MONTHYEARML24170A7312024-07-29029 July 2024 – Exemption from the Requirements of 10 CFR 50.55a(H)(2) Using the Risk-Informed Process for Evaluations Letter ML24170A7342024-07-26026 July 2024 – Exemption from the Requirements of 10 CFR 50.55a(H)(2) Using the Risk-Informed Process for Evaluations ML24170A7352024-07-26026 July 2024 – FRN Exemption from the Requirements of 10 CFR 50.55a(H)(2) Using the Risk-Informed Process for Evaluations ML24067A0372024-03-20020 March 2024 Federal Register Notice - Issuance of Multiple Exemptions Regarding 10 CFR Part 73 - February 2024 ML20177A6452020-07-15015 July 2020 FRN - Notice of Issuance of Multiple Exemptions Regarding Various Parts of 10 CFR Due to COVID-19 Impacts for June 2020 ML20071F7222020-03-24024 March 2020 Gaia Fuel LAR NSHC FRN with SUNSI or SUNSI and SGI ML20079L2702020-03-18018 March 2020 Notice of Consideration of Issuance of Amendment to Renewed Facility Operating License, Proposed No Significant Hazards Consideration Determination, and Opportunity for a Hearing and Order Imposing Procedures ML19238A3692019-09-0303 September 2019 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 09/10/2019 ML19168A0842019-06-26026 June 2019 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 07/02/2019 ML18295A7442018-10-25025 October 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 11/06/18 ML18278A2802018-10-10010 October 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 10/23/2018 NRC-2018-0140, Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 7/17/20182018-07-0505 July 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 7/17/2018 ML18180A2182018-07-0505 July 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 7/17/2018 NRC-2018-0096, Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 22, 20182018-05-14014 May 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 22, 2018 ML18127B7232018-05-14014 May 2018 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 22, 2018 NRC-2017-0238, Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: January 2, 20182017-12-21021 December 2017 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: January 2, 2018 ML17353A1922017-12-21021 December 2017 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: January 2, 2018 ML16271A0922016-09-28028 September 2016 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: October 11, 2016 ML16215A2272016-08-0303 August 2016 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: August 16, 2016 NRC-2016-0161, Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: August 16, 20162016-08-0303 August 2016 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: August 16, 2016 ML16187A2232016-07-18018 July 2016 Federal Register Notice on Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving Proposed No Significant Hazards Considerations and Containing SUNSI and Order Imposing Procedures for Access to SUNSI - Au NRC-2016-0143, Federal Register Notice on Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving Proposed No Significant Hazards Considerations and Containing SUNSI and Order Imposing Procedures for Access to SUNSI2016-07-18018 July 2016 Federal Register Notice on Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving Proposed No Significant Hazards Considerations and Containing SUNSI and Order Imposing Procedures for Access to SUNSI - Au ML16173A0572016-07-11011 July 2016 Notice of Consideration of Issuance of Amendment to Facility Operating License, No Significant Hazards Consideration Determination, Opportunity for Hearing & Order Imposing Procedures for Document Access to Sensitive Unclassified Non-Safeguards Info ML15356A5992015-12-29029 December 2015 Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: January 5, 2016 ML15328A5502015-11-27027 November 2015 Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: December 8, 2015 NRC-2015-0269, Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: December 8, 20152015-11-27027 November 2015 Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: December 8, 2015 ML15218A6252015-08-14014 August 2015 Biweekly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: August 14, 2015 NRC-2015-0165, Application and Amendments to Facility Operating Licenses and Combined Licenses Involving Proposed No Significant Hazards Considerations and Containing Sensitive