MONTHYEARL-05-125, August 2005 Monthly Operating Report for Beaver Valley Power Station, Units 1 and 22005-09-0909 September 2005 August 2005 Monthly Operating Report for Beaver Valley Power Station, Units 1 and 2 L-05-119, June 2005 Monthly Operating Report for Beaver Valley Power, Units 1 and 22005-07-0808 July 2005 June 2005 Monthly Operating Report for Beaver Valley Power, Units 1 and 2 L-05-105, May 2005 Monthly Operating Report for Beaver Valley Power Station2005-06-0707 June 2005 May 2005 Monthly Operating Report for Beaver Valley Power Station L-05-088, April 2005 Monthly Operating Report for Beaver Valley, Units 1 & 22005-05-0606 May 2005 April 2005 Monthly Operating Report for Beaver Valley, Units 1 & 2 L-05-064, March 2005 Monthly Operating Report for Beaver Valley Power Station2005-04-0808 April 2005 March 2005 Monthly Operating Report for Beaver Valley Power Station L-05-044, February 2005 Monthly Operating Report for Beaver Valley, Units 1 & 22005-03-0707 March 2005 February 2005 Monthly Operating Report for Beaver Valley, Units 1 & 2 L-05-024, January 2005 Monthly Operating Report for Beaver Valley, Units 1 and 22005-02-0808 February 2005 January 2005 Monthly Operating Report for Beaver Valley, Units 1 and 2 L-05-004, December 2004 Monthly Operating Report for Beaver Valley Power Station Units 1 and 22005-01-0707 January 2005 December 2004 Monthly Operating Report for Beaver Valley Power Station Units 1 and 2 L-04-157, November 2004 Monthly Operating Report for Beaver Valley Power Station2004-12-0707 December 2004 November 2004 Monthly Operating Report for Beaver Valley Power Station L-04-137, October, 2004 Monthly Operating Report for Beaver Valley Power Station2004-11-0808 November 2004 October, 2004 Monthly Operating Report for Beaver Valley Power Station L-04-133, September 2004 Monthly Operating Report for Beaver Valley Units 1 and 22004-10-0707 October 2004 September 2004 Monthly Operating Report for Beaver Valley Units 1 and 2 L-04-120, August 2004 Monthly Operating Report for Beaver Valley Power Station, Units 1 & 22004-09-0808 September 2004 August 2004 Monthly Operating Report for Beaver Valley Power Station, Units 1 & 2 L-04-111, July 2004 Monthly Operating Report for Beaver Valley Units 1 and 22004-08-0606 August 2004 July 2004 Monthly Operating Report for Beaver Valley Units 1 and 2 L-04-096, June 2004 Monthly Operating Report for Beaver Valley Power Station, Units 1 & 22004-07-0808 July 2004 June 2004 Monthly Operating Report for Beaver Valley Power Station, Units 1 & 2 L-04-079, May 2004 Monthly Operating Report for Beaver Valley Power Station2004-06-0707 June 2004 May 2004 Monthly Operating Report for Beaver Valley Power Station L-04-063, April 2004 Monthly Operating Report for Beaver Valley, Units 1 and 22004-05-0707 May 2004 April 2004 Monthly Operating Report for Beaver Valley, Units 1 and 2 L-04-052, March 2004 Monthly Operating Report for Beaver Valley, Units 1 & 22004-04-0707 April 2004 March 2004 Monthly Operating Report for Beaver Valley, Units 1 & 2 L-04-031, February 2004 Monthly Operating Report for Beaver Valley, Units 1 and 22004-03-0808 March 2004 February 2004 Monthly Operating Report for Beaver Valley, Units 1 and 2 L-04-014, January 2004 Monthly Operating Report for Beaver Valley, Units 1 and 22004-02-0606 February 2004 January 2004 Monthly Operating Report for Beaver Valley, Units 1 and 2 L-03-201, November 2003 Monthly Operating Report for Beaver Valley Units 1 and 22003-12-0505 December 2003 November 2003 Monthly Operating Report for Beaver Valley Units 1 and 2 L-03-184, October 2003 Monthly Operating Report for Beaver Valley, Units 1 & 22003-11-0707 November 2003 October 2003 Monthly Operating Report for Beaver Valley, Units 1 & 2 L-03-156, September 2003 Monthly Operating Report for Beaver Valley Units 1 and 22003-10-0808 