs 20th Floor Seabrook Station Boston, MA 02108 North Atlantic Energy Service Corp.
P.O. Box 300 Board of Selectmen Seabrook, NH 03874 Town of Amesbury Town Hall Mr. Gene F. St. Pierre Amesbury, MA 01913 Station Director Seabrook Station Mr. Dan McElhinney North Atlantic Energy Service Corporation Federal Emergency Management Agency P.O. Box 300 Region I Seabrook, NH 03874 J.W. McCormack P.O. &
Courthouse Building, Room 401 Mr. Frank W. Getman, Jr.
Boston, MA 02109 President and Chief Executive Officer BayCorp Holdings, LTD 20 International Drive, Suite 301 Portsmouth, NH 03801-6809
Seabrook Station, Unit No. 1 cc:
Mr. Bruce D. Kenyon President and Chief Executive Officer Northeast Utilities Service Company P.O. Box 270 Hartford, CT 06141-0270 Mr. Steve Allen Polestar Applied Technology, Inc.
77 Franklin Street, Suite 507 Boston, MA 02110
T. Feigenbaum February 25, 2002 The enclosed Order has been forwarded to the Office of the Federal Register for publication.
Sincerely,
/RA/
Samuel J. Collins, Director Office of Nuclear Reactor Regulation Docket No. 50-443
Enclosures:
- 1. Order
- 2. Order Attachment 1 - Address List
- 3. Order Attachment 2 - Interim Compensatory Measures for High Threat Environment (Safeguards Information) cc w/enclosures 1 and 2 only: See next page DISTRIBUTION (with enclosures 1 and 2 only):
PUBLIC SCollins/JJohnson VDricks JShea OGC ACRS SECY GHill (2 copies per docket)
PD1-2 GWunder TClark EAdensam JClifford RidsRgn1MailCenter Accession No. ML020490034 (Package)
Accession No. ML020 (Cover Letter)
Accession No. ML020510635 (Order)
Accession No. ML020520654 (Order Attachment 1 - Address List)
OFFICE DLPM/PM DLPM//LA DLPM/SC DIPM/D NAME REnnis BClayton JClifford BBoger DATE 2/21/02 2/21/02 2/21/02 2/22/02 OFFICE OGC DLPM/D NRR/ADPT NRR/D NAME LChandler JZwolinski BSheron N/A SCollins DATE 2/22/02 2/22/02 2/25/02 OFFICIAL RECORD COPY
CNO Heading The enclosed Order has been forwarded to the Office of the Federal Register for publication.
Sincerely,
/RA/
Samuel J. Collins, Director Office of Nuclear Reactor Regulation Docket No(s).
Enclosures:
- 1. Order
- 2. Order Attachment 1 - Address List
- 3. Order Attachment 2 - Interim Compensatory Measures for High Threat Environment (Safeguards Information) cc w/enclosures 1 and 2 only: See next page DISTRIBUTION (with enclosures 1 and 2 only):
PUBLIC SCollins/JJohnson VDricks JShea OGC ACRS SECY GHill (2 copies per docket)
PD Reading Project Director Section Chief Project Manager Licensing Assistant Region Contact Accession No. ML020520754 (Package)
Accession No. ML020510637 (Cover Letter)
Accession No. ML020510635 (Order)
Accession No. ML020520654 (Order Attachment 1 - Address List)
OFFICE DLPM/PM DLPM//LA DLPM/SC DIPM/D NAME REnnis BClayton JClifford BBoger DATE 2/21/02 2/21/02 2/21/02 2/22/02 OFFICE OGC DLPM/D NRR/ADPT NRR/D NAME LChandler JZwolinski BSheron N/A SCollins DATE 2/22/02 2/22/02 2/25/02 OFFICIAL RECORD COPY