Unclassified Non-Safeguards Information and Order Imposing Procedures for2015-07-23023 July 2015 Application and Amendments to Facility Operating Licenses and Combined Licenses Involving Proposed No Significant Hazards Considerations and Containing Sensitive Unclassified Non-Safeguards Information and Order Imposing Procedures for Acce ML15188A1632015-07-23023 July 2015 Application and Amendments to Facility Operating Licenses and Combined Licenses Involving Proposed No Significant Hazards Considerations and Containing Sensitive Unclassified Non-Safeguards Information and Order Imposing Procedures for Acce ML15159A6322015-07-0606 July 2015 Letter Approving Direct Transfer of Control of Licenses and Conforming Amendments ML15042A2322015-04-13013 April 2015 Notice of Consideration of Approval of Transfer of Facility Operating License and Conforming Amendment, Opportunity for Hearing ML15022A6532015-01-26026 January 2015 Biweekly Sholly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: February 3, 2015 ML14233A2082014-08-22022 August 2014 Biweekly Sholly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: September 2, 2014 NRC-2014-0193, Biweekly Sholly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: September 2, 20142014-08-22022 August 2014 Biweekly Sholly FRN - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: September 2, 2014 ML14099A2172014-04-28028 April 2014 FRN on Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving Proposed No Significant Hazards Considerations and Containing SUNSI and Order Imposing Procedures for Access to SUNSI ML13225A5572013-08-12012 August 2013 Rescission of Certain Security Orders Concerning Spent Nuclear Fuel in Transit ML13164A2012013-06-13013 June 2013 Correction to Bi-weekly Notice ML12056A0442012-03-12012 March 2012 Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Effective Immediately) - to All Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status NRC-2012-0067, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Effective Immediately) - to All Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status2012-03-12012 March 2012 Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Effective Immediately) - to All Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status ML12025A1622012-02-24024 February 2012 Federal Register Notice - Exemption Regarding Use of M5 Alloy Fuel Rod Cladding NRC-2012-0034, Federal Register Notice - Exemption Regarding Use of M5 Alloy Fuel Rod Cladding2012-02-24024 February 2012 Federal Register Notice - Exemption Regarding Use of M5 Alloy Fuel Rod Cladding ML11313A1622012-02-0606 February 2012 Environmental Assessment and Finding of No Significant Impact ML11313A1632012-02-0606 February 2012 Federal Register Notice, Environmental Assessment and Finding of No Significant Impact ML11255A0572011-12-0202 December 2011 Federal Register Notice - Order Approving Indirect License Transfer NRC-2011-0283, Federal Register Notice - Order Approving Indirect License Transfer2011-12-0202 December 2011 Federal Register Notice - Order Approving Indirect License Transfer NRC-2011-0200, Federal Register Notice - Notice of Consideration2011-08-22022 August 2011 Federal Register Notice - Notice of Consideration ML11221A3772011-08-22022 August 2011 Federal Register Notice - Notice of Consideration ML1122302752011-08-11011 August 2011 Biweekly Sholly Report - Applications and Amendments to Facility Operating Licenses Involving No Significant Hazards Considerations; Fr Publication Date: 8/23/2011 NRC-2011-0187, Biweekly Sholly Report - Applications and Amendments to Facility Operating Licenses Involving No Significant Hazards Considerations; Fr Publication Date: 8/23/20112011-08-11011 August 2011 Biweekly Sholly Report - Applications and Amendments to Facility Operating Licenses Involving No Significant Hazards Considerations; Fr Publication Date: 8/23/2011 NRC-2011-0093, Federal Register Notice, Notice of Withdrawal of Application2011-04-20020 April 2011 Federal Register Notice, Notice of Withdrawal of Application 2024-07-29
[Table view] Category:Exemption from NRC Requirements
