Transmittal of EP-PS-100, Emergency Director/Control Room.
ML033110557
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 10/31/2003
From:
Susquehanna
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
28401 EP-PS-100, Rev 18
Download: ML033110557 (10)


Text

Oct. 31, 2003 Page 1 of 1 MANUAL HARD COPY DISTRIBUTION DOCUMENT TRANSMITTAL 2003-51705 USER INFORMATION: 0 Nam H*R EMPL#:28401 CA#:0363 Address:

Phone#: 4319 TRANSMITTAL INFORMATION:

TO: 1 10/31/2003 LOCATION: DOCUMENT CONTROL DESK FROM: NUCLEAR RECORDS DOCUMENT CONTROL CENTER (NUCSA-2)

THE FOLLOWING CHANGES HAVE OCCURRED TO THE HARDCOPY OR ELECTRONIC MANUAL ASSIGNED TO YOU:

100 - 100 - EMERGENCY DIRECTOR/CONTROL ROOM: EMERGENCY PLAN-POSITION SPECIFIC PROCEDURE REMOVE MANUAL TABLE OF CONTENTS DATE: 10/27/2003 ADD MANUAL TABLE OF CONTENTS DATE: 10/30/2003 CATEGORY: PROCEDURES TYPE: EP ID: EP-PS-100 REPLACE: REV:18 REPLACE: REV:18 REMOVE: PCAF 2003-1643 REV: N/A ADD: PCAF 2003-1643 REV: N/A UPDATES FOR HARD COPY MANUALS WILL BE DISTRIBUTED WITHIN 5 DAYS IN ACCORDANCE WITH DEPARTMENT PROCEDURES. PLEASE MAKE ALL CHANGES AND ACKNOWLEDGE COMPLETE IN YOUR NIMS INBOX UPON RECEIPT OF HARD COPY. FOR ELECTRONIC MANUAL USERS, ELECTRONICALLY REVIEW THE APPROPRIATE DOCUMENTS AND ACKNOWLEDGE COMPLETE IN YOUR NIMS INBOX.

Tab 5 EP-PS-1 00-5 PAR AIRBORNE RELEASES EP ENTERED MONITOR CONDITIONS:

- PLANT STATUSIPROCEDURES

- ONSITE RAD CONDITIONS ASSESSMENT

- STATUS OF RELEASE x

-DOSE PROJECTIONS P PA-1

<MRGENCY BEEN NO~

\ECLARE?

PA-\

YES ARECOMMEND EVACUATIN 2 MROJECTION INDICATINGENS C INE SANDADVISE,

<DOSES OF 21 REM TEDE OR B ES l CTZENS TO TAKE Kl IN 2 5 REM THYROID CDE AT AK ACCORDANCE WITH THE H STANCE OF 2 2 MILT EMERGENCY PLANS.

\A/4PA-5 NO OR UNKNOWN lRECOMMEND EVACUATING l 0-2 MILES AND SHELTERING CONTINUE M D 2-10 MILES AND ADVISE CITIZENS TO BE TO TAKE KlINACCORDANCE WmITH-" ASSSSENT)o THE STATES EMERGENCY PLANS. PA-1 PA-4 1 .PA-# CAN BE USED TO REFER TO PROCEDURE STEPS FOR MORE DETAILED INFORMATION ON THE ACTION TO BE TAKEN.

2. DOSE PROJECTIONS DO NT INCLUDE DOSE ALREADY RECEIVED.
3. TEDE - WHOLE BODY (TEDE) IS THE SUM OF EFFECTIVE DOSE EQUIVALENT RESULTING FROM EXPOSURE TO EXTERNAL SOURCES. THE COMMITTED EFFECTIVE DOSE EQUIVALENT (CEDE) FROM ALL SIGNIFICANT INHALATION PATHWAYS AND THE DOSE DUE TO GROUND DEPOSITION.
4. CDE - COMMITTED DOSE EQUIVALENT TO THE CHILD THYROID.

