MONTHYEARL-24-254, Cycle 25 Core Operating Limits Report2024-11-15015 November 2024 Cycle 25 Core Operating Limits Report L-24-246, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-10-21021 October 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-24-223, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-09-26026 September 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-24-038, License Amendment Request to Remove the Expired One-Time Action for Valve Leak Repair in Technical Specification (TS) 3.5.2 and to Correct Core Operating Limits Rep Ort (COLR) References2024-09-17017 September 2024 License Amendment Request to Remove the Expired One-Time Action for Valve Leak Repair in Technical Specification (TS) 3.5.2 and to Correct Core Operating Limits Rep Ort (COLR) References L-24-015, Twenty-Ninth Refueling Outage Inservice Inspection Summary Report2024-09-17017 September 2024 Twenty-Ninth Refueling Outage Inservice Inspection Summary Report L-24-188, Submittal of Quality Assurance Program Manual, Revision 302024-08-27027 August 2024 Submittal of Quality Assurance Program Manual, Revision 30 L-24-199, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-08-22022 August 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-24-186, Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule2024-08-15015 August 2024 Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule L-24-182, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-07-23023 July 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-24-161, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-07-19019 July 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-24-014, Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling Svstem Evaluation Models2024-07-16016 July 2024 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling Svstem Evaluation Models L-24-164, BV-2, Post Accident Monitor Report2024-06-27027 June 2024 BV-2, Post Accident Monitor Report L-24-094, Reactor Vessel Surveillance Capsule Withdrawal Schedule2024-06-24024 June 2024 Reactor Vessel Surveillance Capsule Withdrawal Schedule L-24-152, Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations2024-06-17017 June 2024 Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations L-24-021, Cycle 30 Core Operating Limits Report2024-05-23023 May 2024 Cycle 30 Core Operating Limits Report L-24-121, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-05-23023 May 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-24-107, CFR 50.55a Request 1-TYP-5-RRP-l, for Alternative Method of Nondestructive Examination for River Water Outlet Piping Weld Repair2024-05-13013 May 2024 CFR 50.55a Request 1-TYP-5-RRP-l, for Alternative Method of Nondestructive Examination for River Water Outlet Piping Weld Repair L-23-269, Application to Revise Technical Specifications to Adopt TSTF-569, Revision of Response Time Testing Definitions2024-05-0707 May 2024 Application to Revise Technical Specifications to Adopt TSTF-569, Revision of Response Time Testing Definitions L-24-054, Submittal of 2023 Annual Radioactive Effluent Release Report 2023 Annual Radiological Environmental Operating Report and 2023 Annual Environmental Operating Report (Non-Radiological)2024-04-29029 April 2024 Submittal of 2023 Annual Radioactive Effluent Release Report 2023 Annual Radiological Environmental Operating Report and 2023 Annual Environmental Operating Report (Non-Radiological) L-24-089, Emergency Preparedness Plan2024-04-23023 April 2024 Emergency Preparedness Plan L-24-088, Discharge Monitoring Report (NPDES) Permit No. PA0025615 for March 20242024-04-22022 April 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 for March 2024 L-24-082, Withdrawal of Exemption Request2024-04-0303 April 2024 Withdrawal of Exemption Request L-24-013, Annual Notification of Property Insurance Coverage2024-03-26026 March 2024 Annual Notification of Property Insurance Coverage L-24-064, Submittal of Discharge Monitoring Report (NPDES) Permit No. PA00256152024-03-13013 March 2024 Submittal of Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-23-264, Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule2024-02-23023 February 2024 Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule L-24-050, Retrospective Premium Guarantee2024-02-22022 February 2024 Retrospective Premium Guarantee L-23-267, Submittal of Discharge Monitoring Report (Npdes), Permit No. PA00256152023-12-18018 December 2023 Submittal of Discharge Monitoring Report (Npdes), Permit No. PA0025615 L-23-198, Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-0707 December 2023 Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation L-23-229, Request for Additional Information Regarding the Spring 2023 Generic Letter 95-05 Voltage-Based Alternate Repair Criteria and Steam Generator F-Star Reports2023-11-29029 November 2023 Request for Additional Information Regarding the Spring 2023 Generic Letter 95-05 Voltage-Based Alternate Repair Criteria and Steam Generator F-Star Reports L-23-241, Submittal of the Updated Final Safety Analysis Report, Revision 272023-11-29029 November 2023 Submittal of the Updated Final Safety Analysis Report, Revision 27 L-23-247, Discharge Monitoring Report (NPDES) Permit No. PA00256152023-11-17017 November 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-23-227, Discharge Monitoring Report (NPDES) Permit No. PA0025615 for Third Quarter 20232023-10-20020 October 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 for Third Quarter 2023 L-23-208, Submittal of Discharge Monitoring Report Cnpdes), Permit No. PA00256152023-09-14014 September 2023 Submittal of Discharge Monitoring Report Cnpdes), Permit No. PA0025615 L-23-167, Twenty-Third Refueling Outage Inservice Inspection Summary Report2023-09-13013 September 2023 Twenty-Third Refueling Outage Inservice Inspection Summary Report L-23-205, Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-09-12012 September 2023 Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-23-172, Quality Assurance Program Manual2023-08-31031 August 2023 Quality Assurance Program Manual L-23-188, Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-08-0707 August 2023 Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments L-23-179, Submittal of Discharge Monitoring Report, (NPDES) Permit No. PA00256152023-07-18018 July 2023 Submittal of Discharge Monitoring Report, (NPDES) Permit No. PA0025615 L-23-165, Discharge Monitoring Report (NPDES) Permit No. PA00256152023-06-26026 June 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-23-139, Response to Request for Additional Information Regarding Fall 2022 180-Day Steam Generator Tube Inspection Report2023-06-13013 June 2023 Response to Request for Additional Information Regarding Fall 2022 180-Day Steam Generator Tube Inspection Report L-23-065, Annual Financial Report2023-05-22022 May 2023 Annual Financial Report L-23-137, Discharge Monitoring Report (NPDES) Permit No. PA00256152023-05-18018 May 2023 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-23-125, Cycle 24 Core Operating Limits Report2023-05-17017 May 2023 Cycle 24 Core Operating Limits Report L-23-132, Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations2023-05-10010 May 2023 Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations L-23-129, Response to Request for Additional Information for 10 CFR 50.55a Request 2-TYP-4-RV-06 for Alternative Repair Methods for Reactor Pressure Vessel Head Penetrations2023-05-0505 May 2023 Response to Request for Additional Information for 10 CFR 50.55a Request 2-TYP-4-RV-06 for Alternative Repair Methods for Reactor Pressure Vessel Head Penetrations L-23-115, Submittal of 2022 Annual Radioactive Effluent Release Report, 2022 Annual Radiological Environmental Operating Report, and 2022 Annual Environmental Operating Report (Non-Radiological2023-04-27027 April 2023 Submittal of 2022 Annual Radioactive Effluent Release Report, 2022 Annual Radiological Environmental Operating Report, and 2022 Annual Environmental Operating Report (Non-Radiological L-23-126, Discharge Monitoring Report (Npdes), Permit No. PA00256152023-04-22022 April 2023 Discharge Monitoring Report (Npdes), Permit No. PA0025615 L-23-053, 2022 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models2023-04-14014 April 2023 2022 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models L-23-061, Submittal of the Decommissioning Funding Status Reports2023-03-31031 March 2023 Submittal of the Decommissioning Funding Status Reports L-23-058, 180-Day Steam Generator Tube Inspection Report2023-03-27027 March 2023 180-Day Steam Generator Tube Inspection Report 2024-09-26
