MONTHYEARML20140A2692020-05-19019 May 2020 External Explosion Discussion Conversation Record ML19078A1562019-03-19019 March 2019 Conversation Record with Jim Vanlooven Et Al./Pge and Holtec International Clarification of a Response to a Request for Additional Information the Trojan ISFSI Renewal Application (Conversation Held on 03/06/19, Dkt No. 72-17) ML19078A1542019-03-19019 March 2019 Conversation Record with Mark Tursa Et Al./Pge and Holtec International Provide an Estimated Time Frame for Responding to a Request for Additional Information the Trojan ISFSI Renewal Application (Conv. Held on 03/12/19, Dkt No. 72-17) ML19036A7152019-02-0404 February 2019 Conversation Record with M. Tursa Et Al./Pge and Holtec International Discuss the Draft Financial Request for Additional Information the Trojan ISFSI Renewal Application (Dkt. 72-17 and SNM-2509), Conversation Held on February 4, 2019 ML18108A2092018-04-18018 April 2018 Conversation Record with Mark Tursa Et Al./Portland General Electric, Holtec International (Docket No. 72-0017 and License No. SNM-2509)(Conversation Held on April 18, 2018) ML18108A2082018-04-18018 April 2018 Conversation Record with Mark Tursa Et Al./Portland General Electric, Holtec International (Docket No. 72-0017 and License No. SNM-2509)(Conversation Held on April 12, 2018) 2020-05-19
[Table view] Category:Verbal Comm
MONTHYEARML20140A2692020-05-19019 May 2020 External Explosion Discussion Conversation Record ML19078A1562019-03-19019 March 2019 Conversation Record with Jim Vanlooven Et Al./Pge and Holtec International Clarification of a Response to a Request for Additional Information the Trojan ISFSI Renewal Application (Conversation Held on 03/06/19, Dkt No. 72-17) ML19078A1542019-03-19019 March 2019 Conversation Record with Mark Tursa Et Al./Pge and Holtec International Provide an Estimated Time Frame for Responding to a Request for Additional Information the Trojan ISFSI Renewal Application (Conv. Held on 03/12/19, Dkt No. 72-17) ML19036A7152019-02-0404 February 2019 Conversation Record with M. Tursa Et Al./Pge and Holtec International Discuss the Draft Financial Request for Additional Information the Trojan ISFSI Renewal Application (Dkt. 72-17 and SNM-2509), Conversation Held on February 4, 2019 ML18108A2092018-04-18018 April 2018 Conversation Record with Mark Tursa Et Al./Portland General Electric, Holtec International (Docket No. 72-0017 and License No. SNM-2509)(Conversation Held on April 18, 2018) ML18108A2082018-04-18018 April 2018 Conversation Record with Mark Tursa Et Al./Portland General Electric, Holtec International (Docket No. 72-0017 and License No. SNM-2509)(Conversation Held on April 12, 2018) 2020-05-19
[Table view] |
Text
,.., ..... ./.
NRC FORM 699 ...,.,. ......,._ U.S. NUCLEAR REGULATORY COMMISSION DATE OF SIGNATURE
!¥.
. 4i{ ,ii lt)l (03-2013)
CONVERSATION RECORD NAME OF PERSON(S) CONTACTED OR IN CONTACT WITH YOU DATE OF CONTACT TYPE OF CONVERSATION DE-MAIL Mark Tursa 04/18/2018 E-MAIL ADDRESS TELEPHONE NUMBER 0 TELEPHONE D INCOMING Mark.Tursa@pgn.com 0 OUTGOING ORGANIZATION DOCKET NUMBER(S)
Portland General Electric 72-17 LICENSE NUMBER(S) CONTROL NUMBER(S)
SNM-2509 SUBJECT Follow up phone call to discuss a single draft technical request for additional information (RAls) the Trojan Independent Spent Fuel Storage Installation (ISFSI) renewal application
SUMMARY
A phone call was held between NRC and Portland General Electric (PGE) to discuss a draft technical RA! on the Trojan ISFSI license renewal application. The full set of draft RAls were originally provided to PGE on March 28, 2018 and discussed on 4/12/2018. One RA! discussed on 4/12/2018 remained unclear. NRC staff discussed and decided the unclear portion of the RAI was addressed though the other portion of the RA! that requested information on the potential for aging effects. This follow up phone call communicated the decision to remove the unclear portion of the RAI.
PGE indicated they may transmit the RA! responses in two batches. For some that require less effort, they may target a late June submission. They would target submitting by the end of October for the second batch.
Continue on Page 2 ACTION REQUIRED (IF ANY)
The NRC will issue the final RAI letter to PGE.
Continue on Page 3 NAME OF PERSON DOCUMENTING CONVERSATION Christopher Markley NRC FORM 699 (03-2013)
Page 1 of _1_