MONTHYEARML24170A7312024-07-29029 July 2024 – Exemption from the Requirements of 10 CFR 50.55a(H)(2) Using the Risk-Informed Process for Evaluations Letter ML24170A7342024-07-26026 July 2024 – Exemption from the Requirements of 10 CFR 50.55a(H)(2) Using the Risk-Informed Process for Evaluations ML24170A7352024-07-26026 July 2024 – FRN Exemption from the Requirements of 10 CFR 50.55a(H)(2) Using the Risk-Informed Process for Evaluations ML24067A0372024-03-20020 March 2024 Federal Register Notice - Issuance of Multiple Exemptions Regarding 10 CFR Part 73 - February 2024 ML24032A2632024-02-23023 February 2024 – Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0044 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) RA-23-0008, Request for Exemption from Certain Requirements in 10 CFR 50.55a(h)(2) Using Risk-Informed Process for Evaluations2024-02-0606 February 2024 Request for Exemption from Certain Requirements in 10 CFR 50.55a(h)(2) Using Risk-Informed Process for Evaluations RA-23-0318, Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-0404 December 2023 Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RA-23-0284, RA-23-0284 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-16016 November 2023 RA-23-0284 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML20330A3012020-12-17017 December 2020 Exemption from Annual Force-on-Force Exercise Requirements of 10 CFR Part 73, Appendix B, General Criteria for Security Personnel, Subsection VI.C.3(l)(1) (EPID L-2020-LLE-0180 (COVID-19)) ML20177A6452020-07-15015 July 2020 FRN - Notice of Issuance of Multiple Exemptions Regarding Various Parts of 10 CFR Due to COVID-19 Impacts for June 2020 ML20142A1852020-06-0909 June 2020 Temporary Exemption from Certain Requirements of 10 CFR Part 73, Appendix B, General Criteria for Security Personnel, Section VI ML19254A6202019-09-17017 September 2019 Duke Energy Fleet (Brunswick, Catawba, Robinson, McGuire, Oconee, and Shearon Harris) - Alternative to Use Encoded Phased Array Ultrasonic Examination in Lieu of Radiography ML12025A1612012-02-24024 February 2012 Transmittal Letter - Exemption Regarding Use of M5 Alloy Fuel Rod Cladding NRC-2012-0034, Federal Register Notice - Exemption Regarding Use of M5 Alloy Fuel Rod Cladding2012-02-24024 February 2012 Federal Register Notice - Exemption Regarding Use of M5 Alloy Fuel Rod Cladding ML12025A1622012-02-24024 February 2012 Federal Register Notice - Exemption Regarding Use of M5 Alloy Fuel Rod Cladding NRC-2010-0020, Exemption2010-12-14014 December 2010 Exemption ML1034001702010-12-14014 December 2010 Exemption ML0936209062010-02-24024 February 2010 Exemption from the Requirements of 10 CFR Part 73, Section 73.55 ML0936209082010-02-24024 February 2010 FRN: Shearon Harris Nuclear Power Power Plant, Unit 1 - Exemption 2024-07-29
[Table view] |
Text
[7590-01-P]
NUCLEAR REGULATORY COMMISSION CAROLINA POWER & LIGHT COMPANY SHEARON HARRIS NUCLEAR POWER PLANT, UNIT NO. 1 DOCKET NO. 50-400 EXEMPTION
[NRC-2010-0020]
1.0 BACKGROUND
Carolina Power & Light Company (CP&L, the licensee) is the holder of Renewed Facility Operating License No. NPF-63, which authorizes operation of the Shearon Harris Nuclear Power Plant (HNP), Unit 1. The license provides, among other things, that the facility is subject to all rules, regulations, and orders of the U.S. Nuclear Regulatory Commission (NRC, the Commission) now or hereafter in effect. The facility consists of one pressurized-water reactor located in New Hill, North Carolina.
2.0 REQUEST/ACTION Title 10 of the Code of Federal Regulations (10 CFR) Part 73, Physical protection of plants and materials, Section 73.55, Requirements for physical protection of licensed activities in nuclear power reactors against radiological sabotage, published as a final rule in the Federal Register on March 27, 2009, effective May 26, 2009, with a full implementation date of March 31, 2010, requires licensees to protect, with high assurance, against radiological sabotage by designing and implementing comprehensive site security plans. The amendments to 10 CFR 73.55 published on March 27, 2009 (74 FR 13926), establish and update generically applicable security requirements similar to those previously imposed by Commission orders issued after the terrorist attacks of September 11, 2001, and implemented by licensees. In addition, the amendments to 10 CFR 73.55 include additional requirements to further enhance site security
based upon insights gained from implementation of the post-September 11, 2001, security orders.