EP-AD-000-126, Revision 11, Page 1 of 6

Tab5 0 EP-PS-1 00-5 PAR LIQUID RELEASES INDICATIONS OF A POTENTIAL LIQUID RELEASE

- UNISOLABLE RADWASTE TANK RELEASE

- LEAK TO COOUNG TOWER BASIN L- LEAK TO SPRAY POND PL-1 EC Values RADIONUCUDE (IJCmIl)

Co-60 3E' 4

Sr-91 2E ]

Mo-99 2E'6 Te-132 9E6 1-131 1E6 1-133 7E' 1-134 4E-4 1-135 3E6 Cs-134 9E7 .

Cs-136 6E'6 Cs-137 I Em Ba-139 2E 4 Ba-140 BE' Ba-i 41 3E 4 Np-239 2E-6 NOTES:

1. PL-# CAN BE USED TO REFER TO PROCEDURE STEPS FOR MORE DETAILED INFORMATION ON THE ACTION TO BE TAKEN.
2. CALLS TO DANVILLE ARE COURTESY INFORMATION CALLS ONLY.

PROTECTIVE ACTION RECOMMENDATION CALLS MUST BE MADE BY DEPIBRP.

Yes RAD PERSONNEL NOTIFY DEPIBRP FOR DOWNSTREAM USERS TO DIVERT WATER SUPPLY & ESTIMATED TIME OF ARRIVAL OF RELEASE AT DANVILLE PL-9 EP-AD-000-126, Revision 11, Page 2 of 6

Tab 5 EP-PS-1 00-5 PUBLIC PROTECTIVE ACTION RECOMMENDATION GUIDE AIRBORNE RELEASES EL PA-1 MONITOR CONDITIONS FOR PAR APPLICATION The following conditions should be continuously evaluated to determine if a PAR should be implemented or changed:

  • Plant status and prognosis for changes in conditions
  • Onsite radiological conditions
  • Status of actual or potential radioactive releases
  • Offsite dose projections or actual offsite radiological conditions
  • Escalation in Emergency Classification (i.e., General)

(Go to PA-2)

O PA-2 HAS A GENERAL EMERGENCY BEEN DECLARED?

El YES - If a GENERAL EMERGENCY has been declared, a PAR must be made within 15 minutes of the emergency declaration-The PAR requirement is found in NUREG-0654. (Go to PA-3)

El NO- If a GENERAL EMERGENCY has not been declared, continue to monitor plant status, parameter trends, and prognosis for termination or escalation of the event. (Go to PA-1)

Cl PA-3 IS THERE A VALID DOSE PROJECTION INDICATING DOSES OF > 1 REM TEDE OR 2 5 REM CDE CHILD THYROID AT A DISTANCE OF >-2 MILES?

El YES -. If the projected doses at 2 miles are 2 1 REM TEDEorŽ>5 REM CDE child thyroid, then-full evacuation (0-10 miles) is recommended. (Go to PA-5)

El NO/UNKNOWN - (Go to PA-4)

El PA-4 RECOMMEND EVACUATION 0-2 MILES; SHELTER 2-10 MILES AND ADVISE CITIZENS TO TAKE KI IN ACCORDANCE WITH THE STATE'S EMERGENCY PLANS.

Limited Evacuation (0-2 miles) and sheltering is appropriate for events that are significant enough to cause a General Emergency classification and dose projections are low, unknown, or below full evacuation guidelines. A recommendation is also given to the state to advise citizens to take KI in accordance with the state's emergency plans.

El PA-5. EVACUATE 0-10 MILES AND ADVISE CITIZENS TO TAKE Kl IN ACCORDANCE WITH THE STATE'S EMERGENCY PLANS.

Full evacuation of members of the general public is recommended at this point based on the emergency classification and dose projections. A recommendation is also given to the state to advise citizens to take KI in accordance with the state's emergency plans.