October 2003 September 2003 Monthly Operating Report for Beaver Valley Units 1 and 2 L-03-141, August 2003 Monthly Operating Report for Beaver Valley Units 1 & 22003-09-0808 September 2003 August 2003 Monthly Operating Report for Beaver Valley Units 1 & 2 L-03-121, July 2003 Monthly Operating Report for Beaver Valley, Units 1 & 22003-08-0707 August 2003 July 2003 Monthly Operating Report for Beaver Valley, Units 1 & 2 L-03-107, June 2003 Monthly Operating Report for Beaver Valley, Units 1 & 22003-07-0808 July 2003 June 2003 Monthly Operating Report for Beaver Valley, Units 1 & 2 L-03-096, May 2003 Monthly Operating Report for Beaver Valley, Units 1 & 22003-06-0606 June 2003 May 2003 Monthly Operating Report for Beaver Valley, Units 1 & 2 L-03-077, April 2003 Monthly Operating Report for Beaver Valley, Units 1 and 22003-05-0606 May 2003 April 2003 Monthly Operating Report for Beaver Valley, Units 1 and 2 L-03-058, March 2003 Monthly Operating Report for Beaver Valley Power Station2003-04-0707 April 2003 March 2003 Monthly Operating Report for Beaver Valley Power Station L-03-043, February 2003 Monthly Operating Report for Beaver Valley Power Station, Units 1 & 22003-03-10010 March 2003 February 2003 Monthly Operating Report for Beaver Valley Power Station, Units 1 & 2 L-03-027, January 2003 Monthly Operating Report for Beaver Valley Power Station2003-02-0707 February 2003 January 2003 Monthly Operating Report for Beaver Valley Power Station L-02-116, November 2002 Monthly Operating Report for Beaver Valley Units 1 & 22002-12-0606 December 2002 November 2002 Monthly Operating Report for Beaver Valley Units 1 & 2 L-02-111, October 2002 Monthly Operating Report for Beaver Valley Units 1 & 22002-11-0707 November 2002 October 2002 Monthly Operating Report for Beaver Valley Units 1 & 2 L-02-104, September 2002 Monthly Operating Report for Beaver Valley2002-10-0707 October 2002 September 2002 Monthly Operating Report for Beaver Valley L-02-096, August 2002 Monthly Operating Report for Beaver Valley Units 1 & 22002-09-0606 September 2002 August 2002 Monthly Operating Report for Beaver Valley Units 1 & 2 L-02-085, July 2002 Monthly Operating Report for Beaver Valley Units 1 & 22002-08-0707 August 2002 July 2002 Monthly Operating Report for Beaver Valley Units 1 & 2 L-02-074, June 2002 Monthly Operating Report for Beaver Valley Units 1 & 22002-07-0808 July 2002 June 2002 Monthly Operating Report for Beaver Valley Units 1 & 2 L-02-071, May 2002 Monthly Operating Report for Beaver Valley Units 1 & 22002-06-0707 June 2002 May 2002 Monthly Operating Report for Beaver Valley Units 1 & 2 L-02-056, April 2002 Monthly Operating Report for Beaver Valley Power Station2002-05-0707 May 2002 April 2002 Monthly Operating Report for Beaver Valley Power Station L-02-037, March 2002 Monthly Operating Report for Beaver Valley, Units 1 & 22002-04-0505 April 2002 March 2002 Monthly Operating Report for Beaver Valley, Units 1 & 2 L-02-026, February 2002 Monthly Operating Report for Beaver Valley Units 1 & 22002-03-0707 March 2002 February 2002 Monthly Operating Report for Beaver Valley Units 1 & 2 2005-09-09
[Table view] |
Text
FENOC Beaver Valley Power Station P. 0. Box 4 Shippingport, PA 15077 L-05-1 19 July 8, 2005 Beaver Valley Power Station Unit 1 - Docket No. 50-334, License No. DPR-66
-Unit-2-*Docket No.-50-412,-License No. NPF-73 -
Monthly Operating Report U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:
In ;.accordance . with NRC Generic Letter 97-02, "Revised Contents of the Monthly Operating Report",' and Unit 1 and 2 Technical Specification 6.9.4, the "Monthly Operating Report" is submitted for Unit 1 and Unit 2 for the month of June, 2005. This information has also been inputted into the INPO Consolidated Data Entry (CDE) System. No regulatory commitments are contained in this submittal.
