L-05-119, June 2005 Monthly Operating Report for Beaver Valley Power, Units 1 and 2

From kanterella
Revision as of 02:15, 9 December 2019 by StriderTol (talk | contribs) (Created page by program invented by StriderTol)
(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to navigation Jump to search
June 2005 Monthly Operating Report for Beaver Valley Power, Units 1 and 2
ML052010143
Person / Time
Site: Beaver Valley
Issue date: 07/08/2005
From: Pearce L
FirstEnergy Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
GL-97-002, L-05-119
Download: ML052010143 (3)


Text

FENOC Beaver Valley Power Station P. 0. Box 4 Shippingport, PA 15077 L-05-1 19 July 8, 2005 Beaver Valley Power Station Unit 1 - Docket No. 50-334, License No. DPR-66

-Unit-2-*Docket No.-50-412,-License No. NPF-73 -

Monthly Operating Report U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:

In ;.accordance . with NRC Generic Letter 97-02, "Revised Contents of the Monthly Operating Report",' and Unit 1 and 2 Technical Specification 6.9.4, the "Monthly Operating Report" is submitted for Unit 1 and Unit 2 for the month of June, 2005. This information has also been inputted into the INPO Consolidated Data Entry (CDE) System. No regulatory commitments are contained in this submittal.

Respectfully, W. Pearce Vice-President BVPS DTJ/cjg Enclosures cc:-. NRC Regional Office . . .; :l ..

-King of-Prussia, PA,..; ..,.^-.... .'..-. -

.. .. ' '.*b.24

OPERATING DATA REPORT DOCKET NO. 50-334 UNIT NAME Beaver Vallev 1 DATE Uuly-M-00 COMPLETED BY David T. Jones TELEPHONE 724-682-4962 REPORTING PERIC June 2005

1. Design Electrical Rating 835.00
2. Maximum Dependable Capacity (MWe-Net) 821.00 This Month Yr-to-Date Cumulative
3. Number of Hours the Reactor was Critical 720.00 4,343.00 180,506.14
4. Number of Hours Generator On-line 720.00 4,343.00 177,960.14

--- 5.-ReserveShutdownHours__ Ad -- - ---. 0.00--- -0.00 _ _0.00 - _

6. Net Electrical Energy Generated (MWHrs) 598,100.00 3,613,510.00 134,933,429.0 UNIT SHUTDOWNS Type Method of F: Forced Duration - Shutting Cause & Corrective Action No. Date S: Scheduled (Hours) Reason 1 Down 2 Comments NONE.

1 2 Reason: Method:

A Equipment Failure (Explain) 1 Manual B Maintenance or Test 2 Manual Trip/Scram C Refueling 3 Automatic Trip/Scram D Regulatory Restriction 4 Continuation E Operator Training & License Examination 5 Other (Explain)

F Administration G Operational Error (Explain)

H Other (Explain)

SUMMARY

The Unit operated at a nominal value of 100% output for the entire month of June 2005.

Page 1 of 1

OPERATING DATA REPORT DOCKET NO. 50-412 UNIT NAME Beaver Valley2 DATE COMPLETED BY David T. Jones TELEPHONE 724-682-4962 REPORTING PERIC June 2005

1. Design Electrical Rating 836.00
2. Maximum Dependable Capacity (MWe-Net) 831.00 This Month Yr-to-Date Cumulative
3. Number of Hours the Reactor was Critical 720.00 3,766.75 130,159.23
4. Number of Hours Generator On-line 720.00 3,752.17 129,400.55

-_ -_ ---- 5S.--Reserve Shutdown Hours -d .- -O.000 0 __ - 0.0- 0.00 _- .-_-

6. Net Electrical Energy Generated (MWHrs) 593,184.00 2,999,622.00 102,133,852.0 UNIT SHUTDOWNS NONE.

2 Reason: Method:

A Equipment Failure (Explain) 1 Manual B Maintenance or Test 2 Manual Trip/Scram C Refueling 3 Automatic Trip/Scram D Regulatory Restriction 4 Continuation E Operator Training & License Examination 5 Other (Explain)

F Administration G Operational Error (Explain)

H Other (Explain)

SUMMARY

The Unit operated at a nominal value of 100% output for the entire month of June 2005.