[Table view] Category:License-Monthly Operating Report
MONTHYEARL-05-125, August 2005 Monthly Operating Report for Beaver Valley Power Station, Units 1 and 22005-09-0909 September 2005 August 2005 Monthly Operating Report for Beaver Valley Power Station, Units 1 and 2 L-05-119, June 2005 Monthly Operating Report for Beaver Valley Power, Units 1 and 22005-07-0808 July 2005 June 2005 Monthly Operating Report for Beaver Valley Power, Units 1 and 2 L-05-105, May 2005 Monthly Operating Report for Beaver Valley Power Station2005-06-0707 June 2005 May 2005 Monthly Operating Report for Beaver Valley Power Station L-05-088, April 2005 Monthly Operating Report for Beaver Valley, Units 1 & 22005-05-0606 May 2005 April 2005 Monthly Operating Report for Beaver Valley, Units 1 & 2 L-05-064, March 2005 Monthly Operating Report for Beaver Valley Power Station2005-04-0808 April 2005 March 2005 Monthly Operating Report for Beaver Valley Power Station L-05-044, February 2005 Monthly Operating Report for Beaver Valley, Units 1 & 22005-03-0707 March 2005 February 2005 Monthly Operating Report for Beaver Valley, Units 1 & 2 L-05-024, January 2005 Monthly Operating Report for Beaver Valley, Units 1 and 22005-02-0808 February 2005 January 2005 Monthly Operating Report for Beaver Valley, Units 1 and 2 L-05-004, December 2004 Monthly Operating Report for Beaver Valley Power Station Units 1 and 22005-01-0707 January 2005 December 2004 Monthly Operating Report for Beaver Valley Power Station Units 1 and 2 L-04-157, November 2004 Monthly Operating Report for Beaver Valley Power Station2004-12-0707 December 2004 November 2004 Monthly Operating Report for Beaver Valley Power Station L-04-137, October, 2004 Monthly Operating Report for Beaver Valley Power Station2004-11-0808 November 2004 October, 2004 Monthly Operating Report for Beaver Valley Power Station L-04-133, September 2004 Monthly Operating Report for Beaver Valley Units 1 and 22004-10-0707 October 2004 September 2004 Monthly Operating Report for Beaver Valley Units 1 and 2 L-04-120, August 2004 Monthly Operating Report for Beaver Valley Power Station, Units 1 & 22004-09-0808 September 2004 August 2004 Monthly Operating Report for Beaver Valley Power Station, Units 1 & 2 L-04-111, July 2004 Monthly Operating Report for Beaver Valley Units 1 and 22004-08-0606 August 2004 July 2004 Monthly Operating Report for Beaver Valley Units 1 and 2 L-04-096, June 2004 Monthly Operating Report for Beaver Valley Power Station, Units 1 & 22004-07-0808 July 2004 June 2004 Monthly Operating Report for Beaver Valley Power Station, Units 1 & 2 L-04-079, May 2004 Monthly Operating Report for Beaver Valley Power Station2004-06-0707 June 2004 May 2004 Monthly Operating Report for Beaver Valley Power Station L-04-063, April 2004 Monthly Operating Report for Beaver Valley, Units 1 and 22004-05-0707 May 2004 April 2004 Monthly Operating Report for Beaver Valley, Units 1 and 2 L-04-052, March 2004 Monthly Operating Report for Beaver Valley, Units 1 & 22004-04-0707 April 2004 March 2004 Monthly Operating Report for Beaver Valley, Units 1 & 2 L-04-031, February 2004 Monthly Operating Report for Beaver Valley, Units 1 and 22004-03-0808 March 2004 February 2004 Monthly Operating Report for Beaver Valley, Units 1 and 2 L-04-014, January 2004 Monthly Operating Report for Beaver Valley, Units 1 and 22004-02-0606 February 2004 January 2004 Monthly Operating Report for Beaver Valley, Units 1 and 2 L-03-201, November 2003 Monthly Operating Report for Beaver Valley Units 1 and 22003-12-0505 