EP-AD-000-1 26, Revision 11, Page 3 of 6

Tab 5 EP-PS-1 00-5 LIQUID L PL-1 ENTRY This section is entered when there are indications of a potential unplanned radioactive liquid release.

Indications of potential unplanned releases include:

  • an unisolable radwaste tank release
  • Ieak to spray pond (Go to PL-2) o PL-2 CHEMISTRY/ENVIRONMENTAL SAMPLING DIRECTOR (ESD)

TAKES AND ANALYZES SAMPLE (Go to PL-3)

PL-3 IS THERE AN UNPLANNED RELEASE TO THE RIVER?

0 YES - An unplanned release to the river has occurred when event-related radioactive materials are released to the river that are not controlled by the release methodol6gies described in the QDCM and applicable Chemistry procedures.

(Go to PL-4)

O NO- If there is no unplanned release to the river, then no notifications are required and monitoring should continue.

o PL-4 RAD PERSONNEL NOTIFY DEP/BRP THAT A RELEASE HAS OCCURRED Depending on which facility is activated, the notification to BRP will be made by the RPC (TSC), Dose Assessment Supervisor, or Radiological Liaison at the EOF.

DO NOT MAKE ANY PROTECTIVE ACTION RECOMMENDATIONS AT THIS TIME.

(Go to PL-5)

EP-AD-000-1 26, Revision 11, Page 4 of 6

Tab 5

.EP-PS-1 00-5 LIQUID (COIS'D)

PL-5 IS RELEASE 2 TECHNICAL REQUIREMENTS LIMITS (AT THE RELEASE POINT)?

0 YES- Releases are at or greater than Technical Requirements limits when Chemistry determines that the limits are exceeded based on methodologies described in the ODCM and applicable Chemistry procedures.

(Go to PL-6) 0 NO - If the release is < Technical Requirements limits, then no further notifications are required and monitoring should continue.

O PL-6 RAD PERSONNEL NOTIFY DANVILLE THAT A RELEASE HAS OCCURRED Depending on which facility is activated, the notification to Danville will be made by the RPC (TSC), Dose Assessment Supervisor, or Radiological Liaison at the EOF.

DO NOT MAKE ANY PROTECTIVE ACTION RECOMMENDATIONS AT THIS TIME.

(Go to PL-7) o PL-7 CHEM/FTD EVALUATES RELEASE VERSUS PAGs The results of the sample analysis are compared to the PAGs for radionuclides in drinking water. The analysis calculates the expected concentration at Danville, taking into account the dilution afforded by the river.

PL-8 DOES RELEASE EXCEED PAGs (AT DANVILLE)?

0 YES- If a single isotope exceeds its effluent concentration (EC) value or the sum of EC fractions exceeds 0.85, then a protective action recommendation should be made for downstream water users (e.g.,

Danville) to DIVERT DRINKING WATER supply to a backup supply or terminate user intake until the release has passed.

(Go to PL-9)

O NO- If the PAGs are not exceeded, monitoring should continue and the State should be notified that no PAR for the liquid release is required.

(Go to PL-1 0)

EP-AD-000-126, Revision 11, Page 5 of 6

Tab 5 EP-F:S-l 00-5 LIQUID (CONT'P) 0 PL-9 RAD PERSONNEL NOTIFY DEP/BRP OF PAR Depending on which facility is activated, the PAR notification to DEP/BRP will be made by the RPC (TSC), Dose Assessment Supervisor, or Radiological Liaison at the EOF. The PAR FORM shall be used to document the PAR.

DO NOT COMMUNICATE THE PROTECTIVE ACTION RECOMMENDATION TO DANVILLE. THE DEPIBRP IS RESPONSIBLE FOR THIS COMMUNICATION AND ANY COMMUNICATION TO OTHER DRINKING WATER SUPPLIERS OR WATER USERS.