Page 1 of 1

Text

FENOC Beaver Valley Power Station P. 0. Box 4 Shippingport, PA 15077 L-05-1 19 July 8, 2005 Beaver Valley Power Station Unit 1 - Docket No. 50-334, License No. DPR-66

-Unit-2-*Docket No.-50-412,-License No. NPF-73 -

Monthly Operating Report U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:

In ;.accordance . with NRC Generic Letter 97-02, "Revised Contents of the Monthly Operating Report",' and Unit 1 and 2 Technical Specification 6.9.4, the "Monthly Operating Report" is submitted for Unit 1 and Unit 2 for the month of June, 2005. This information has also been inputted into the INPO Consolidated Data Entry (CDE) System. No regulatory commitments are contained in this submittal.

Respectfully, W. Pearce Vice-President BVPS DTJ/cjg Enclosures cc:-. NRC Regional Office . . .; :l ..

-King of-Prussia, PA,..; ..,.^-.... .'..-. -

.. .. ' '.*b.24

OPERATING DATA REPORT DOCKET NO. 50-334 UNIT NAME Beaver Vallev 1 DATE Uuly-M-00 COMPLETED BY David T. Jones TELEPHONE 724-682-4962 REPORTING PERIC June 2005

1. Design Electrical Rating 835.00
2. Maximum Dependable Capacity (MWe-Net) 821.00 This Month Yr-to-Date Cumulative
3. Number of Hours the Reactor was Critical 720.00 4,343.00 180,506.14
4. Number of Hours Generator On-line 720.00 4,343.00 177,960.14

--- 5.-ReserveShutdownHours__ Ad -- - ---. 0.00--- -0.00 _ _0.00 - _

6. Net Electrical Energy Generated (MWHrs) 598,100.00 3,613,510.00 134,933,429.0 UNIT SHUTDOWNS Type Method of F: Forced Duration - Shutting Cause & Corrective Action No. Date S: Scheduled (Hours) Reason 1 Down 2 Comments NONE.

1 2 Reason: Method:

A Equipment Failure (Explain) 1 Manual B Maintenance or Test 2 Manual Trip/Scram C Refueling 3 Automatic Trip/Scram D Regulatory Restriction 4 Continuation E Operator Training & License Examination 5 Other (Explain)

F Administration G Operational Error (Explain)

H Other (Explain)

SUMMARY

The Unit operated at a nominal value of 100% output for the entire month of June 2005.

Page 1 of 1

OPERATING DATA REPORT DOCKET NO. 50-412 UNIT NAME Beaver Valley2 DATE COMPLETED BY David T. Jones TELEPHONE 724-682-4962 REPORTING PERIC June 2005

1. Design Electrical Rating 836.00
2. Maximum Dependable Capacity (MWe-Net) 831.00 This Month Yr-to-Date Cumulative
3. Number of Hours the Reactor was Critical 720.00 3,766.75 130,159.23
4. Number of Hours Generator On-line 720.00 3,752.17 129,400.55

-_ -_ ---- 5S.--Reserve Shutdown Hours -d .- -O.000 0 __ - 0.0- 0.00 _- .-_-

6. Net Electrical Energy Generated (MWHrs) 593,184.00 2,999,622.00 102,133,852.0 UNIT SHUTDOWNS NONE.

2 Reason: Method:

A Equipment Failure (Explain) 1 Manual B Maintenance or Test 2 Manual Trip/Scram C Refueling 3 Automatic Trip/Scram D Regulatory Restriction 4 Continuation E Operator Training & License Examination 5 Other (Explain)

F Administration G Operational Error (Explain)

H Other (Explain)

SUMMARY

The Unit operated at a nominal value of 100% output for the entire month of June 2005.

Page 1 of 1