December 2003 November 2003 Monthly Operating Report for Beaver Valley Units 1 and 2 L-03-184, October 2003 Monthly Operating Report for Beaver Valley, Units 1 & 22003-11-0707 November 2003 October 2003 Monthly Operating Report for Beaver Valley, Units 1 & 2 L-03-156, September 2003 Monthly Operating Report for Beaver Valley Units 1 and 22003-10-0808 October 2003 September 2003 Monthly Operating Report for Beaver Valley Units 1 and 2 L-03-141, August 2003 Monthly Operating Report for Beaver Valley Units 1 & 22003-09-0808 September 2003 August 2003 Monthly Operating Report for Beaver Valley Units 1 & 2 L-03-121, July 2003 Monthly Operating Report for Beaver Valley, Units 1 & 22003-08-0707 August 2003 July 2003 Monthly Operating Report for Beaver Valley, Units 1 & 2 L-03-107, June 2003 Monthly Operating Report for Beaver Valley, Units 1 & 22003-07-0808 July 2003 June 2003 Monthly Operating Report for Beaver Valley, Units 1 & 2 L-03-096, May 2003 Monthly Operating Report for Beaver Valley, Units 1 & 22003-06-0606 June 2003 May 2003 Monthly Operating Report for Beaver Valley, Units 1 & 2 L-03-077, April 2003 Monthly Operating Report for Beaver Valley, Units 1 and 22003-05-0606 May 2003 April 2003 Monthly Operating Report for Beaver Valley, Units 1 and 2 L-03-058, March 2003 Monthly Operating Report for Beaver Valley Power Station2003-04-0707 April 2003 March 2003 Monthly Operating Report for Beaver Valley Power Station L-03-043, February 2003 Monthly Operating Report for Beaver Valley Power Station, Units 1 & 22003-03-10010 March 2003 February 2003 Monthly Operating Report for Beaver Valley Power Station, Units 1 & 2 L-03-027, January 2003 Monthly Operating Report for Beaver Valley Power Station2003-02-0707 February 2003 January 2003 Monthly Operating Report for Beaver Valley Power Station L-02-116, November 2002 Monthly Operating Report for Beaver Valley Units 1 & 22002-12-0606 December 2002 November 2002 Monthly Operating Report for Beaver Valley Units 1 & 2 L-02-111, October 2002 Monthly Operating Report for Beaver Valley Units 1 & 22002-11-0707 November 2002 October 2002 Monthly Operating Report for Beaver Valley Units 1 & 2 L-02-104, September 2002 Monthly Operating Report for Beaver Valley2002-10-0707 October 2002 September 2002 Monthly Operating Report for Beaver Valley L-02-096, August 2002 Monthly Operating Report for Beaver Valley Units 1 & 22002-09-0606 September 2002 August 2002 Monthly Operating Report for Beaver Valley Units 1 & 2 L-02-085, July 2002 Monthly Operating Report for Beaver Valley Units 1 & 22002-08-0707 August 2002 July 2002 Monthly Operating Report for Beaver Valley Units 1 & 2 L-02-074, June 2002 Monthly Operating Report for Beaver Valley Units 1 & 22002-07-0808 July 2002 June 2002 Monthly Operating Report for Beaver Valley Units 1 & 2 L-02-071, May 2002 Monthly Operating Report for Beaver Valley Units 1 & 22002-06-0707 June 2002 May 2002 Monthly Operating Report for Beaver Valley Units 1 & 2 L-02-056, April 2002 Monthly Operating Report for Beaver Valley Power Station2002-05-0707 May 2002 April 2002 Monthly Operating Report for Beaver Valley Power Station L-02-037, March 2002 Monthly Operating Report for Beaver Valley, Units 1 & 22002-04-0505 April 2002 March 2002 Monthly Operating Report for Beaver Valley, Units 1 & 2 L-02-026, February 2002 Monthly Operating Report for Beaver Valley Units 1 & 22002-03-0707 March 2002 February 2002 Monthly Operating Report for Beaver Valley Units 1 & 2 2005-09-09
[Table view] |
Text
FENOC FIrtEnwgy =1lea1 O. ratgopa Beaver Valley Power Station P. O. Box 4 Shippingport,PA 15077 L-03-027 February 7, 2003 Beaver Valley Power Station Unit I - Docket No. 50-334, License No. DPR-66 Unit 2 - Docket No. 50-412, License No. NPF-73 Monthly Operating Report U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:
In accordance with NRC Generic Letter 97-02, "Revised Contents of the Monthly Operating Report", and Unit 1 and 2 Technical Specification 6.9.4, the "Monthly Operating Report" is submitted for Unit 1 and Unit 2 for the month of January 2003.