O PL-10 RAD PERSONNEL NOTIFY DEPNBRP No PAR is required. Depending on- which facility is activated, the RPC (TSC), Dose Assessment Supervisor, or Radiological Liaison at the EOF shall notify DEP/BRP that no PAR is required.

EP-AD-000-1 26, Revision 11, Page 6 of 6

Tab 9 EP-PS-1 00-9 PROTECTIVE ACTION RECOMMENDATION STATE NOTIFICATION FORM El THIS IS A DRILL E THIS IS AN ACTUAL EVENT (This form is to be used to communicate PPL's Protective Action to the senior state official at 717-651-2148.) /

1. This is of the Susquehanna Steam Electric Station.

(Fill in your name)

2. 1am the: E Emergency Director at the Susquehanna SES Control Room El Emergency Director at the Technical Support Center El Recovery Manager at the Emergency Operations Facility
3. I am about to provide a Protective Action Recommendation. Do Lhave the Senior State Official on the line?

Name

4. A General Emergency has been declared as of
5. This declaration was made due to:
6. The PPL'Susquehanna Protective Action Recommendation is:

E] Evacuate 0-10 miles and advise citizens to take KI in accordance with the state's emergency plans.

El Evacuate 0-2 miles and shelter 2-10 miles and advise citizens to take KI in accordance with the state's emergency plans.

El Divert Danville drinking water supply from the Susquehanna River El Evacuate beyond 10 miles (specify distance ) and advise citizens to take KI in accordance with the state's emergency plans.

7. Date/Time:

EP-AD-000-077, Revision 1, Page 1 of 1

Tab9 EP-PS-l 00-9

- Control #_

I EMERGENCY NOTIFICATION REPORT 1.. Call Status: [l THIS IS A DRILL [1 THIS IS AN ACTUAL EVENT

2. This is: at Susquehanna Steam Electric Station.

(Communicator's Name)

My telephone number is: Notification time is:

(Callback telephone number) (Time notification initiated)

2. EMERGENCY CLASSIFICATION:

El UNUSUAL EVENT El SITE AREA EMERGENCY E ALERT L[ GENERAL EMERGENCY El The event has been terminated.

UNIT: El ONE Declaration DATE:

Time:

El Two (Time classification/ (Date classification/

D ONE&TWO termination declared) termination declared)

THIS REPRESENTS AIAN: El INITIAL DECLARATION Li ESCALATION } IN CLASSIFICATION STATUS E No CHANGE

4. The Emergency Action Level (EAL) Number is:_ _ _ _

1

  • For initial declaration, static update, or escalation, BRIEF NON-TECHNICAL DESCRIPTION OF THE EVENT: l
  • provide current classification EAL-number only.

For significant events, or when directed by the ED, RM, or EOFSS, provide a brief description.

For termination, write emeraencv has been terminated.

l

5. THERE IS: :1 No El AN AIRBORNE NON-ROUTINE RADIOLOGICAL RELEASE IN PROGRESS

[] A LIQUID

6. WIND DIRECTION IS FROM: _ WIND SPEED IS: mph.

(Data from 10 meter meteorological tower, available on PICSY.)

7.

Conclusion:

[1 THIS IS A DRILL [I THIS IS AN ACTUAL EVENT APPROVED: Time: Date:

(ED, RM, or EOFSS) (Time form approved) (Date form approved)

EP-AD-000-310, Revision 5, Page 1 of 1

( C( TAB9 EP-PS-10.

( *1 POTASSIUM IODIDE (KI) TRACKING FORM (Recommended dose: I tabletlday = 130 mg)

EST. DATEITIME OF START KI INTAKE KI ISSUED TO: SOCIAL EXPOSURE STOP DOSAGEl SECURITY # . (Tablets)

(NAME)

DATE TIME DATE TIME DATE J TIME

. .- m A.re by:

Approved by:-* Date Emergency Director - or - Recovery Manager EP-AD-000-141, Revision 0, Page 1 of 1, File R36-9