Respectfully, W. Pearce Vice-President BVPS DTJ/cjg Enclosures cc:-. NRC Regional Office . . .; :l ..
-King of-Prussia, PA,..; ..,.^-.... .'..-. -
.. .. ' '.*b.24
OPERATING DATA REPORT DOCKET NO. 50-334 UNIT NAME Beaver Vallev 1 DATE Uuly-M-00 COMPLETED BY David T. Jones TELEPHONE 724-682-4962 REPORTING PERIC June 2005
- 1. Design Electrical Rating 835.00
- 2. Maximum Dependable Capacity (MWe-Net) 821.00 This Month Yr-to-Date Cumulative
- 3. Number of Hours the Reactor was Critical 720.00 4,343.00 180,506.14
- 4. Number of Hours Generator On-line 720.00 4,343.00 177,960.14
--- 5.-ReserveShutdownHours__ Ad -- - ---. 0.00--- -0.00 _ _0.00 - _
- 6. Net Electrical Energy Generated (MWHrs) 598,100.00 3,613,510.00 134,933,429.0 UNIT SHUTDOWNS Type Method of F: Forced Duration - Shutting Cause & Corrective Action No. Date S: Scheduled (Hours) Reason 1 Down 2 Comments NONE.
1 2 Reason: Method:
A Equipment Failure (Explain) 1 Manual B Maintenance or Test 2 Manual Trip/Scram C Refueling 3 Automatic Trip/Scram D Regulatory Restriction 4 Continuation E Operator Training & License Examination 5 Other (Explain)
F Administration G Operational Error (Explain)
H Other (Explain)
SUMMARY
The Unit operated at a nominal value of 100% output for the entire month of June 2005.
Page 1 of 1
OPERATING DATA REPORT DOCKET NO. 50-412 UNIT NAME Beaver Valley2 DATE COMPLETED BY David T. Jones TELEPHONE 724-682-4962 REPORTING PERIC June 2005
- 1. Design Electrical Rating 836.00
- 2. Maximum Dependable Capacity (MWe-Net) 831.00 This Month Yr-to-Date Cumulative
- 3. Number of Hours the Reactor was Critical 720.00 3,766.75 130,159.23
- 4. Number of Hours Generator On-line 720.00 3,752.17 129,400.55
-_ -_ ---- 5S.--Reserve Shutdown Hours -d .- -O.000 0 __ - 0.0- 0.00 _- .-_-
- 6. Net Electrical Energy Generated (MWHrs) 593,184.00 2,999,622.00 102,133,852.0 UNIT SHUTDOWNS NONE.
2 Reason: Method:
A Equipment Failure (Explain) 1 Manual B Maintenance or Test 2 Manual Trip/Scram C Refueling 3 Automatic Trip/Scram D Regulatory Restriction 4 Continuation E Operator Training & License Examination 5 Other (Explain)
F Administration G Operational Error (Explain)
H Other (Explain)
SUMMARY
The Unit operated at a nominal value of 100% output for the entire month of June 2005.