Respectfully, M. B.Bezilla7 Vice-President DTJ/cmg Enclosures cc: NRC Regional Office King of Prussia, PA
UNIT SHUTDOWNS DOCKET NO. 50-334 UNIT NAME BVPS Unit #1 DATE February 3, 2003 COMPLETED BY David T. Jones TELEPHONE (724) 682-4962 REPORTING PERIOD: January 2003 (1) Reason (2) Method A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Trip / Scram C - Refueling 3 - Automatic Trip / Scram D - Regulatory Restriction 4 - Continuation E - Operator Training / Ucense Examination 5 - Other (Explain)
F - Administrative G - Operational Error (Explain)
H - Other (Explain)
SUMMARY
The Unit operated at a nominal value of 100% output for the entire report period.
OPERATING DATA REPORT DOCKET NO.: 50-334 UNIT NAME: BVPS UNIT #1 REPORT DATE: 02/03/03 COMPLETED BY: DAVID T. JONES TELEPHONE: (724) 682-4962
"* Notes: Rated thermal power at
- la. REPORTING PERIOD: JANUARY 2003 "* BVPS-I was uprated from 2652 MWt*
835
"* to 2689 MWt on 10/20/01. Net *
- 1. DESIGN ELECTRICAL RATING (Net MWe):
"*MDC was also uprated from *
-2.- 'MAX. DEPENDABLE-CAPACITY (Net MWe): 821
" B810_(We-to-821 MWe._
THIS MONTH YEAR TO DATE CUMULATIVE 3a. HOURS IN REPORTING PERIOD: 744.0 744.0 234528.0
- 3. NO. OF HRS. REACTOR WAS CRITICAL: 744.0 744.0 161335.5
- 4. SERVICE HOURS GENERATOR ON LINE: 744.0 744.0 158856.0
- 5. UNIT RESERVE SHUTDOWN HOURS: 0.0 0.0 0.0
- 6. NET ELECTRICAL ENERGY GEN. (MWH): 624890.0 624890.0 119280897.0
- 7. GROSS ELECT. ENERGY GEN. (MWH): 661080.0 661080.0 127330670.0
- 8. GROSS THERMAL ENERGY GEN. (MWH): 1998176.0 1998176.0 392269485.5
- 9. (M): 100.0 100.0 69.2 UNIT AVAILABILITY FACTOR
- 10. UNIT CAPACITY FACTOR (MDC) (M:) 102.3 102.3 64.6
- 11. UNIT FORCED OUTAGE RATE (%): 0.0 0.0 15.6
UNIT SHUTDOWNS DOCKET NO. 50-412 UNIT NAME BVPS Unit #2 DATE February 3, 2003 COMPLETED BY David T. Jones TELEPHONE (724) 682-4962 REPORTING PERIOD: January 2003 No. Date Type Duration Reason Method of Cause / Corrective Actions (Y/MID) F: Forced (Hours) (1) Shutting S: Scheduled Down (2) Comments NONE.
(1) Reason (2) Method A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Tnp / Scram C - Refueling 3 - Automatic Tnp / Scram D- Regulatory Restnction 4 - Continuation E - Operator Training / Ucense Examination 5 - Other (Explain)
F - Administrative G -Operational Error (Explain)
H - Other (Explain)
SUMMARY
The Unit operated at a nominal value of 100% output for the entire report period.
OPERATING DATA REPORT DOCKET NO.: 50-412 UNIT NAME: BVPS UNIT #2 REPORT DATE: 02/03/03 COMPLETED BY: DAVID T. JONES TELEPHONE: (724) 682-4962
- Notes: Rated thermal power at
- la. REPORTING PERIOD: JANUARY 2003
- BVPS-2 was uprated from 2652 MWt*
- to 2689 Mwt on 10/30/01. Net *
- 1. DESIGN ELECTRICAL RATING (Net MWe): 836
- MDC was also uprated from *
- 2. MAX. DEPENDABLE CAPACITY-(Net MWe): 831 THIS MONTH YEAR TO DATE CUMULATIVE 3a. HOURS IN REPORTING PERIOD: 744.0 744.0 133311.0
- 3. NO. OF HERS . REACTOR WAS CRITICAL: 744.0 744.0 110299.1
- 4. SERVICE HOURS GENERATOR ON LINE: 744.0 744.0 109570.5
- 5. UNIT RESERVE SHUTDOWN HOURS: 0.0 0.0 0.0
- 6. NET ELECTRICAL ENERGY GEN. (MWH): 631089.0 631089.0 85813492.0
- 7. GROSS ELECT. ENERGY GEN. (MWH): 662238.0 662238.0 90694283.0
- 8. GROSS THERMAL ENERGY GEN. (MWH): 1997888.0 1997888.0 276597499.0
- 9. UNIT AVAILABILITY FACTOR (M): 100.0 100.0 82.2
- 10. UNIT CAPACITY FACTOR (MDC) (M): 102.1 102.1 77.5 II. UNIT FORCED OUTAGE RATE (M): 0.0 0.0 9.7
Text
FENOC FIrtEnwgy =1lea1 O. ratgopa Beaver Valley Power Station P. O. Box 4 Shippingport,PA 15077 L-03-027 February 7, 2003 Beaver Valley Power Station Unit I - Docket No. 50-334, License No. DPR-66 Unit 2 - Docket No. 50-412, License No. NPF-73 Monthly Operating Report U. S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 Gentlemen:
In accordance with NRC Generic Letter 97-02, "Revised Contents of the Monthly Operating Report", and Unit 1 and 2 Technical Specification 6.9.4, the "Monthly Operating Report" is submitted for Unit 1 and Unit 2 for the month of January 2003.
Respectfully, M. B.Bezilla7 Vice-President DTJ/cmg Enclosures cc: NRC Regional Office King of Prussia, PA
UNIT SHUTDOWNS DOCKET NO. 50-334 UNIT NAME BVPS Unit #1 DATE February 3, 2003 COMPLETED BY David T. Jones TELEPHONE (724) 682-4962 REPORTING PERIOD: January 2003 (1) Reason (2) Method A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Trip / Scram C - Refueling 3 - Automatic Trip / Scram D - Regulatory Restriction 4 - Continuation E - Operator Training / Ucense Examination 5 - Other (Explain)
F - Administrative G - Operational Error (Explain)
H - Other (Explain)
SUMMARY
The Unit operated at a nominal value of 100% output for the entire report period.
OPERATING DATA REPORT DOCKET NO.: 50-334 UNIT NAME: BVPS UNIT #1 REPORT DATE: 02/03/03 COMPLETED BY: DAVID T. JONES TELEPHONE: (724) 682-4962
"* Notes: Rated thermal power at
- la. REPORTING PERIOD: JANUARY 2003 "* BVPS-I was uprated from 2652 MWt*
835
"* to 2689 MWt on 10/20/01. Net *
- 1. DESIGN ELECTRICAL RATING (Net MWe):
"*MDC was also uprated from *
-2.- 'MAX. DEPENDABLE-CAPACITY (Net MWe): 821
" B810_(We-to-821 MWe._
THIS MONTH YEAR TO DATE CUMULATIVE 3a. HOURS IN REPORTING PERIOD: 744.0 744.0 234528.0
- 3. NO. OF HRS. REACTOR WAS CRITICAL: 744.0 744.0 161335.5
- 4. SERVICE HOURS GENERATOR ON LINE: 744.0 744.0 158856.0
- 5. UNIT RESERVE SHUTDOWN HOURS: 0.0 0.0 0.0
- 6. NET ELECTRICAL ENERGY GEN. (MWH): 624890.0 624890.0 119280897.0
- 7. GROSS ELECT. ENERGY GEN. (MWH): 661080.0 661080.0 127330670.0
- 8. GROSS THERMAL ENERGY GEN. (MWH): 1998176.0 1998176.0 392269485.5
- 9. (M): 100.0 100.0 69.2 UNIT AVAILABILITY FACTOR
- 10. UNIT CAPACITY FACTOR (MDC) (M:) 102.3 102.3 64.6
- 11. UNIT FORCED OUTAGE RATE (%): 0.0 0.0 15.6
UNIT SHUTDOWNS DOCKET NO. 50-412 UNIT NAME BVPS Unit #2 DATE February 3, 2003 COMPLETED BY David T. Jones TELEPHONE (724) 682-4962 REPORTING PERIOD: January 2003 No. Date Type Duration Reason Method of Cause / Corrective Actions (Y/MID) F: Forced (Hours) (1) Shutting S: Scheduled Down (2) Comments NONE.
(1) Reason (2) Method A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Tnp / Scram C - Refueling 3 - Automatic Tnp / Scram D- Regulatory Restnction 4 - Continuation E - Operator Training / Ucense Examination 5 - Other (Explain)
F - Administrative G -Operational Error (Explain)
H - Other (Explain)
SUMMARY
The Unit operated at a nominal value of 100% output for the entire report period.
OPERATING DATA REPORT DOCKET NO.: 50-412 UNIT NAME: BVPS UNIT #2 REPORT DATE: 02/03/03 COMPLETED BY: DAVID T. JONES TELEPHONE: (724) 682-4962
- Notes: Rated thermal power at
- la. REPORTING PERIOD: JANUARY 2003
- BVPS-2 was uprated from 2652 MWt*
- to 2689 Mwt on 10/30/01. Net *
- 1. DESIGN ELECTRICAL RATING (Net MWe): 836
- MDC was also uprated from *
- 2. MAX. DEPENDABLE CAPACITY-(Net MWe): 831 THIS MONTH YEAR TO DATE CUMULATIVE 3a. HOURS IN REPORTING PERIOD: 744.0 744.0 133311.0
- 3. NO. OF HERS . REACTOR WAS CRITICAL: 744.0 744.0 110299.1
- 4. SERVICE HOURS GENERATOR ON LINE: 744.0 744.0 109570.5
- 5. UNIT RESERVE SHUTDOWN HOURS: 0.0 0.0 0.0
- 6. NET ELECTRICAL ENERGY GEN. (MWH): 631089.0 631089.0 85813492.0
- 7. GROSS ELECT. ENERGY GEN. (MWH): 662238.0 662238.0 90694283.0
- 8. GROSS THERMAL ENERGY GEN. (MWH): 1997888.0 1997888.0 276597499.0
- 9. UNIT AVAILABILITY FACTOR (M): 100.0 100.0 82.2
- 10. UNIT CAPACITY FACTOR (MDC) (M): 102.1 102.1 77.5 II. UNIT FORCED OUTAGE RATE (M): 0.0 0.0 9.7