By letter dated February 24, 2010 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML093620908), the NRC granted an exemption to the licensee for three specific items subject to the new rule in 10 CFR 73.55, allowing the implementation of these items to be extended until December 15, 2010. The licensee has implemented all other physical security requirements established by this rulemaking prior to March 31, 2010, the required implementation date.
By letter dated September 20, 2010, the licensee requested an exemption in accordance with 10 CFR 73.5, Specific exemptions. Specifically, the licensee requested an extension of the implementation date for one remaining item from December 15, 2010, to November 30, 2011. Portions of the licensees September 20, 2010, letter contain security-related information and, accordingly, a redacted version of this letter is available for public review in the ADAMS No. ML102650191. The licensee requested this exemption to allow an additional extension from the current implementation date granted in the prior exemption to implement one remaining item of the requirements that involves important physical modifications to the HNP, Unit 1 security system. The licensee identified several issues that have delayed the work to this point and impacted the projected schedule, such as the existence of safety-related conduit and dedicated safe shut down equipment of HNP, Unit 1 within the area where important security modifications are planned. These issues were revealed as the design evolved from the conceptual state to a detailed design state and led to a significant increase in the projects complexity and scope of tasks to be performed. The licensee stated that additional time, beyond that previously approved, is needed due the extensive redesign and review effort that was unforeseen at the conceptual design stage. Granting an exemption would allow the
licensee time to complete the necessary security modifications to meet the regulatory requirements.
3.0 DISCUSSION OF PART 73 SCHEDULE EXEMPTION FROM THE MARCH 31, 2010, FULL IMPLEMENTATION DATE Pursuant 10 CFR 73.55(a)(1), By March 31, 2010, each nuclear power reactor licensee, licensed under 10 CFR Part 50, shall implement the requirements of this section through its Commission-approved Physical Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, and Cyber Security Plan referred to collectively hereafter as security plans.
In accordance with 10 CFR 73.5, the Commission may, upon application by any interested person or upon its own initiative, grant exemptions from the requirements of 10 CFR Part 73 when the exemptions are authorized by law, and will not endanger life or property or the common defense and security, and are otherwise in the public interest.
NRC approval of this exemption would allow an additional extension from the implementation date granted under a previous exemption from December 15, 2010, to November 30, 2011, for one remaining item of the three requirements of the final rule. As stated above, 10 CFR 73.5 allows the NRC to grant exemptions from the requirements of 10 CFR 73. The NRC staff has determined that granting of the licensees proposed exemption would not result in a violation of the Atomic Energy Act of 1954, as amended, or the Commissions regulations. Therefore, the exemption is authorized by law.
In the draft final rule provided to the Commission, the NRC staff proposed that the requirements of the new regulation be met within 180 days. The Commission directed a change from 180 days to approximately 1 year for licensees to fully implement the new requirements.
This change was incorporated into the final rule.
As noted in the final rule, the Commission anticipated that licensees would have to conduct site-specific analyses to determine what changes were necessary to implement the
rules requirements, and that changes could be accomplished through a variety of licensing mechanisms, including exemptions. Since issuance of the final rule, the Commission has rejected a request to generically extend the rules compliance date for all operating nuclear power plants, but noted that the Commissions regulations provide mechanisms for individual licensees, with good cause, to apply for relief from the compliance date (
Reference:
June 4, 2009, letter from R. W. Borchardt, NRC, to M. S. Fertel, Nuclear Energy Institute (ADAMS Accession No. ML091410309)). The licensees request for an exemption is, therefore, consistent with the approach set forth by the Commission and discussed in the June 4, 2009, letter.
