Category:Letter
MONTHYEARML24022A1172024-01-23023 January 2024 Acceptance of Requested Licensing Action Amendment Request to Revise Renewed Facility Operating License and Permanently Defueled Technical Specifications to Support Resumption of Power Operations ML24012A2422024-01-16016 January 2024 Acceptance of Requested Licensing Action License Transfer Request ML23236A0042023-12-27027 December 2023 Issuance of Amendment 274 Re Changes to Perm Defueled Emergency Plan and Perm Defueled Emergency Action Level Scheme ML23355A1242023-12-26026 December 2023 Withdrawal of an Amendment Request Re License Amendment Request to Revise License Condition to Eliminate Cyber Security Plan Requirements ML23192A0772023-12-26026 December 2023 Letter Exemption from the Requirements of 10 CFR 140.11(a)(4) Concerning Offsite Primary and Secondary Liability Insurance ML23191A5222023-12-22022 December 2023 Exemption Letter from the Requirements of 10 CFR 50.54(W)(1) Concerning Onsite Property Damage Insurance (EPID - L-2022-LLE-0032) ML23263A9772023-12-22022 December 2023 Exemption from Certain Emergency Planning Requirements and Related Safety Evaluation ML23354A2602023-12-21021 December 2023 Reference Simulator Inspection Request for Information L-23-019, Proof of Financial Protection 10 CFR 140.152023-12-18018 December 2023 Proof of Financial Protection 10 CFR 140.15 PNP 2023-030, License Amendment Request to Revise Renewed Facility Operating License and Permanently Defueled Technical Specifications to Support Resumption of Power Operations2023-12-14014 December 2023 License Amendment Request to Revise Renewed Facility Operating License and Permanently Defueled Technical Specifications to Support Resumption of Power Operations PNP 2023-035, Withdrawal of License Amendment Request - Revise License Condition to Eliminate Cyber Security Plan Requirements2023-12-12012 December 2023 Withdrawal of License Amendment Request - Revise License Condition to Eliminate Cyber Security Plan Requirements PNP 2023-028, Application for Order Consenting to Transfer of Control of License and Approving Conforming License Amendments2023-12-0606 December 2023 Application for Order Consenting to Transfer of Control of License and Approving Conforming License Amendments L-23-012, Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point2023-11-13013 November 2023 Master Decommissioning Trust Agreement Changes for Indian Point Nuclear Generating Units 1, 2 and 3, Pilgrim Nuclear Power Station, Palisades Nuclear Plant and the Non-Qualified Trust for Big Rock Point ML23291A4402023-11-0303 November 2023 Acceptance of Requested Licensing Action Request for Exemption from 10 CFR 50.82(a)(2) to Support Reauthorization of Power Operations IR 05000255/20230032023-10-0404 October 2023 NRC Inspection Report No. 05000255/2023003(DRSS)-Holtec Decommissioning International, LLC, Palisades Nuclear Plant ML23275A0012023-10-0202 October 2023 Request for Withholding Information from Public Disclosure for Palisades Nuclear Plant PNP 2023-025, Request for Exemption from Certain Termination of License Requirements of 10 CFR 50.822023-09-28028 September 2023 Request for Exemption from Certain Termination of License Requirements of 10 CFR 50.82 PNP 2023-026, Pre-Submittal Meeting Presentation - Palisades Nuclear Plant License Transfer Application to Support Resumption of Power Operations2023-09-28028 September 2023 Pre-Submittal Meeting Presentation - Palisades Nuclear Plant License Transfer Application to Support Resumption of Power Operations PNP 2023-023, Special Report High Range Noble Gas Monitor Inoperable2023-08-0909 August 2023 Special Report High Range Noble Gas Monitor Inoperable ML23215A2302023-08-0303 August 2023 Notice of Organization Change - Chief Nuclear Officer IR 05000255/20230022023-07-19019 July 2023 NRC Inspection Report 05000255/2023002 DRSS-Holtec Decommissioning International, LLC, Palisades Nuclear Plant ML23087A0362023-05-0202 May 2023 PSDAR Review Letter ML23117A2172023-05-0101 May 2023 Safety Evaluation for Quality Assurance Program Manual Reduction in Commitment PNP 2023-018, 2022 Annual Non-Radiological Environmental Operating Report2023-04-25025 April 2023 2022 Annual Non-Radiological Environmental Operating Report L-23-004, HDI Annual Occupational Radiation Exposure Data Reports - 20222023-04-24024 April 2023 HDI Annual Occupational Radiation Exposure Data Reports - 2022 PNP 2023-007, and Big Rock Point, 2022 Annual Radioactive Effluent Release and Waste Disposal Reports2023-04-19019 April 2023 and Big Rock Point, 2022 Annual Radioactive Effluent Release and Waste Disposal Reports PNP 2023-008, 2022 Radiological Environmental Operating Report2023-04-18018 April 2023 2022 Radiological Environmental Operating Report L-23-003, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-31031 March 2023 Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations PNP 2023-002, 6 to Updated Final Safety Analysis Report2023-03-31031 March 2023 6 to Updated Final Safety Analysis Report ML23088A0382023-03-29029 March 2023 Stations 1, 2, & 3, Palisades Nuclear Plant, and Big Rock Point - Nuclear Onsite Property Damage Insurance PNP 2023-006, Report of Changes to Security Plan, Revision 202023-03-29029 March 2023 Report of Changes to Security Plan, Revision 20 PNP 2023-012, Presentation on Regulatory Path to Reauthorize Power Operations2023-03-16016 March 2023 Presentation on Regulatory Path to Reauthorize Power Operations ML23038A0982023-03-15015 March 2023 Request for Withholding Information from Public Disclosure ML23095A0642023-03-14014 March 2023 American Nuclear Insurers, Notice of Cancellation Rescinded PNP 2023-001, Regulatory Path to Reauthorize Power Operations2023-03-13013 March 2023 Regulatory Path to Reauthorize Power Operations PNP 2023-004, Report of Changes to Palisades Nuclear Plant Technical Specification Bases2023-03-0808 March 2023 Report of Changes to Palisades Nuclear Plant Technical Specification Bases PNP 2023-005, Response to Palisades Nuclear Plant - Request for Additional Information Related to the Post-Shutdown Decommissioning Activities Report2023-03-0101 March 2023 Response to Palisades Nuclear Plant - Request for Additional Information Related to the Post-Shutdown Decommissioning Activities Report ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities ML23052A1092023-02-17017 February 2023 FEMA Letter to NRC, Proposed Commission Paper Language for Palisades Nuclear Plant Emergency Plan Decommissioning Exemption Request ML23032A3992023-02-0101 February 2023 Regulatory Path to Reauthorize Power Operations IR 05000255/20220032022-12-28028 December 2022 NRC Inspection Report No. 05000255/2022003(DRSS); 07200007/2022001 (Drss) Holtec Decommissioning International, LLC, Palisades Nuclear Plant L-22-042, Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.152022-12-14014 December 2022 Oyster, Pilgrim, Indian Point, Palisades and Big Rock Point - Proof of Financial Protection 10 CFR 140.15 PNP 2022-037, Report of Changes to Security Plan, Revision 192022-12-14014 December 2022 Report of Changes to Security Plan, Revision 19 ML22321A2852022-11-17017 November 2022 LLC Master Decommissioning Trust Agreement for Palisades Nuclear Plant IR 05000255/20224012022-11-0909 November 2022 Decommissioning Palisades Nuclear Plant - Decommissioning Security Inspection Report 05000255/2022401 PNP 2022-036, Response to Request for Additional Information Regarding License Amendment Request for Proposed Permanently Defueled Emergency Plan and Permanently Defueled Emergency Action Level Scheme2022-11-0808 November 2022 Response to Request for Additional Information Regarding License Amendment Request for Proposed Permanently Defueled Emergency Plan and Permanently Defueled Emergency Action Level Scheme PNP 2022-035, International - Notification of Commitment Cancellations for Remaining Activities Related to Beyond-Design-Basis Seismic Hazard Reevaluations2022-11-0202 November 2022 International - Notification of Commitment Cancellations for Remaining Activities Related to Beyond-Design-Basis Seismic Hazard Reevaluations PNP 2022-024, Request for Exemption from 10 CFR 140.11(a)(4) Concerning Primary and Secondary Liability Insurance2022-10-26026 October 2022 Request for Exemption from 10 CFR 140.11(a)(4) Concerning Primary and Secondary Liability Insurance PNP 2022-026, Request for Exemption from 10 CFR 50.54(w)(1) Concerning Onsite Property Damage Insurance2022-10-26026 October 2022 Request for Exemption from 10 CFR 50.54(w)(1) Concerning Onsite Property Damage Insurance ML22292A2572022-10-25025 October 2022 Permanently Defueled Emergency Plan License Amendment RAI Letter 2024-01-23
[Table view] |
See also: RIS 2003-14
Text
March 2, 2004
Mr. Daniel J. Malone
Site Vice President
Palisades Nuclear Plant
Nuclear Management Company, LLC
27780 Blue Star Memorial Highway
Covert, MI 49043-9530
SUBJECT: PALISADES NUCLEAR PLANT
CONFIRMATION OF INITIAL OPERATOR LICENSE EXAMINATIONS
Dear Mr. Malone:
In a letter dated September 22, 2003, your staff responded to NRC Regulatory Issue Summary
(RIS) 2003-14, "Preparation and Scheduling of Operator Licensing Examinations." An initial
license examination was requested for the weeks of May 23, and May 30, 2005, and another
initial license examination for the weeks of December 4, and December 11, 2006. The
requested examination for May 2005 has been scheduled and a chief examiner assigned to that
examination. The examination requested for December 2006 will be scheduled as we approach
that date.
On-site validation of the examinations will occur at Palisades Nuclear Plant approximately
3 weeks before the examination administration date. In the unlikely event that we are unable
to support the examinations during the scheduled weeks, we will inform you immediately upon
discovery of such conditions and make arrangements to administer the examinations at a
mutually acceptable date.
As indicated in your RIS response letter, your staff will develop the examinations. Please
inform us if the number of candidates decreases below 10 as this will impact the examination
schedule.
A supplementary letter will be sent to the training department approximately 120 days prior to
the initial examination informing them of the chief examiners name. The letter will also outline
examination security expectations, list the materials required by the NRC to conduct the
examination, reconfirm the examination dates, and reconfirm the number of candidates you
have in the training program. If you have any questions concerning this information, please
contact Mr. C. Phillips of my staff at 630-829-9739.
D. Malone -2-
In accordance with 10 CFR 2.790 of the NRCs "Rules of Practice," a copy of this letter will be
available electronically for public inspection in the NRC Public Document Room or from the
Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS
is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public
Electronic Reading Room).
Sincerely,
/RA/
Roger D. Lanksbury, Chief
Operations Branch
Division of Reactor Safety
Docket No. 50-255
License No. DPR-20
cc: J. Cowan, Executive Vice President
and Chief Nuclear Officer
R. Fenech, Senior Vice President, Nuclear
Fossil and Hydro Operations
D. Cooper, Senior Vice President - Group Operations
L. Lahti, Manager, Regulatory Affairs
J. Rogoff, Vice President, Counsel and Secretary,
A. Udrys, Esquire, Consumers Energy Company
S. Wawro, Director of Nuclear Assets, Consumers Energy Company
Supervisor, Covert Township
Office of the Governor
Michigan Department of Environmental Quality -
Waste and Hazardous Materials Division
Michigan Department of Attorney General
D. Malone -2-
In accordance with 10 CFR 2.790 of the NRCs "Rules of Practice," a copy of this letter will be
available electronically for public inspection in the NRC Public Document Room or from the
Publicly Available Records (PARS) component of NRCs document system (ADAMS). ADAMS
is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public
Electronic Reading Room).
Sincerely,
/RA/
Roger D. Lanksbury, Chief
Operations Branch
Division of Reactor Safety
Docket No. 50-255
License No. DPR-20
cc: J. Cowan, Executive Vice President
and Chief Nuclear Officer
R. Fenech, Senior Vice President, Nuclear
Fossil and Hydro Operations
D. Cooper, Senior Vice President - Group Operations
L. Lahti, Manager, Regulatory Affairs
J. Rogoff, Vice President, Counsel and Secretary,
A. Udrys, Esquire, Consumers Energy Company
S. Wawro, Director of Nuclear Assets, Consumers Energy Company
Supervisor, Covert Township
Office of the Governor
Michigan Department of Environmental Quality -
Waste and Hazardous Materials Division
Michigan Department of Attorney General
DOCUMENT NAME: G:\DRS\ML040640781.wpd
To receive a copy of this document, indicate in the box "C" = Copy w/o attach/encl "E" = Copy with attach/encl "N" = No copy
OFFICE RIII:DRS RIII:DRS RIII:DRS
NAME MABies:sd CPhillips RDLanksbury
DATE 02/24/04 02/24/04 03/02/04
OFFICIAL RECORD COPY
D. Malone -3-
ADAMS Distribution:
WDR
DFT
JHE
DCT
RidsNrrDipmIipb
GEG
HBC
JAL3
DRPIII
DRSIII
PLB1
JRK1
M. A. Bies (concurrence copy)