Page 1 of 1
Text
FENOC Beaver Valley Power Station P. 0. Box 4 Shippingport, PA 15077 L-05-1 19 July 8, 2005 Beaver Valley Power Station Unit 1 - Docket No. 50-334, License No. DPR-66
-Unit-2-*Docket No.-50-412,-License No. NPF-73 -
Monthly Operating Report U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:
In ;.accordance . with NRC Generic Letter 97-02, "Revised Contents of the Monthly Operating Report",' and Unit 1 and 2 Technical Specification 6.9.4, the "Monthly Operating Report" is submitted for Unit 1 and Unit 2 for the month of June, 2005. This information has also been inputted into the INPO Consolidated Data Entry (CDE) System. No regulatory commitments are contained in this submittal.
Respectfully, W. Pearce Vice-President BVPS DTJ/cjg Enclosures cc:-. NRC Regional Office . . .; :l ..
-King of-Prussia, PA,..; ..,.^-.... .'..-. -
.. .. ' '.*b.24
OPERATING DATA REPORT DOCKET NO. 50-334 UNIT NAME Beaver Vallev 1 DATE Uuly-M-00 COMPLETED BY David T. Jones TELEPHONE 724-682-4962 REPORTING PERIC June 2005
- 1. Design Electrical Rating 835.00
- 2. Maximum Dependable Capacity (MWe-Net) 821.00 This Month Yr-to-Date Cumulative
- 3. Number of Hours the Reactor was Critical 720.00 4,343.00 180,506.14
- 4. Number of Hours Generator On-line 720.00 4,343.00 177,960.14
--- 5.-ReserveShutdownHours__ Ad -- - ---. 0.00--- -0.00 _ _0.00 - _
- 6. Net Electrical Energy Generated (MWHrs) 598,100.00 3,613,510.00 134,933,429.0 UNIT SHUTDOWNS Type Method of F: Forced Duration - Shutting Cause & Corrective Action No. Date S: Scheduled (Hours) Reason 1 Down 2 Comments NONE.
1 2 Reason: Method:
A Equipment Failure (Explain) 1 Manual B Maintenance or Test 2 Manual Trip/Scram C Refueling 3 Automatic Trip/Scram D Regulatory Restriction 4 Continuation E Operator Training & License Examination 5 Other (Explain)
F Administration G Operational Error (Explain)
H Other (Explain)
SUMMARY
The Unit operated at a nominal value of 100% output for the entire month of June 2005.
Page 1 of 1
OPERATING DATA REPORT DOCKET NO. 50-412 UNIT NAME Beaver Valley2 DATE COMPLETED BY David T. Jones TELEPHONE 724-682-4962 REPORTING PERIC June 2005
- 1. Design Electrical Rating 836.00
- 2. Maximum Dependable Capacity (MWe-Net) 831.00 This Month Yr-to-Date Cumulative
- 3. Number of Hours the Reactor was Critical 720.00 3,766.75 130,159.23
- 4. Number of Hours Generator On-line 720.00 3,752.17 129,400.55
-_ -_ ---- 5S.--Reserve Shutdown Hours -d .- -O.000 0 __ - 0.0- 0.00 _- .-_-
- 6. Net Electrical Energy Generated (MWHrs) 593,184.00 2,999,622.00 102,133,852.0 UNIT SHUTDOWNS NONE.
2 Reason: Method:
A Equipment Failure (Explain) 1 Manual B Maintenance or Test 2 Manual Trip/Scram C Refueling 3 Automatic Trip/Scram D Regulatory Restriction 4 Continuation E Operator Training & License Examination 5 Other (Explain)
F Administration G Operational Error (Explain)
H Other (Explain)
SUMMARY
The Unit operated at a nominal value of 100% output for the entire month of June 2005.
Page 1 of 1