Shearon Harris Schedule Exemption Request The licensee provided detailed information in its letter dated September 20, 2010, describing the reason and justification for an exemption to extend the implementation date for the one remaining requirement. Additionally, the licensee has provided information regarding the revised scope for projects at HNP, Unit 1 and the impacts on the licensees ability to meet the current implementation date of December 15, 2010. The existence of safety-related conduit and dedicated safe shut down (SSD) equipment of HNP, Unit 1 within the area where important security modifications are planned have delayed the work and impacted the projected schedule.
A direct outside access route to the physical construction area has not been available due to design basis tornado and missile considerations for the safety-related conduits and SSD equipment. The licensee is now pursuing a design solution that will allow both temporary and ultimately permanent direct outside access to the area to ensure that the new plans will meet all regulatory requirements. The extensive redesign and review efforts that were unforeseen at the conceptual design stage need additional time beyond that previously approved. Portions of the September 20, 2010, letter contain security-related information regarding the site security plan, details of specific portions of the regulation from which the licensee seeks exemption,
justification for the additional extension request, a description of the required changes to the physical security systems, and a revised timeline with critical path activities that would enable the licensee to achieve full compliance by November 30, 2011. The timeline provides dates indicating when (1) design activities will be completed and approved, (2) the exterior missile protection plate will be modified for entry, and (3) the new and relocated equipment will be installed and tested.
The site-specific information provided within the HNP exemption request is relative to the requirements from which the licensee requested exemption and demonstrates the need for modification to meet the one specific remaining requirement of 10 CFR 73.55. The proposed implementation schedule depicts the critical activity milestones of the security system upgrades; is consistent with the licensees solution for meeting the requirements; is consistent with the scope of the modifications and the issues and challenges identified; and is consistent with the licensees requested compliance date.
Notwithstanding the proposed schedule exemption for this one remaining requirement, the licensee will continue to be in compliance with all other applicable physical security requirement as described in 10 CFR 73.55 and reflected in its current NRC-approved physical security program. By November 30, 2011, the HNP physical security system will be in full compliance with all of the regulatory requirements of 10 CFR 73.55, as published on March 27, 2009.
4.0 CONCLUSION
FOR PART 73 SCHEDULE EXEMPTION REQUEST The NRC staff has reviewed the licensees submittals and concludes that the licensee has provided adequate justification for its request for an extension of the previously authorized implementation date from December 15, 2010, with regard to one remaining requirement of 10 CFR 73.55, to November 30, 2011. This conclusion is based on the NRC staffs determination that the licensee has made a good faith effort to meet the requirements in a timely manner, has sufficiently described the reason for the unanticipated delays, and has provided an updated
detailed schedule with adequate justification to the additional time requested for the extension.
The long-term benefits that will be realized when the security systems upgrade is complete justify extending the full compliance date with regard to the specific requirements of 10 CFR 73.55 for this particular licensee. The security measures that HNP needs additional time to implement are new requirements imposed by amendments to 10 CFR 73.55, as published on March 27, 2009, and are in addition to those required by the security orders issued in response to the events of September 11, 2001. Accordingly, an exemption from the March 31, 2010, implementation date is authorized by law and will not endanger life or property or the common defense and security, and the Commission hereby grants the requested exemption.
As per the licensee's request and the NRC's regulatory authority to grant an exemption to the March 31, 2010, implementation date for the one item specified in Attachment 1 of the CP&L letter dated September 20, 2010, the licensee is required to implement this one remaining item and be in full compliance with 10 CFR 73.55 by November 30, 2011. In achieving compliance, the licensee is reminded that it is responsible for determining the appropriate licensing mechanism (i.e., 10 CFR 50.54(p) or 10 CFR 50.90) for incorporation of all necessary changes to its security plans.
In accordance with 10 CFR 51.32, Finding of no significant impact, the Commission has previously determined that the granting of this exemption will not have a significant effect on the quality of the human environment (75 FR 77919 dated December 14, 2010).
This exemption is effective upon issuance.
Dated at Rockville, Maryland, this 14th day of December 2010.
FOR THE NUCLEAR REGULATORY COMMISSION
/RA/
Joseph G. Giitter, Director Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation